Question

A project has an AC of $4,500, and a PV of $5,000. If the SPI is...

A project has an AC of $4,500, and a PV of $5,000. If the SPI is 1.1, what is the CPI?

a. 1.3

b. 0.9

c. 1.22

d. 1.0

0 0
Add a comment Improve this question Transcribed image text
Answer #1

AC = $4500

PV = $5000

SPI = 1.1

EV = SPI × PV = 1.1 × $5000 = $5500

CPI = EV/AC = $5500 / $4500 = 1.22

So the answer is option c

Add a comment
Know the answer?
Add Answer to:
A project has an AC of $4,500, and a PV of $5,000. If the SPI is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC 1,000 8,000 8,000 7,000 Which ite...

    Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC 1,000 8,000 8,000 7,000 Which item has the LOWEST SPI? Item 1 Item 4 Item 2. Item 3 Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC...

  • The SPI, which can be used to estimate project completion date, is calculated by? A. EV/PV...

    The SPI, which can be used to estimate project completion date, is calculated by? A. EV/PV B. EV/AC C. BAC-ETC D. Budget - Cost

  • Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000...

    Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000 C 12,000 13,000 11,000 D 8,000 10,000 12,000 E 10,000 12,000 13,000 F 7,000 9,000 10,000 G 8,000 9,000 10,000 A project to develop a country park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances, and CPI and SPI. What meaning do you derive from the...

  • Q 16 Question 16 Julia Penfield was working on a project and needed to update her...

    Q 16 Question 16 Julia Penfield was working on a project and needed to update her boss on it’s CPI. If EV = 50,000, PV = 45,000, and AC = 41,000 what is the CPI? Select one: a. 1.21 b. 0.82 c. 1.16 d. 1.20 Q 17 Question 17 Kerri Lerner wanted to determine her project’s SPI. If EV = 42,000, PV = 40,000, and AC = 39,000, what is the SPI? Select one: a. 0.95 b. 0.98 c. 1.16...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • Your project has a CPI of 0.85 and a SPI of 0.95. Which of the following...

    Your project has a CPI of 0.85 and a SPI of 0.95. Which of the following statements is TRUE? a. Your project is behind schedule and project costs are over the planned costs b. Your project is ahead of schedule and project costs are over the planned costs c. Your project is behind schedule and project costs are under the planned costs d. Your project is ahead of schedule and project costs are under the planned costs

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • Your project has an EV of $24,000, PV of $29,000, and AC of $45,000. If BAC...

    Your project has an EV of $24,000, PV of $29,000, and AC of $45,000. If BAC is $96,000, what percent of the work has been completed? a. 30 percent b. 25 percent c. 40 percent d. 20 percent

  • A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both...

    A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The original project budget is $10. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the estimate at completion (EAC) of the project? $12.96 $13.17 $14.75 $15 What is your reasoning? ________________________________________________________

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT