Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis.
a. Based on the critical path, find the probability of completing the office renovation project by 38 days. Refer to the standard normal table. (Make sure to round all intermediate calculations for te and variance to two decimal places.)
|
Time Estimates (days) |
||||
|
Activity |
Optimistic |
Most Likely |
Pessimisitic |
Immediate Predecessor(s) |
|
START |
0 |
0 |
0 |
|
|
A |
5 |
10 |
15 |
START |
|
B |
0 |
1 |
3 |
A |
|
C |
15 |
20 |
32 |
A |
|
D |
3 |
5 |
8 |
B |
|
E |
2 |
3 |
4 |
D |
|
F |
8 |
10 |
13 |
C |
|
G |
0 |
2 |
3 |
D |
|
H |
1 |
2 |
4 |
G |
|
I |
2 |
2 |
2 |
C, G |
|
J |
2 |
3 |
5 |
I |
|
K |
0 |
1 |
2 |
H |
|
L |
1 |
2 |
3 |
J, K |
|
FINISH |
0 |
0 |
0 |
E, F, L |
The critical path is A-C-F
Expected time for the activity A = (5 + 4*10 + 15)/6 = 10
Expected time for the activity C = (15 + 4*20 +32)/6 = 21.16
Expected time for the activity F = (8 + 4*10 + 13)/6 = 10.16
Total estimated time of completion = 10 + 21 + 10 = 41.32 days
Variance for event A = ((15 - 5)/6)2 = 2.7889
Variance for event C = ((8 - 3)/6)2 = 0.6938
Variance for event F = ((13 - 8)/6)2 = 0.6938
Total variance = 2.7889 + 0.6938 + 0.6938 = 4.1765
Standard deviation =
4.1765 =
2.0436
z-score = (38 - 41.32) / 2.0436 = -1.624
Probability (z< -1.624) = 0.0526
Hence, probability of completing the office renovation project by 38 days is 5.26%
Consider the office renovation project data in the following table. A "zero" time estimate means that...
Consider the following network for a small maintenance project (all times are in days). [7 Marks] Activity Immediate Predecessor [s] Optimistic Time Most Likely Time Pessimistic Time A - 2 3 4 B - 5 6 7 C - 5 6 7 D A 3 4 5 E A 2 3 4 F C 3 4 5 G C 8 10 16 H B, E, F 5 6 7 I B, E, F 7 11 15 J B, E,...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence diagram is shown in Figure 1 Figure 2 Figure 3 Figure 1 Figure 2 Figure 3
In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence...
Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...
Barbara Gordon, the project manager for Web Ventures, compiled a table showing time estimate for each of thecompany's manufacturing activities of a project. The list of activities, immediate predecessors, and estimated times appear in the following table: Activity Immediate Predecessor(s) Time (days) A - 4 B - 6 C - 1 D B 10 E A, D F C 5 G E, F 12 a) Therefore, the critical activities for the manufacturing project are (A - E - G,...
project are listed for a In the following table the activities with their precedence sequence and expected time (days) Immediate Predecessor(s) Time (days) Activity 7 A 2 A B 4 C 4 5 5 E C F 2 G E, F 3 H G, H a) The activities on the critical path are b) The project length is days.
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....
I need help Software Project Management question Q1. For the following table of information: a) Draw a network diagram (Activity on Arrow) b) List down all the network paths c) Determine the critical path(s) Activity Predecessor Duration A Start 5 days B A 2 days C A 3 days D B 4 days E C 6 days F C 3 days G D, E 4 days H F 2 days I G 3 days J H 1...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) S A Figure 1 C A 4 5 5 F 5 F G E, F D GH 2 3 H The correct AOA precedence diagram is shown in a Figure 2 Q Figure 3
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) - ITMO OWNono Ana E, F D GH a) The activities on the critical path are b) The project length is days. A-B-E-G-1 A-B-D-H-1 A-C-F-G-
Florida Power & Light is attempting to modernize the meters placed at people houses. The company Operations Manager, Mr. Jacob Marina, has asked for your assistance in preparing part of the project plan. Mr. Marina has identified the tasks, durations (in days), and predecessor relationships, and provides them in the following table: Immediate Most Activity Predecessor(s) Optimistic Likely Pessimistic A -- 1 2 4 B A 2 4 8 C B 3 5 15 D C 3 5 12 E...