The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions.
Hospital Expansion Project
|
Activity |
Description |
Immediate predecessor(s) |
Activity Time (Weeks) |
|---|---|---|---|
|
A |
Select administrative and medical staff |
- |
12 |
|
B |
Select site and do site survey |
- |
9 |
|
C |
Select equipment |
A |
10 |
|
D |
Prepare final construction plans and layout |
B |
10 |
|
E |
Bring utilities to the site |
B |
24 |
|
F |
Interview applicants and fill positions in nursing, support staff, maintenance, and security |
A |
10 |
|
G |
Purchase and take delivery of equipment |
C |
35 |
|
H |
Construct the hospital |
D |
40 |
|
I |
Develop an information system |
A |
15 |
|
J |
Install the equipment |
E, G, H |
4 |
|
K |
Train nurses and support staff |
F, I, J |
6 |
1) What are the project paths for hospital expansion project?
| a. |
AFK, AIK, ACGJK, BDHJK, BEJK |
|
| b. |
AFK, AIK, ABDJK, BCGJK, BEJK |
|
| c. |
AFK, AJK, ACGJK, BDHJK, BEIK |
|
| d. |
AFK, AIK, ABGJK, BCHJK, BEJK |
2) What is the project completion time in weeks?
| a. |
33 weeks |
|
| b. |
43 weeks |
|
| c. |
67 weeks |
|
| d. |
69 weeks |
3) Is activity H, constructing the hospital, a critical activity for this project? Please select the answer with the most appropriate justification.
| a. |
Yes, because H has the longest activity time of 40 weeks. |
|
| b. |
Yes, because H is on the path with the most activities. |
|
| c. |
Yes, because H is on the path with the longest total activity time. |
|
| d. |
No, A should be the critical activity because A precedes the most number of activities (C, F, and I). |
4) What is the slack of the activity C?
| a. |
2 |
|
| b. |
4 |
|
| c. |
6 |
|
| d. |
8 |
5) What is the slack of the activity H?
| a. |
0 |
|
| b. |
5 |
|
| c. |
36 |
|
| d. |
40 |
| Activity | Preceding Activity | Duration, D | Early start, ES=Max of early finish of preceeding activities | Early finish, EF = ES + D | Late finish, LF= Min of LS of successor activities | Late start, LS= LF - D | Total slack= LF-EF | Activities on the critical path | Critical activity, activities with 0 slack time |
| A | 12 | 0.00 | 12.00 | 14.00 | 2.00 | 2.00 | |||
| B | 9 | 0.00 | 9.00 | 9.00 | 0.00 | 0.00 | B | YES | |
| C | 10 | 12.00 | 22.00 | 24.00 | 14.00 | 2.00 | |||
| D | 10 | 9.00 | 19.00 | 19.00 | 9.00 | 0.00 | D | YES | |
| E | 24 | 9.00 | 33.00 | 59.00 | 35.00 | 26.00 | |||
| F | 10 | 12.00 | 22.00 | 63.00 | 53.00 | 41.00 | |||
| G | 35 | 22.00 | 57.00 | 59.00 | 24.00 | 2.00 | |||
| H | 40 | 19.00 | 59.00 | 59.00 | 19.00 | 0.00 | H | YES | |
| I | 15 | 12.00 | 27.00 | 63.00 | 48.00 | 36.00 | |||
| J | 4 | 59.00 | 63.00 | 63.00 | 59.00 | 0.00 | J | ||
| K | 6 | 63.00 | 69.00 | 69.00 | 63.00 | 0.00 | K |
| Paths | All crash Activity Duration (days) | |
| AFK | 28.00 | |
| AIK | 33.00 | |
| ACGJK | 67.00 | |
| BDHJK | 69.00 | Critical Path |
| BEJK | 43.00 |
Answer 1
Project paths for the hospital expansion project
| a. |
AFK, AIK, ACGJK, BDHJK, BEJK |
Answer 2
Project completion time in weeks
(d) 69 weeks
Answer 3
Is activity H, constructing the hospital, a critical activity for
this project
() Yes, because H is on the path with the longest total activity
time
Answer 4
Slack of the activity C.
(a) 2 weeks
Answer 5
Slack of the activity H?
(a) 0
Dear Student,
Please ask, if you have any doubts through the comment section. Do
rate the answer.
The following activities of a hospital expansion project has been identified in the following table. First,...
A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I
The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 3 2 B с D E F 4 A B B с DE E 1 3 G 2 Determine the amount of slack time for Activity E Ola. O weeks b. 1 week c. 2 weeks d. 3 weeks
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) Precedes A (start) 2 B, C B 2 E C 6 F E 3 F F (end) 4 — This exercise contains only parts b, c, and d. b) Define the critical path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
Problem 3 A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) Activity Immediate Predecessor(s) A В 7 C 7 A В, С D 14 Е 10 5 D E Н F, G a. Choose the correct network diagram below. O A. O B. в O C. O D. S в Problem 3 Question Help O D. O C b. Calculate the slack for each activity. Which activities are on the critical...