Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
|
Activity |
Normal Time(weeks) |
Crash Time(weeks) |
Normal Cost |
Total Cost with Crashing |
Immediate Predecessor(s) |
|
A |
44 |
33 |
$ 2 comma 000$2,000 |
$ 2 comma 650$2,650 |
long dash— |
|
B |
22 |
11 |
$ 2 comma 200$2,200 |
$ 3 comma 000$3,000 |
long dash— |
|
C |
33 |
33 |
$ 500$500 |
$ 500$500 |
long dash— |
|
D |
88 |
44 |
$ 2 comma 400$2,400 |
$ 2 comma 720$2,720 |
A |
|
E |
66 |
33 |
$ 1 comma 000$1,000 |
$ 1 comma 450$1,450 |
B |
|
F |
33 |
22 |
$ 3 comma 200$3,200 |
$ 4 comma 700$4,700 |
C |
|
G |
44 |
22 |
$ 1 comma 400$1,400 |
$ 1 comma 900$1,900 |
D, E |
a) Based on the given information regarding the activities for the project, the project length =
1616
weeks.b) The total cost required for completing this project on normal time =
$1270012700.
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
▼
.The cost of the project based on the first activity selected for crashing will increase by
$nothing.
d) The maximum weeks by which the project can be reduced by crashing =
▼
weeks.Total cost of crashing the project to minimum (or maximum weeks possible) =
$nothing.
a) Critical path is the longest path = ADG = 4 + 8 + 4 = 16 weeks
b) Total cost = 2000 + 2200 + 500 + 2400 + 1000 + 3200 + 1400 = $12700
c) D has lowest crashing cost, hence can be crashed by 1 week at cost of (2720 - 2400) / 4 = $80
d) Crashing A , D and G to maximum i.e. A by 1 week, D by 4 week and G by 2 weeks.
Total cost = Crash cost - Normal cost = 2650 - 2000 + 2720 - 2400 + 1900 - 1400 = $1470
The new critical path is BEG = 2 + 6 + 2 = 10 weeks , so we need to reduce it by 1 week. Reduce E by 1 week at cost of (1450-1000)/3 = 150
Hence, total cost = 1470 + 150 = $1620 for project duration of 9 weeks.
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity A Normal Time Crash Time Normal (weeks) (weeks) Cost 4 3 $2,000 2 $2,100 $750 Total Cost with Immediate Crashing Predecessor(s) $2,650 - $2,800 - $750 B 2 3 $2.400 $2,680 Ā $900 3 § $1,200 3 $900 $3,200 § $4,600 $9,500 $2,000...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...
Development of Version 20 of a particular accounting software product is being considered by Jose Noguera's technology form in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Immediate Predecessor(s) Activity Normal Time Crash Time Normal (weeks) (weeks) Cost $2,200 $2,200 5750 $2,300 $900 $3.000 $1,600 Total Cost with Crashing $2,850 $3.000 5750 $2.580 $1,200 $4.500 52.200 D.E d) The maximum weeks by which the project can be reduced by crashing =...
oblem S.ST evelopmient of Version 2 0 of a particular accounting software product is being considered by Jose Noguera's ompletion of this projedt are listed in the following table: technology firm in Baton Rouge. The activities necessary to Total Cost Normal Time Crash Time Normal with (weeks) Cost Crashing Immediate Predecessors) S2,000 $2.600 S2,300 $3,100 S750 $750 S2,500 $2.780 $1,000 $1,375 $3.000 S4,200 $1400 $2.000 D E a) Based on the given information regarding the activities for the project,the project...
1) Based on the given information regarding the activities for
the project, the project length= ___ weeks.
2) The total cost required for completing this project on normal
time= $____
3) For reducing the duration of the project by one week, the
activity that should be crashed first is activity ___.
4) The cost of the project based on the first activity selected
for crashing will increase by $___.
5) The maximum weeks by which the project can be reduced...
Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing...
Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks). Activity Immediate Predecessor a m b A -- 2 5 8 B A 3 6 9 C A 4 7 10 D B 2 5 14 E D 3 3 3 F C 6 8 10 G E, F 1 1 1 H C 6 10 14 I G,...
Problem 3.28 - Bookmatch Problem The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 11 B, C $ 400 B 11 E $ 100 C 44 F $ 200 E 22 F $ 300 F (end) 22 long dash— $ 400 Suppose that Rafay is only given...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...