The guidance system of a ship is controlled by a computer that
has three major modules. In order for the computer to function
properly, all three modules must function. Two of the modules have
reliabilities of .87, and the other has a reliability of .97.
a.What is the reliability of the computer? (Round
your answer to 4 decimal places.)
Reliability
b. A backup computer identical to the one being used will
be installed to improve overall reliability. Assuming the new
computer automatically functions if the main one fails, determine
the resulting reliability. (Round your intermediate
calculations and final answers to 4 decimal places.)
Reliability
c. If the backup computer must be activated by a switch in
the event that the first computer fails, and the switch has a
reliability of .95, what is the overall reliability of the system?
(Both the switch and the backup computer must function in order for
the backup to take over.) (Round your intermediate
calculations and final answers to 4 decimal places.)
Reliability
2
Item 2
Item 2 3.33 points
Determine the availability for each of these cases:
a. MTBF = 48 days, average repair time = 6 days.
(Round your answer to 2 decimal places.)
Availability
b. MTBF = 278 hours, average repair time = 8
hours. (Round your answer to 2 decimal
places.)
Availability
A manager must decide between two machines. The manager will
take into account each machine’s operating costs and initial costs,
and its breakdown and repair times. Machine A has a projected
average operating time of 139 hours and a projected average repair
time of 6 hours. Projected times for machine B are an average
operating time of 69 hours and a repair time of 5 hours. What are
the projected availabilities of each machine? (Round your
answers to 3 decimal places.)
| Availability | |
| Machine A | |
| Machine B | |
According to the guidelines provided by HomeworkLib, abiding by the HomeworkLib's honor code, only first question will be answered. Please post the other one separately. Thank you.
(a)
Since all three modules must function for the computer to function properly, the reliability of the
computer is the product of the reliabilities of three modules:
Reliability (Reliability of first module)*(Reliability of second module)*
(Reliability of third module)
Reliability (0.87)*(0.87)*(0.97)
= 0.7342 (rounded to four decimal places)
(b)
The reliability of the system
Reliability of first computer + (1- Reliability of first computer)
(Reliability of second computer)
(0.7342) + (1-0.7342) (0.7342)
0.9294
So the reliability of the system 0.9294
(c)
The addition of the switch changes the reliability of the second computer to (Reliability of switch)*(Reliability of first module)*(Reliability of second module)*(Reliability of third module)
(0.95)*(0.87)*(0.87)*(0.97)
.6975
Then, the reliability of the two computers (Reliability of first computer) + (1- Reliability of first computer) (Reliability of second computer)
(0.7342) + (1- 0.7342) (0.6975)
0.9196
Then the overall reliability of the system 0.9196
The guidance system of a ship is controlled by a computer that has three major modules....
The guidance system of a ship is controlled by a computer that has three major modules. In order for the computer to function properly, all three modules must function. Two of the modules have reliabilities of .95, and the other has a reliability of .99. a.What is the reliability of the computer? (Round your answer to 4 decimal places.) Reliability b. A backup computer identical to the one being used will be installed to improve overall reliability. Assuming...
The guidance system of a ship is controlled by a computer that has three major modules. In order for the computer to function properly, all three modules must function. Two of the modules have reliabilities of .97, and the other has a reliability of .87. a.What is the reliability of the computer? (Round your answer to 4 decimal places.) Reliability .8186 .8186 Correct b. A backup computer identical to the one being used will be installed to improve overall...
A manager must decide between two machines. The manager will take into account each machine's operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 140 hours and a projected average repair time of 7 hours. Projected times for machine B are an average operating time of 69 hours and a repair time of 4 hours. What are the projected availabilities of each machine? (Round your answers to 3 decimal...
Determine the availability for each of these cases a. MTBF-58 days, average repair time 4 days. (Round your answer to 2 decimal places.) Availability b. MTBF = 288 hours, average repair time = 9 hours. (Round your answer to 2 decimal places.) Availability
Determine the availability for each of these cases: a. MTBF = 50 days, average repair time = 8 days. (Round your answer to 2 decimal places.) Availability _______ b. MTBF = 280 hours, average repair time = 10 hours. (Round your answer to 2 decimal places.) Availability ________
A computer repair shop has two work centers. The first center examines the computer to see what is wrong, and the second center repairs the computer. Let x1 and x2 be random variables representing the lengths of time in minutes to examine a computer (x1) and to repair a computer (x2). Assume x1 and x2 are independent random variables. Long-term history has shown the following times. Examine computer, x1: μ1 = 29.7 minutes; σ1 = 8.0 minutes Repair computer, x2:...
Kalyan Singhal Corp. makes three products, and has three machines available as resources as given in the following LP Maximize contribution contribution 6x, 8x24x X1 7X24X3 72 2x 1x2x 76 X,4X21X3 s 72 X2.X3 20 (C,: hours on machine 1) (C2: hours on machine 2) C3: hours on machine 3) a) Using a computer software for solving LP, the optimal solution achieved is: x, L] (round your response to two decrnal places). 2round your response to two decimal places) X3(round...
The time until failure for an electronic switch has an exponential distribution with an average time to failure of 4 years, so that λ = 1/4 = 0.25. (Round your answers to four decimal places.) (a)What is the probability that this type of switch fails before year 3? (b)What is the probability that this type of switch will fail after 5 years? (c) If two such switches are used in an appliance, what is the probability that neither switch fails...
The Wilcox Student Health Center has just implemented a new computer system and service process to "improve efficiency". The process flowchart and analysis framework is also provided. As pharmacy manager, you are concerned about waiting time and its potential impact on college students who "get no respect". All prescriptions (Rxs) go through the following process: Assume that students arrive to drop off Rxs at a steady rate of two Rxs per minute, with an average of one Rx per student....
Better Products, Inc., manufactures three products on two machines. In a typical week, 40 hours are available on each machine. The profit contribution and production time in hours per unit are as follows: Category Product 1 Product 2 Product 3 Profit/unit $36 $58 $19 Machine 1 time/unit 0.5 2.5 1.5 Machine 2 time/unit 1 1.5 1.5 Two operators are required for machine 1; thus, 2 hours of labor must be scheduled for each hour of machine 1 time. Only one...