Network Diagram:

Possible Paths:
Start-A-B-C-D-H-End = 23 hours
Start-A-B-C-E-F-G-H-End = 34 hours ......... Critical Path (longest duration path
Start-A-B-C-F-G-H-End = 28 hours
For reducing the project duration, the least incremental crash cost activities on Critical Path should be crashed.
Incremental Crash Cost = (Crash Cost - Normal Cost) / (Normal Duration - Crash Duration)
| Activity | Normal Time | Crash Time | Normal Cost | Crash Cost | Incremental Crash Cost |
| A | 2 | 2 | 10 | 0 | NA |
| B | 3 | 2 | 15 | 23 | 8 |
| C | 5 | 4 | 25 | 30 | 5 |
| D | 3 | 1 | 20 | 24 | 2 |
| E | 6 | 4 | 30 | 45 | 7.5 |
| F | 1 | 1 | 5 | 0 | NA |
| G | 7 | 6 | 35 | 50 | 15 |
| H | 10 | 7 | 50 | 62 | 4 |
Crashing Schedule to reduce the project duration by 8 hours i.e 34 - 8 = 26 hours
| Crashed Activity | No Crashing | H | C | E | B | G |
| No. of days Crashed | 0 | 3 | 1 | 2 | 1 | 1 |
| Crashing Cost | 0 | 12 | 5 | 15 | 8 | 15 |
| Total Crashing Cost | 0 | 12 | 17 | 32 | 40 | 55 |
| Critical Path | A-B-C-E-F-G-H | A-B-C-E-F-G-H | A-B-C-E-F-G-H | A-B-C-E-F-G-H | A-B-C-E-F-G-H | A-B-C-E-F-G-H |
| TPT | 34 | 31 | 30 | 28 | 27 | 26 |
a) From the above table, crash cost for 8 hours of time-saving is $55
b) From the above table, 20$ budget is sufficient to crash 4 hours of time, as it will only require $17
PLEASE HELP ME BY LIKING THIS ANSWER. THANK YOU VERY MUCH FOR THE LIKE!
3. The client of a project has requested the project team to crash 8 hours of...
3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?...
The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...
The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...
Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the project table below calculate the crash cost for 8 hours of time-savings. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash Crash Duration Normal Duration Immediate Crash Cost ($) Normal Cost ($) Activity (hours) (hours) Predecessors 10 0 15 23 3 30 25 4 20 24...
62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20 2 - 3 2 60 60 3 1 4 0 70 0 4 1 2 1 50 10 5 2 5 3 100 60 6 3 2 1 90 100 7 4 5 1 50 30 8 5 2 0 60 40 9 6,7,8 3 1 200 200 Consider the project above. If the indirect costs of the project are:...
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...
TYPE: A CRAMOCerat Managmenti Sume 20t9 2 JCh. 3. Project Management] Jacksonville Bike Shop is behind on a custom bike and needs to crash 1 day of time from the 6-step project. Given the project table below answer the following questions. Suppose this shop calls the customer and asks for a project extension, reducing the amount of time she/he nceds to crash. [Note: The project can be speeded up (or "crashed") by spending For example, activity A currently takes 10...
Assume the network and data that follow: ACTIVITY NORMAL TIME (WEEKS) NORMAL COST CRASH TIME (WEEKS) CRASH COST IMMEDIATE PREDECESSORS A 3 $ 60 2 $ 80 — B 5 70 4 110 A C 9 50 6 80 A D 7 100 6 130 A E 8 90 6 100 B F 5 30 3 50 D G 6 110 5 190 C, E, F b. Indicate the critical path when normal activity times are used. A-B-E-G A-C-F-G A-D-E-G...
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...