Question

Office Automation Inc., has developed a proposal for introducing a new computerized office system that will...

Office Automation Inc., has developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be accomplished in order to complete the new office system project. Information about the activities is shown in the table below. Times are in weeks.

Data for Office Automation, Inc.

Activity

Description

Immediate Predecessors

Normal Time

Crash Time

Normal Cost ($)

Crash Cost ($)

A

Plan needs

-----------

10

8

30

70

B

Order equipment

A

8

6

120

150

C

Install equipment

B

10

7

100

160

D

Set up training lab

A

7

6

40

50

E

Training course

D

10

8

50

75

F

Testing system

C, E

3

3

60

-------

a). Show the network for the project.

b). Develop an activity schedule for the project using normal times.

c). What are the critical path activities and what is the expected project completion time?

d.) Use the Trial and Error Method to solve this problem. What is the Total Cost of Crashing including the Normal Cost?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Paths are:

A-B-C-F = 33 weeks

A-D-E-F = 31 weeks

So, critical path is A-B-C-F

Total added cost due to crashing = 1,52,500

Add a comment
Know the answer?
Add Answer to:
Office Automation Inc., has developed a proposal for introducing a new computerized office system that will...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 24. Office Automation, Inc., developed a proposal for introducing a new computerized office system that will...

    24. Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Predecessor Time (weeks) Normal Crash Cost ($1000s) Normal Crash Activity Description Plan needs Order equipment Install equipment Set up training lab Conduct training course Test...

  • Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the pro...

    Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Activity Description Immediate Predecessor Normal Time (weeks) Crash Time (weeks) Normal Cost ($1000s) Crash Cost ($1000s) A Plan needs ------ 10 8 30 70 B Order equipment...

  • 18. Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in th...

    18. Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities Crash Cost ($1000s) Activity Description Immediate NormalCrash Normal Predecessor Time TimeCost (weeks) (weeks ($1000s) 10 70 150 160 50 75 Plan needs Order equipment Install equipment...

  • Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the pr...

    Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Activity Description Immediate Predecessor Normal Time (weeks) Crash Time (weeks) Normal Cost ($1000s) Crash Cost ($1000s) A Plan needs ------ 10 8 30 70 B Order equipment...

  • Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc....

    Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture...

    A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture and market a new laptop computer. Their estimates are listed below Immediate Activity Description Estimated completion time (days) 90 15 Predecessors Prototype design Purchase of materials Manufacture of prototype Revision of design Initial production run Staff training Staff input on prototype Sales training Preproduction advertising campaign Post production advertising campaign 20 21 25 14 28 30 C,F D,I Management has also provided you with...

  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • 3. The client of a project has requested the project team to crash 8 hours of...

    3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT