Question

You are using earned value analysis to track your project's progress. In your project, earned value...

You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget.

Select an answer:

  • behind; under

  • ahead of; under

  • ahead of: over

  • behind; over

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Note: Please rate the answer (upvote) and do ask if any doubt is there.

Answer:

  • Option 2: Ahead of; under

Explanation:

  • Since the earned value is higher than the planned value, this means the project has achieved a value more than what was planned for that duration, hence it is ahead of schedule.
  • Similarly, when the earned value is higher than the actual value, this means the project has spent a lesser amount for a particular quantity of work than the budgeted amount for the similar quantity of work, hence it is under budget.

Note: Please rate the answer (upvote) and do ask if any doubt is there.

Add a comment
Know the answer?
Add Answer to:
You are using earned value analysis to track your project's progress. In your project, earned value...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Your company was hired as a subcontractor for a client's "Destiny project and awarded two main work packages within that project. Your company refers to this project internally using the cost...

    Your company was hired as a subcontractor for a client's "Destiny project and awarded two main work packages within that project. Your company refers to this project internally using the cost code "P2 2019". You're given the table below that lists the work packages, their cost code, their budget, and their scheduled start day and end day (as agreed upon with the main contractor). The start and end days are measured in working days after the main project's start. So,...

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it Page 6 of 8 IS8100-01 Fa2019 under or over budget? Use all of the calculated variances and indexes from above to support your argument. [50-100-word response.]

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • Your project has a CPI of 0.85 and a SPI of 0.95. Which of the following...

    Your project has a CPI of 0.85 and a SPI of 0.95. Which of the following statements is TRUE? a. Your project is behind schedule and project costs are over the planned costs b. Your project is ahead of schedule and project costs are over the planned costs c. Your project is behind schedule and project costs are under the planned costs d. Your project is ahead of schedule and project costs are under the planned costs

  • In earned value analysis the "schedule variance" is the earned value minus the planned value. Consider...

    In earned value analysis the "schedule variance" is the earned value minus the planned value. Consider the following situation. A project has a planned schedule of 12 months with an estimated project cost of $800,000 . At six months into the project, the project manager quits and you are asked to take over the project. You discover that the accumulated costs are already $200,000 but only 25% of the work is complete. What is the schedule variance for this project?...

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Sketch (free-hand sketch acceptable) a graph to show the relationship between PV, AC, EV, BAC, and EAC. Interpret the sketch explaining on-budget (cost) and on-time (schedule) progress of the project. [75-150-word response.]

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Sketch (free-hand sketch acceptable) a graph to show the relationship between PV, AC, EV, BAC, and EAC. Interpret the sketch explaining on-budget (cost) and on-time (schedule) progress of the project. [75-150-word response.]

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT