Question

Your project has a CPI of 0.85 and a SPI of 0.95. Which of the following...

Your project has a CPI of 0.85 and a SPI of 0.95. Which of the following statements is TRUE?

a. Your project is behind schedule and project costs are over the planned costs

b. Your project is ahead of schedule and project costs are over the planned costs

c. Your project is behind schedule and project costs are under the planned costs

d. Your project is ahead of schedule and project costs are under the planned costs

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a. Your project is behind schedule and project costs are over the planned costs

Based on the value of CPI and SPI, the project is over budget as the value of CPI(Cost Performance Index) is less than 1, the project is behind schedule as the value of SPI(Schedule Performance Index) is less than 1 as well.

Add a comment
Know the answer?
Add Answer to:
Your project has a CPI of 0.85 and a SPI of 0.95. Which of the following...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • Based on the values EV=$10,000, SPI=1.1, and AC=$12,000, which best describes the current status of the...

    Based on the values EV=$10,000, SPI=1.1, and AC=$12,000, which best describes the current status of the project? The project is over cost and behind schedule. The project is under cost and ahead of schedule. The project is over cost and ahead of schedule. The project is at cost and behind schedule

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • Please solve these questions by choosing the correct answer 25 B) Work Breakciown Siructure is: A)...

    Please solve these questions by choosing the correct answer 25 B) Work Breakciown Siructure is: A) A hierarchically-organized depiction of the project organization ) A hierarchical representation of project risks 5 C D) A hierarchical structure of resource categories A deliverables-oriented decomposition of the project work Based on your experience with three similar past projects, you estimate an 8-10 month implementation time frame for a new project. What is this type of estimation technique called? A) Three-Point Estimating B) Bottom-Up...

  • You are using earned value analysis to track your project's progress. In your project, earned value...

    You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget. Select an answer: behind; under ahead of; under ahead of: over behind; over

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....

  • A project has an AC of $4,500, and a PV of $5,000. If the SPI is...

    A project has an AC of $4,500, and a PV of $5,000. If the SPI is 1.1, what is the CPI? a. 1.3 b. 0.9 c. 1.22 d. 1.0

  • Canyouhelpme with this questionYou are managing a project to expand a major county road in your...

    Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...

  • Q1- Part A- Which of the following can best describe the project status in regard to...

    Q1- Part A- Which of the following can best describe the project status in regard to budget and schedule? a- Behind schedule-Overbudget b- Behind schedule- Underbudget c- Ahead the schedule- Overbudget d- Ahead of schedule- Underbudget Part B- It is possible to have the scheduler report saying the project is behind schedule while the earned value analysis is showing a positive schedule variance. TRUE or FALSE Part C EV is cost-based, so it is more reliable than CPM. TRUE of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT