Question

For the project outlined on the following table, (a) draw a network diagram (arrow or PDM,
as you prefer), and (b) identify the critical path and duration. (c) Identify the task(s) you
would crash and the incremental cost to reduce project duration by (i) one week; (ii) a second
week; (iii) a third week.

Duration (Weeks) Cost (Dollars) Task Follows Task(s) Normal Crash Normal Crash (Start) (Start) A, B B C D uun $500 400 600 $6

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a)

Network Diagram

w > Start End

(b)

Critical path is the path which takes longest time.

We will look at all possible paths and find the critical path with longest completion time. Project duration is same as the completion time for critical path activities

Possible paths are:

A-C-E : 3+5+4=12

B-C-E: 2+5+4 = 11

B-D-E: 2+5+4=11

Hence, the critical path is A-C-E with total project duration of 12 weeks

c)

Now to crash the project, we will first estimate the crash slope for all activities. Activities on critical path will be crashed to reduce over project duration, starting with activities with lowest cost slope and available weeks to crash for each critical activity.

Crash slope = (Crash cost - Normal cost)/ (Normal time - crash time)

We will calculate crash slope as below

Duration (Weeks) Cost (Dollars) Crash slope
Task Normal Crash Normal Crash
A 3 2 500 600 (600-500)/ (3-2)=100
B 2 1 400 450 50
C 5 3 600 750 75
D 5 4 550 640 90
E 4 3 400 550 150

(i) Reduce project duration by one week

Among activities on critical path A-C-E, the lowest cost slope activity is C so first we will crash activity C by 1 week and project duration is reduced to 12-1 = 11 weeks. The cost of crashing is $75

Possible paths are: A-C-E (11), B-C-E (10), B-D-E (11). Two critical paths are A-C-E and B-D-E

(ii) Second week

Next we will crash B with lowest cost slope of 50 which will reduce time for B-D-E to 10 weeks. However to crash overall project duration, we need to crash another activity A-C-E by 1 week. C with lowest cost slope of 75 can be crashed again by one more week.

Hence, we will crash B by 1 week and C by 1 week. Project duration is reduced to 10 weeks. Total cost of crashing is $50+$75 = $125

Possible paths are: A-C-E (10), B-C-E (8), B-D-E (10). Two critical paths are A-C-E and B-D-E

(iii) Third week

Now, next looking at activities D, A and E which can crashed. We will crash E by 1 week which is a common activity among two critical paths. This will optimize the crash cost else we had to crash both D and A by 1 week which will have higher crash cost.

Crash activity E by 1 week to reduce the project duration to 9 weeks. Total crashing cost = $150

Possible paths are: A-C-E (9), B-C-E (7), B-D-E (9). Two critical paths are A-C-E and B-D-E.

Please give thumbs up/ likes if the answer is helpful. Thank you!

Add a comment
Know the answer?
Add Answer to:
For the project outlined on the following table, (a) draw a network diagram (arrow or PDM,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the...

    NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using the convention discussed in the class. (If challenged with drawing tools, you can hand draw, take a picture, and paste...

  • Question 2. (30%) The following table provides the information necessary to construct project network and calculate...

    Question 2. (30%) The following table provides the information necessary to construct project network and calculate a total project cost. In case of activity crash, the information includes crash cost for each activity. Activity Immediate predecessor(s) Activity time (weeks) Normal cost (x1000$) Additional cost for crashing one week (x1000$) Normal After maximum crash A - 16 12 2,000 300 B - 14 9 1,000 160 C A 8 6 500 100 D A 5 4 600 700 E B 4...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max            Crash cost             Activity                           Predecessors          Time (weeks)             Crash*    per week                   A                                none                                    7                          7         N/A                   B                                none                                    3                          2        $500                   C                                A                                       5                          3      $1000                   D                                A, B                                    6                          4      $2000                   E                                 C, D                                    4                          3      $1250                   F                                D                                       3                          2      $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • 1. For the following schedule, Draw the AON network diagram for the project and calculate the...

    1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...

  • Draw the Network Diagram (PDM) Identify All the Paths Through the Network

    1) Draw the network diagram (PDM)2) Identify all the paths through the network3) select the critical path and explain why 4) calculate the standard deviation of the critical path ActivityPrecedenceDurationSDANA62BNA10CNA82DNA41EA, B62FC, D62GE62HE, F20JH10KH92LG113MG113NK, L51PM31QK41

  • Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity...

    Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Predecessor(s) Normal Time Crash Time Normal Cost $400 Crash Cost $700 1600 2000 800 1100 1000 NNW 600 1200 1450 800 800 500 650 400 600 900 1300 F G H1 1000 650 8. Draw the network for this project. (10 points) 9. Please indicate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish on the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT