Your project has an EV of $24,000, PV of $29,000, and AC of $45,000. If BAC is $96,000, what percent of the work has been completed?
a. 30 percent
b. 25 percent
c. 40 percent
d. 20 percent
b. 25 Percent
Percent Complete = (EV/BAC)*100
= (24000/96000)*100
= 0.25*100
= 25%
Your project has an EV of $24,000, PV of $29,000, and AC of $45,000. If BAC...
Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...
The SPI, which can be used to estimate project completion date, is calculated by? A. EV/PV B. EV/AC C. BAC-ETC D. Budget - Cost
Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...
1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project performance data with reference to the project plan, developing performance measures, and communicating performance information?” a. controlling b. monitoring c. executing d. managing 3 Which of the following formulas represents the schedule performance index (SPI)? a. EV/PV b. EV PV c. EV AC d. EV/AC 4 If your sponsor asks for an estimate as to how much more money your team needs to complete...
soon, hence you have to write your answer in the Texi-Field given below Actual Cost (AC). Planned Value (PV) and Eamed Value (EV) of the activities of an ongoing project atter 5 months and after 8 months are given in the following table. All values and costs are in Rs lakhs. Comment on the status of the a) activities (activity delayediearty, activity cost over-runiunderrun), and b) status of the project and estimated total costat completion at 5 months and at...
Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC 1,000 8,000 8,000 7,000 Which item has the LOWEST SPI? Item 1 Item 4 Item 2. Item 3
Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC...
Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: 51.200.000. EV: 51.000.000. AC: $1.200.000 You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC - EV) is at 51.000.000, what should be your new EAC (estimate at completion)? A) $1.800.000 B) $2.000.000 C) $2.200.000 D) $2.400.000
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....
Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000 C 12,000 13,000 11,000 D 8,000 10,000 12,000 E 10,000 12,000 13,000 F 7,000 9,000 10,000 G 8,000 9,000 10,000 A project to develop a country park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances, and CPI and SPI. What meaning do you derive from the...