(b)
The critical path of a project is composed off activities with zero total slack. The critical path(s) is/ are the longest path(s) in a project network. The slacks for each activity can be computed by carrying out forward pass and backward pass in the project network.
Forward Pass:
ES of the starting activities = 0
ES of all other activities = Max. (EF of their immediate predecessors)
EF of an activity = Its ES + Its duration
Backward Pass:
LF of ending activities = Max. (All the EFs)
LF of all other activities = Min. (LS of their immediate successors)
LS of an activity = Its LF - Its duration
Total slack (or, float) = LF - EF for each activity.
| Activity | Duration | ES | EF | LS | LF | Slack |
| A | 90 | 0 | 90 | 0 | 90 | 0 |
| B | 15 | 90 | 105 | 95 | 110 | 5 |
| C | 5 | 105 | 110 | 110 | 115 | 5 |
| D | 20 | 129 | 149 | 129 | 149 | 0 |
| E | 21 | 149 | 170 | 173 | 194 | 24 |
| F | 25 | 90 | 115 | 90 | 115 | 0 |
| G | 14 | 115 | 129 | 115 | 129 | 0 |
| H | 28 | 149 | 177 | 166 | 194 | 17 |
| I | 30 | 90 | 120 | 119 | 149 | 29 |
| J | 45 | 149 | 194 | 149 | 194 | 0 |
The critical path is constituted by activities with slack=0. So, the critical path is A-F-G-D-J with project completion time=194 days.
(c)
First, compute the cost slope using the following formula:
Slope = (Crash cost - Normal cost) / (Normal time - Crash time)
| Activity | Normal time | Normal cost | Crash time | Crash cost | Slope | Max crash limits |
| A | 90 | 2250 | 85 | 2520 | 54.00 | 5 |
| B | 15 | 180 | 13 | 210 | 15.00 | 2 |
| C | 5 | 90 | 4 | 120 | 30.00 | 1 |
| D | 20 | 300 | 16 | 340 | 10.00 | 4 |
| E | 21 | 231 | 17 | 315 | 21.00 | 4 |
| F | 25 | 250 | 22 | 375 | 41.67 | 3 |
| G | 14 | 70 | 12 | 112 | 21.00 | 2 |
| H | 28 | 392 | 25 | 448 | 18.67 | 3 |
| I | 30 | 510 | 28 | 570 | 30.00 | 2 |
| J | 45 | 1350 | 41 | 1530 | 45.00 | 4 |
Always select activities on the critical paths for crashing which has the minimum slope.




The step-3 is the last step because the project duration has been reduced to 186 days. The activities crashed were D (4 days), G (2 days), and F (2 days). The total minimum cost is 5,788.33 ($,000).
A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture...
A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture and market a new laptop computer. Their estimates are listed below Immediate Activity Description Estimated completion time (days) 90 15 Predecessors Prototype design Purchase of materials Manufacture of prototype Revision of design Initial production run Staff training Staff input on prototype Sales training Preproduction advertising campaign Post production advertising campaign 20 21 25 14 28 30 C,F D,I Management has also provided you with...
Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Predecessor(s) Normal Time Crash Time Normal Cost $400 Crash Cost $700 1600 2000 800 1100 1000 NNW 600 1200 1450 800 800 500 650 400 600 900 1300 F G H1 1000 650 8. Draw the network for this project. (10 points) 9. Please indicate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish on the...
The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...
Choose an event or significant task and prepare an activities
list following a format similar to that used in the text, Table
9.3, Chapter 9, page 391. Be sure to include the immediate
predecessors.
Then, create a project network similar to that shown in Figure
9.7, Chapter 9, page 392.
Do NOT include times for the activities and do NOT attempt to
determine the critical path.
Examples of events you might consider (there are many
others):
formal dinner for 5...
Question 1 Adelaide produces "Final Exam Care Packages" for resale. She is currently working a total of five hours per day to produce 100 care packages. a) What is Adelaide's productivity? Adelaide thinks that by redesigning the package, she can increase her total productivity to 133 care packages per day. b) What will be her new productivity? c) What will be the percentage increase in productivity if Aditi makes the change? Question 2 Punjab Performance Auto, Inc., modifies 375 autos...
Project management
Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...
Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...
Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...
Use the following information for questions 1 to 10. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...
Continual Technology Training (CTT) is a technology learning centre founded by Dr. Alan Hong. CTT provides short technical courses catered to adults working in Singapore’s science and technology sectors. The courses conducted, such as Artificial Intelligence and Machine Learning, equip learners with the latest technical knowledge that they can apply in their work. CTT started three years ago at Happy World Plaza with one classroom and Dr. Hong was the only trainer. Recently, with the promotion of life-long learning by...