Imagine US is a startup that offers high-definition 3-D prenatal ultrasounds for high-end customers. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses):
Activity 1: Welcome a patient and explain the procedure. (7 minutes)
Activity 2: Prep the patient (e.g., show them to the room, apply ultrasound gel). (3 minutes)
Activity 3: Take images. (14 minutes)
Activity 4: Analyze images. (9 minutes)
Activity 5: Discuss diagnostic with patient. (23 minutes)
They have three workers. Suppose they are to assign activities to workers such a. that each activity is assigned to only one worker and each worker must be assigned consecutive tasks. What would be the maximum capacity of this process (patients per hour)?
Suppose tasks are assigned to three workers and now workers are able to do
b. multiple tasks and their assigned tasks do not need to be consecutive. What would be the maximum capacity of this process (patients per hour)?

Question a)
Conditions are
1. Each activity should be assigned to only one worker
2. Each worker must assign consecutive tasks
then work assigned to each worker as below
| WORKER | ASSIGNED | TIME |
| W1 | A1 | 7 |
| W1 | A2 | 3 |
| W2 | A3 | 14 |
| W3 | A4 | 9 |
| W3 | A5 | 23 |
| TOTAL | 56 |
Activity 1 and 2 capacity = 10 minutes
Activity 3 and 4 capacity = 23 minutes
Activity 5 = 23 minutes
Maximum capacity = 60/23 = 2.61 patients per hour
Question b
Conditions-
1. Workers can do multiple task
2. Assigned task do not needto be consecutive. That is it can be consecutive also.
If so each worker can attend each patient at a time. then
| W1 | W2 | W3 | ||||
| Start | Stop | Start | Stop | Start | Stop | |
| A1 | 0 | 7 | 0 | 7 | 0 | 7 |
| A2 | 7 | 10 | 7 | 10 | 7 | 10 |
| A3 | 10 | 24 | 10 | 24 | 10 | 24 |
| A4 | 24 | 33 | 24 | 33 | 24 | 33 |
| A5 | 33 | 56 | 33 | 56 | 33 | 56 |
If one worker is there then he could complete the job in 56 minutes.
Capacity = 60/56 = 1.07patients per hour
Now there three workers
capacity = 1.07 x 3 = 3.21 patients per hour
As per above given instruction the the job sequence should be as below

Question a)
Conditions are
1. Each activity should be assigned to only one worker
2. Each worker must assign consecutive tasks
then work assigned to each worker as below
| WORKER | ASSIGNED | TIME |
| W1 | A1 | 7 |
| W1 | A2 | 3 |
| W2 | A3 | 14 |
| W3 | A4 | 9 |
| W3 | A5 | 23 |
| TOTAL | 56 |
Total time for attending one patient = 56 min
Maximum capacity = 60/56 = 1.07 patients per hour
Question b
Conditions-
1. Workers can do multiple task
2. Assigned task do not needto be consecutive. That is it can be consecutive also.
If so each worker can attend each patient at a time. then
| W1 | W2 | W3 | ||||
| Start | Stop | Start | Stop | Start | Stop | |
| A1 | 0 | 7 | 0 | 7 | 0 | 7 |
| A2 | 7 | 10 | 7 | 10 | 7 | 10 |
| A3 | 10 | 24 | 10 | 24 | 10 | 24 |
| A4 | 24 | 33 | 24 | 33 | 24 | 33 |
| A5 | 33 | 56 | 33 | 56 | 33 | 56 |
If one worker is there then he could complete the job in 56 minutes.
Capacity = 60/56 = 1.07patients per hour
Now there three workers
capacity = 1.07 x 3 = 3.21 patients per hour
Imagine US is a startup that offers high-definition 3-D prenatal ultrasounds for high-end customers. The service...
The White Tooth Device Company is a manufacturer of high-end electric toothbrushes. For each toothbrush, there are a sequence of assembly steps performed by five workers. Each worker does two tasks. Workers are paid $15 per hour. Worker Task Time (seconds) A T1 40 A T2 25 B T3 20 B T4 15 C T5 10 C T6 15 D T7 10 D T8 20 E T9 25 E T10 35 Instruction: Round "cost of direct labor" and "average labor...
Mr. K’s is a very popular hair salon. It offers high-quality
hairstyling and physical relaxation services at a reasonable price,
so it always has unlimited demand. The service process includes
five activities that are conducted in the sequence described next
(the time required for each activity is shown in parentheses):
Activity 1: Welcome a guest and offer homemade herb tea (12
minutes).
Activity 2: Wash and condition hair (12 minutes).
Activity 3: Neck, shoulder, and back stress-release massage (12
minutes)....
The White Tooth Device Company is a manufacturer of high-end electric toothbrushes. For each toothbrush, there are a sequence of assembly steps performed by five workers. Each worker does two tasks. Workers are paid $24 per hour. Time (seconds) Task Worker T1 A 51 A T2 44 В тЗ 10 В T4 13 C Т5 29 C T6 14 T7 20 D T8 17 Е T9 44 Е T10 38 Instruction: Round "cost of direct labor" and "average labor utilization"...
Mr. K’s is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described next (the time required for each activity is shown in parentheses): Activity 1: Welcome a guest and offer homemade herb tea (11 minutes). Activity 2: Wash and condition hair (11 minutes). Activity 3: Neck, shoulder, and back stress-release massage (11 minutes)....
PA 4-4 (Algo) Mr. K's is a very popular hair salon. It... Mr. K's is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described next (the time required for each activity is shown in parentheses): Activity 1: Welcome a guest and offer homemade herb tea (9 minutes). Activity 2: Wash and condition hair...
Samson & Me is a very popular hair salon. It offers high-quality hair-styling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes these activities that are conducted in the sequence described below. (The time required for each activity is shown in parenthesis): Activity 1: Welcome a guest and offer homemade herb tea. (8 minutes) Activity 2: Wash and condition hair. (10 minutes) Activity 3: Design the hairstyle and style the hair....
QUESTION 4 Mr. K's is a very popular hair salon. It offers high-quality hair styling and physical relaxabon services at a reasonable price, so I always has unlimited demand. The service process includes five activities that are conducted in the sequence described below. The time required for each activity is shown in parenthesis Activity 1: Welcome a guest and offer homemade herb tea (10 minutes) Activity 2: Wash and condition hair (10 minutes) Activity 3: Neck, shoulder and back stress...
Mr.K's Hair Salon (Q1-Q10) Mr.K's is a hair salon whose service process includes six activities conducted in the sequence described below. (The time required for each activity is shown in parentheses): Activity 1: Welcome guests and serve herb tea. (10 minutes) Activity 2: Offer styling suggestions. (15 minutes) Activity 3: Condition hair. (10 minutes) Activity 4: Do the hair. (30 minutes) Activity 5: Wash hair. (10 minutes) Activity 6: Check out the guest. (5 minutes) Three servers (S1, S2, and...
Mr. K's is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parenthesis):Activity 1: Welcome a guest and offer homemade herb tea. (10 minutes)Activity 2: Wash and condition hair. (10 minutes)Activity 3: Neck, shoulder, and back stress release massage. (10 minutes)Activity 4: Design...
Part I – Process and Capacity Analysis Mortgage, Inc. processes loan applications in a “back-office” service facility. Each loan application must undergo a sequence of three separate processing activities before Mortgage, Inc. can make a decision to approve or decline the application. That is, a loan application first passes through Activity 1, then Activity 2, and finally Activity 3. Each activity has a fixed number of workers (given below). For example, there are three workers assigned to Activity 1 and...