|
Activity |
PV (in $) |
EV (in $) |
AC |
|
A |
9,200 |
10,000 |
9,700 |
|
B |
23,000 |
20,000 |
18,000 |
|
C |
12,000 |
13,000 |
11,000 |
|
D |
8,000 |
10,000 |
12,000 |
|
E |
10,000 |
12,000 |
13,000 |
|
F |
7,000 |
9,000 |
10,000 |
|
G |
8,000 |
9,000 |
10,000 |
Earned Value Management (EVM) is nothing but important technique by which the time and cost performance of a project is controlled.
The three metrics of earned value management are: -
Planned Value (PV)
Actual Cost (AC)
Earned Value (EV)
Earned value is the approach where project plan, actual work and work completed value can be monitored in order to see if a project is on track. It shows how much of the project budget and schedule should have been spent based on the amount of work done so far.
Schedule variance can be calculated using earned value and planned value.
SV = EV - PV
Where, SV = schedule variance
EV = earned value
PV = planned value
Positive value of schedule variance indicate that the work not yet schedule to be completed at this time has been done. Negative value of schedule variance indicates the work schedule to be completed at this time is not done.


Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000...
Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000 C 12,000 13,000 11,000 D 8,000 10,000 12,000 E 10,000 12,000 13,000 F 7,000 9,000 10,000 G 8,000 9,000 10,000 Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000.
Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC 1,000 8,000 8,000 7,000 Which item has the LOWEST SPI? Item 1 Item 4 Item 2. Item 3
Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC...
You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...
You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....
Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...
Teams of 2. Teams are not allowed to work together. Problem # 1: Forklift Purchased Jan 1 Cost: $180,000 RV: $25,000 Life: 6 years or 110,000 hours Y1: 17,000 hours Y2: 13,000 hours Y3: 25,000 hours Y4: 20,000 hours YS: 17,000 hours Y6: 18,000 hours of 2 Problem #2: Oven Purchased Jan 1 Cost: $90,000 RV: $15,000 Life: 4 years or 50,000 hours Y1: 12,000 hours Y2: 14,000 hours Y3: 16,000 hours Y4: 8,000 hours Problem #3: Aston Martin Purchased...
Each problem is worth 2 point for a total of 10 points EXTRA CREDIT Fully depreciate all problems using all three methods (SL, UOfP, DDB). All team members must work through this everyone stays together on each problem (you cannot split up the work). One packet turned in with everyone's first and last name printed. Teams of 2. Teams are not allowed to work together. Problem # 1: Forklift Purchased Jan 1 Cost: $180,000 RV: $25,000 Life: 6 years or...
X-treme Vitamin Company is considering two investments, both of which cost $20,000. The cash flows are as follows: Year Project A Project B $23,000 $20,000 2 10,000 9,000 3 10,000 15,000 1 Use Appendix B for an approximate answer but calculate your final answer using the formula and financial calculator methods. a-1. Calculate the payback period for Project A and Project B. (Round your answers to 2 decimal places.) Project A Project B Payback Period year(s) year(s) b-1. Calculate the...