In risk management, insurance is an example of:
Select one:
a. Risk avoidance
b. Risk deflection
c. Risk acceptance
d. Contingency planning
There is a definite link between the level of risk an enterprise encounters and project time frame.
Select one:
a. true
b. false
If review of a project's status indicates that EV = $400, AC = $400, and PV = $500, the project is:
Select one:
a. On budget, behind schedule
b. On budget, ahead of schedule
c. Over budget, behind schedule
d. Over budget, ahead of schedule
The bottom-most level of the WBS -- the level at which project budget and schedule data are captured -- is called:
Select one:
a. Work package
b. Code of accounts
c. Budget baseline
d. Change control level
In risk management, insurance is an example of
b.Risk deflection
Insurance is a way of transferring the risk i.e risk deflection
There is a definite link between the level of risk an enterprise encounters and project time frame.
Correct answer is True
Longer the project duration, higher chance of risk affecting project
If review of a project's status indicates that EV = $400, AC = $400, and PV = $500, the project is:
SPI = EV/PV = 400/500 = 0.8
SPI <1 suggests that project is behind schedule
CPI = EV/AC = 400/400 = 1
CPI = 1 suggests that project is on budget
Correct answer is a. On budget, behind schedule
The bottom-most level of the WBS -- the level at which
project budget and schedule data are captured -- is
called:
correct answer is a. Work package
In risk management, insurance is an example of: Select one: a. Risk avoidance b. Risk deflection...
to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...
Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC, are all cumulative. Acronyms: BCWS (Budgeted Cost of Work Scheduled) is equal to PV (Planned Value). BCWP (Budgeted Cost of Work Performed) is equal to EV (Earned Value). AC (Actual Cost) is the actual costs that we pay for the works. Variances: Schedule variance: when BCWP - BCWS is negative, the project is behind schedule, when the value is 0, it is on schedule,...
Please solve these questions by choosing the correct
answer
25 B) Work Breakciown Siructure is: A) A hierarchically-organized depiction of the project organization ) A hierarchical representation of project risks 5 C D) A hierarchical structure of resource categories A deliverables-oriented decomposition of the project work Based on your experience with three similar past projects, you estimate an 8-10 month implementation time frame for a new project. What is this type of estimation technique called? A) Three-Point Estimating B) Bottom-Up...
You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...
Question 2 Identify the one INCORRECT statement regarding project Risk Management. Group of answer choices A. A risk contingency plan is not executed if the risk never happens. B. The owner of a risk is responsible for watching over and/or resolving the risk. C. The risk register is the "log" of all risks - open or closed. D. A risk mitigation strategy is used to clean up after the risk has happened. E. Risk management is the responsibility of everyone...
solv
rroject Manager You are required to estimate the time to paint a large wall. You know it takes two hour one square foot of wall. The wall has an area of 30 square foot. So you estimate that hours to paint the wall. Which estimation model are you using? A) Bottom-up J S , J UB Parametric C) Analogous v ie j oy - D) Expert judgment Cost baseline is usually represented using which curve or line? A) S...
Select the ONE INCORRECT statement about a "Risk Assessment Worksheet." Group of answer choices A. This worksheet identifies the mitigation strategies and the contingency plans for managing the risk. B. This worksheet includes a "risk category" to help in categorizing this risk along with all of the other risks the project manager is managing. C. This worksheet contains a "timeline" of when the risk may occur to help with prioritizing this risk along with all of the other risks the...
26) The Farm Fresh Egg project was too great for one person to pull off. The construction costs for the coop and chicken run were enormous and the sinister threat of avian flu hung over the area like a black cloud. It was only through the combined efforts of Matsushita Chickenworks and the City of Edmond that the project would be undertaken, since they would be able to: A) Minimize the risk C) Accept the risk B) Transfer the risk...
The Farm Fresh Egg project was too great for one person to pull off. The construction costs for the coop and chicken run were enormous and the sinister threat of avian flu hung over the area like a black cloud. It was only through the combined efforts of Matsushita Chickenworks and the City of Edmond that the project would be undertaken, since they would be able to: A) Minimize the risk B) Transfer the risk. C) Accept the risk D)...