Pre-requisite Formulas
ES = EF of Preceding activity (0 for source task), highest to be selected
EF = ES + Activity Time of the tasks
LF = LS of succeeding activity (Critical path time for Sink Task), lowest to be selected
LS = LF - Activity Time of the tasks
Answer-
The Network flow diagram along with the Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF) is as shown in the diagram-

To identify the critical path, we will first identify those tasks which has ES=LS and EF=LF. The tasks A,F,G.D & J are the tasks adhering to this criteria and hence, constitute the critical path. Therefore the critical path is A-F-G-D-J.
The scheduled project duration is = Sum of tasks in critical path = 90+25+14+20+45 = 194 days
Time taken by Non Critical paths-
A-F-G-D-E = 90+25+14+20+21 = 170 days
A-F-G-D-H = 90+25+14+20+28 = 177 days
A-B-C-G-D-E = 90+15+5+14+20+21 = 165 days
A-B-C-G-D-H = 90+15+5+14+20+28 = 172 days
A-B-C-G-D-J = 90+15+5+14+20+45 = 189 days
A-I-J = 90+30+45 = 165 days
B) The management wants to bring the project 8 days before the scheduled period. Therefore, the critical activities needs to be crashed by 8 days.
Calculating Improvement factor for all activity using formula - Improvement factor = (Crash Cost - Normal Cost)/(Normal Time - Crash Time)
| Activity | Normal Time | Normal Cost | Crash Time | Crash Cost | Improvement Factor |
| A | 90 | 2250 | 85 | 2520 | 54 |
| B | 15 | 180 | 13 | 210 | 15 |
| C | 5 | 90 | 4 | 120 | 30 |
| D | 20 | 300 | 16 | 340 | 10 |
| E | 21 | 231 | 17 | 315 | 21 |
| F | 25 | 250 | 22 | 375 | 41.66666667 |
| G | 14 | 70 | 12 | 112 | 21 |
| H | 28 | 392 | 25 | 448 | 18.66666667 |
| I | 30 | 510 | 28 | 570 | 30 |
| J | 45 | 1350 | 41 | 1530 | 45 |
Highlighted are the critical activities.
From the above table we see that, out of the critical activities,
the Improvement factor of Activity D is least and should be crashed
first. On crashing Activity D, we shall get a reduction in project
duration of 4 days.
Now, we see that the Improvement factor of Activity G is the next lowest figure and should be crashed second. On crashing Activity G, we shall get a reduction in project duration of 2 days. Thus resulting in the total project duration reduction to 6 days.
Now, we see that the Improvement factor of Activity F is the next lowest figure and should be crashed third. On crashing Activity F, we shall get a reduction in project duration of 3 days. Thus resulting in the total project duration reduction to 9 days.
Therefore, the critical path duration after crashing will now be = 90+22+12+16+45 = 185 days
Time taken by Non Critical paths-
A-F-G-D-E = 90+22+12+16+21 = 161 days
A-F-G-D-H = 90+22+12+16+28 = 168 days
A-B-C-G-D-E = 90+15+5+12+16+21 = 159 days
A-B-C-G-D-H = 90+15+5+12+16+28 = 166 days
A-B-C-G-D-J = 90+15+5+12+16+45 = 183 days
A-I-J = 90+30+45 = 165 days
As the non-critical paths still have time duration less than the critical path, the critical path doesn't change on crashing.
C) To achieve the desired time of project completion, the management has to undergo the above stated crashing steps. This crashing would subsequently also increase the investment required for project completion. Based on the investment capabilities, the management should decide how much early they should target to release the product as compared to the normal scheduled time. Nevertheless, evaluating the steep increase of Improvement factor in the third crashing step, the management should stop crashing at the second step itself. The monetary investment required to undertake the third crashing doesn't justify the extent to which it bring reduction in project duration. Therefore, the product should be launched at 188th day rather than on 186th, if monetary investment is given highest precedence.
Please Like & Provide your reviews in comments. :-)
A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture and market a new laptop computer. Their estimates are listed...
A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture and market a new laptop computer. Their estimates are listed below Immediate Activity Description Estimated completion time (days) 90 15 Predecessors Prototype design Purchase of materials Manufacture of prototype Revision of design Initial production run Staff training Staff input on prototype Sales training Preproduction advertising campaign Post production advertising campaign 20 21 25 14 28 30 C,F D,I Management has also provided you with...
Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Predecessor(s) Normal Time Crash Time Normal Cost $400 Crash Cost $700 1600 2000 800 1100 1000 NNW 600 1200 1450 800 800 500 650 400 600 900 1300 F G H1 1000 650 8. Draw the network for this project. (10 points) 9. Please indicate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish on the...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 7 7 N/A B none 3 2 $500 C A 5 3 $1000 D A, B 6 4 $2000 E C, D 4 3 $1250 F D 3 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...
use excel to solve the
problem
You and several friends are about to prepare a lasagna dinner. The tasks to be performed, their immediate predecessors, and their estimated durations are as follows: Tasks That Time Task Description (minutes) Must Precede 30 Buy the mozzarella cheese* Slice the mozzarella Beat 2 eggs Mix eggs and ricotta cheese Cut up onions and mushrooms Cook the tomato sauce 25 15 10 Boil large quantity of water Boil the lasagna noodles Drain the lasagna...
A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...
Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...
If you would like to reduce the overall completion time of the
project by 1 day, which activity (A, B, C, D, E, F, G, or H) should
be crashed?
The list of activities of a data analysis project, their precedence relationships, and their activity times (in number of days) are given in the table below. Activity ID Predecessors Activity Time (Days) A 3 B А 4 с B 2 D с 5 E B 7 F с 2 G...