You have decided to enter into a time and materials contract with a supplier for your project. The project will require two different types of labor categories, the first which charges $200 per hour and the second which charges $175 per hour. The project requires 50 hours of the first labor category and 40 of the second. You will also purchase $5,000 of tools and equipment with no fee and $25,000 of materials with a 2% fee added on. What will you owe on this contract?
| We will owe the following amounts on the given contract: | ||
| Particulars | Working | Amount($) |
| Labour Cost: | ||
| First Category | (50hrs*$200 p/hr) | 10000 |
| Second Category | (40hrs*$175p/hr) | 7000 |
| Cost of Tools: | 5000 | |
| Cost of Materials including fee: | ($25000*1.02) | 25500 |
| Total Amount we will owe on this contract is : | 47500 |
You have decided to enter into a time and materials contract with a supplier for your...
On the bill for a Time & Materials contract, you see the following line items. LABOR Labor Category Labor Rate Hours Used Designer $200/hour 100 Architect $300/hour 200 Engineer $250/hour 400 MATERIALS Item Cost Fee Building Materials $300,000 5% Tools $200,000 -- Vehicle Rental $50,000 2% How much does your project owe? (5 points)
For direct materials, the materials were purchased from a new
supplier who is anxious to enter into a long-term purchase
contract. Would you recommend that the company sign the
contract?
Yes or No
For direct labor, compute the rate and efficiency variances.
(Indicate the effect of each variance by selecting "F" for
favorable, "U" for unfavorable, and "None" for no effect (i.e.,
zero variance). Input all amounts as positive values.)
Labor rate variance
Labor efficiency
variance
In the past, the...
Hi,
I am requesting your help.
Thank you,
Michelle
_______________________________________________
Select:
a.
Materials and labor resources
Information resources
b.
Materials and labor resources
Information resources
c.
Materials and labor resources
Information resources
d.
Materials and labor resources
Information resources
e.
Materials and labor resources
Information resources
f.
Materials and labor resources
Information resources
You are a management consultant with McKenzie and Company. You specialize in helping companies accurately identify and acquire the appropriate production inputs for their operations. Based on...
IT Project management, Include the reference
Task You have decided to enter a South African Innovative App Competition. The competition requires you (and your team) to think of an innovative idea that could lead to a development of an App aimed at assisting and benefiting South African citizens in one of the following categories Category 1 Category 2 Category3 Category4 Consumer Behaviour Government Services Matric (Grade 12) to Tertiary Your Choice Think of a problem (idea) in any one of...
Project Procurement Management Senior management at Manage Your Health, Inc. (MYH) decided that it would be best to outsource employee training on the Recreation and Wellness system, which will be rolled out soon. MYH also wants to outsource the incentive program designed to motivate employees to use the system and improve their health. MYH feels that the right outside company could get people excited about the system and provide a good incentive program. As part of the seller selection process,...
You make refrigerators. Currently, you manufacture compressors for your refrigerators in-house. An outside supplier has offered to sell you equivalent compressors at a wholesale price of $85 per unit. You need 1,000 compressors per month. The internal production costs per compressor are as follows: cost per unit direct materials $30 direct labor $30 variable overhead $20 fixed overhead $20 total $100 If you outsource the production of compressors (the buy option) in the short term, how will this choice affect...
Your firm designs PowerPoint slides for computer training classes, and you have just received a request to bid on a contract to produce the slides for an 8-session class. From previous experience, you know that your firm follows an 85 percent learning rate. For this contract it appears the effort will be substantial, running 50 hours for the first session. The variable cost is $100/hour and the fixed cost is $600 per session. a) How much effort (in hours) will...
as a new manager at Bracelets Unlimited. In the past the company has done very little you have decided to prepare a comprehensive You have just been hired in the way of budgeting. Since you are well trained in budgeting master budget for the upcoming year. You have worked with accounting and other areas of the company to compile the following information. The company sell its bracelets for $15 each. Actual sales for the last three months and budgeted sales...
Exotic materials in a large power plant A new state-of-the-art coal-fired power plant was to be built at a newly developed site. There, it would be connected to plants that would also provide biological waste as fuel, in return for high-pressure steam and energy.The power plant reaches high efficiencies, filters its exhaust gas and particles, and is able to compress and back CO2 into subterranean reservoirs of old gas fields. The project showcases the latest technology concerning coal-fired plants, including...
Your company makes tennis rackets which you sell through a specialty shop. You instructed the shop owner whose policy is to realize 40% margin on anything s/he sells to sell them at $150.00 per racket. Your production cost and other expenses are below: Factory Labor per racket $15.00 Materials per racket $20.00 Racket labels (per 5,000) $500.00 Racket design $20,000.00 Advertising $10,000.00 Shipping to the store $5,000.00 In addition to these expenses, you have negotiated an endorsement contract with Mr....