What is the critical path? Describe how the critical path is determined? What is slack (float)?...

What is the critical path? Describe how the critical path is determined?

What is slack (float)? What is total slack? What is free slack?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The critical path is defined as the chain of activities that is present in a project network, which holds the most value and takes the longest duration of time to complete. The project duration is therefore determined by the critical path, where a delay in any of the critical activities in the critical path delays the entire project.

The most straightforward method is to determine different chains, calculate their duration and the chai with the maximum duration represents the critical path. If two chains have the same maximum duration, both represent the criteria path.

The second and more comprehensive method takes a forward and backward pass of the network, calculating its ES, EF, LS, LF values and determining the slack for the activist, the chain with 0 slack represents the critical path, if two chains have 0 slack, both represent the critical path.

2. Slack is the difference between the earliest time an activity can be started and the last time the activity can be started. It is represented as LS - ES, or LF - EF, and converts the understanding that an activity that has slack can be delayed for the duration of the slack without deleting the project. It is therefore useful in crashing or fast-tracking the projects.


Total slack is the LS - ES, OR LF - EF while free slack is the ES of the predecessor activity - duration of the current activity - the ES of the current activity.

Add a comment
Know the answer?
Add Answer to:
What is the critical path? Describe how the critical path is determined? What is slack (float)?...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT