Question

At the Hard Rock Café, like many organizations, project management is a key planning tool. Tomasso...

At the Hard Rock Café, like many organizations, project management is a key planning tool. Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within 5-month planning horizon. Tomasso identifies activities, their immediate predecessors and time estimates as shown in the table below. As a chief project manager, you have been asked to prepare a report for your company. This report needs to address the concerns of the following: (a) Introduction (b) An explanation of the model and the methodology used (i.e. CPM and PERT). (c) Display your estimated outputs using tables and graphs as well as network diagram. (d) A discussion of the results estimated. (e) Any other comments you feel relevant to the issues being addressed. (f) Conclusion and recommendations. HINT: 1) Determine the project network, critical path, expected time duration. 2) What is the probability that the project can be completed within 5 months? . Table1: Managing Hard Rock’s Rockfest Activity Activity Description Immediate Predecessor Duration (days) o- m- p a Finalize site and building contracts - 1-10-15 b Set police and fire security plan a 1-5-8 c Hire director a 3-5-7 d Develop site plan c 10-14-21 e Set venue capacity d 5-10-12 f Set TV deal c 1-2-4 g Plan for TV camera placement f 3-5-7 h Select local promoter a 6-14-20 i Passes and stage credentials h 3-6-10 j Sound and staging h 15-22-30 k Power, plumbing, AC, toilet services a 3-10-15 l Hire operations manager h 14-25-40 m Hire production manager l 7-12-20 n Hire sponsor coordinator m 10-15-25 o Finalize sponsors n 30-45-60 p Target headline entertainers l 3-7-10 q Target support entertainers p 2-5-8 r Travel accommodations for talent q 10-12-16 s Define signage for sponsors r,o 2-4-7 t Ticketmaster contract p 10-18-21 u Travel accommodations for staff p 1-2-3 v On-site ticketing k,b,g,e,i,j 0.5-0.5-0.5 w Final control s,t,u,v 0.5-0.5-0.5 son - w

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Project scheduling with uncertain activity times (Optimistic, Most likely, Pessimistic)

a - 1 10 15
b a 1 5 8
c a 3 5 7
d c 10 14 21
e d 5 10 12
f c 1 2 4
g f 3 5 7
h a 6 14 20
i h 3 6 10
j h 15 22 30
k a 3 10 15
l h 14 25 40
m l 7 12 20
n m 10 15 25
o n 30 45 60
p l 3 7 10
q p 2 5 8
r q 10 12 16
s r,o 2 4 7
t p 10 18 21
u p 1 2 3
v k,b,g,e,l,j 0.5 0.5 0.5
w s,t,u,v 0.5 0.5 0.5
son w 0 0 0

Expected time of each activity,

Activity to tm tp te=(to+4⋅tm+tp)/6 σ2=(tp-to/6)2
a 1 10 15 9.33 5.44
b 1 5 8 4.83 1.36
c 3 5 7 5 0.44
d 10 14 21 14.5 3.36
e 5 10 12 9.5 1.36
f 1 2 4 2.17 0.25
g 3 5 7 5 0.44
h 6 14 20 13.67 5.44
i 3 6 10 6.17 1.36
j 15 22 30 22.17 6.25
k 3 10 15 9.67 4
l 14 25 40 25.67 18.78
m 7 12 20 12.5 4.69
n 10 15 25 15.83 6.25
o 30 45 60 45 25
p 3 7 10 6.83 1.36
q 2 5 8 5 1
r 10 12 16 12.33 1
s 2 4 7 4.17 0.69
t 10 18 21 17.17 3.36
u 1 2 3 2 0.11
v 0.5 0.5 0.5 0.5 0
w 0.5 0.5 0.5 0.5 0
son 0 0 0 0 0

The earliest and latest expected time for each activity is calculated by considering the expected time te

Activity Immediate Predecessors Duration
a - 9.33
b a 4.83
c a 5
d c 14.5
e d 9.5
f c 2.17
g f 5
h a 13.67
i h 6.17
j h 22.17
k a 9.67
l h 25.67
m l 12.5
n m 15.83
o n 45
p l 6.83
q p 5
r q 12.33
s r,o 4.17
t p 17.17
u p 2
v k,b,g,e,l,j 0.5
w s,t,u,v 0.5
son w 0

Edge and it's preceded and succeeded node

Edge Node1 → Node2
a 1→2
c 2→3
h 2→7
k 2→9
b 2→19
d 3→4
f 3→6
e 4→5
d 5→10
d 5→19
g 6→19
j 7→8
l 7→10
i 7→19
v 8→17
d 9→19
d 10→8
m 10→11
p 10→14
n 11→12
o 12→13
s 13→16
q 14→15
t 14→16
u 14→17
r 15→13
d 16→17
w 17→18
son 18→19

The critical path of the project is: 1-2-7-10-11-12-13-16-17-18-19 and critical activities are a,h,l,m,n,o,s,d,w,son.
The total project time is 126.67

The probability that the project would be completed in 5 months i.e. 5*30 = 150 days

The project duration required is 126.67 = Summation of Mean

Summation of Variance = 91.94, Summation of Std. Deviation = Square root of Variance = 9.588

In this case, there is 99.25% chance that the project will be over in 150 days.

Add a comment
Know the answer?
Add Answer to:
At the Hard Rock Café, like many organizations, project management is a key planning tool. Tomasso...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...

  • QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are s...

    QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...

  • 3 Global Warming Antarctic Research Project Months.... (5000) 7 G 9 6 Plane 10 points 13...

    3 Global Warming Antarctic Research Project Months.... (5000) 7 G 9 6 Plane 10 points 13 portor 2 15 7 10 K 15 15 L 16 eBook 5 C7 Here 0 5 27 0 F 10 Purchase clothing 3 10 0 Tavel 0 10 5 15 7 15 1 16 References 3 8 14 J 15 0 А 3 0 Pry plan 0 To 6 Tai 0 093 925 131 14 14 1 15 5 D 6 6 11 H...

  • (15. Doug Casey is in charge of planning and coordinating next spring's sales management training program...

    (15. Doug Casey is in charge of planning and coordinating next spring's sales management training program for his company. Doug listed the following activity information for this project: Immediate Predecessor M Time (weeks) Most Probable Activity Optimistic 1.5 2.0 Pessimistic 2.5 2.0 2.5 6.0 2.0 Description Plan topic Obtain speakers List meeting locations Select location Finalize speaker travel plans Make final check with speakers Prepare and mail brochure Take reservations Handle last-minute details BD Ε B, D G F, H...

  • 2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10...

    2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10 8 K 9 8 7 L 10 6 5 M 3 3 3 N KM 9 5 1 O KM 10 7 4 P LN 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will...

  • Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus...

    Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...

  • Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

    Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....

  • A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8...

    A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?

  • A senior manager has finished reviewing the latest draft of an upcoming project. the following table...

    A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened. Activity Precedes Normal Time. (week) Crashing Costs ($000) 1st...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT