MTBF ( mean time between failure) = 45 hours

Availability ( of machine) = 0.90

We have to find MTTR ( mean time to failure)

As formula for availability is

Availability = MTBF/ ( MTBF+ MTTR)

0.90 = 45 / ( 45+ MTTR)

Thus MTTR = (45/ 0.90) - 45

= 50 - 45 = 5

Thus mean time to failure (MTTR) is 5 hours.

.

Add a comment
Know the answer?
Add Answer to:
Consider a CNC machine in an automated production line that has a mean time between failure...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Part I A full shift of production was scheduled to run on machine X. Production was stopped for 2...

    just #3 Part I A full shift of production was scheduled to run on machine X. Production was stopped for 20 minutes due to a machine failure, 10 minutes for a bin change, 30 minutes for a quality concern requiring a tool repair. Assumptions: A) A day- 8 hours with 20 minutes break time B) A total of 1200 parts is processed per day and only 6 is rejected/scraped C)- The ideal cycle time established by engineering or the equipment...

  • A manufacturer of disk drives for notebook computers wants a MTBF of at least 50,000hours. Recent...

    A manufacturer of disk drives for notebook computers wants a MTBF of at least 50,000hours. Recent test results for 12 units were one failure at 8,000 hours, two at 20,000 hours, and two more at 48,000 hours. The remaining units were still running at 60,000 hours. Determine the following: a)Percent of failures? = b) Number of failures per unit-hour = c) The mean time between failures? (MTBF) is the expected time between a repair and the next failure of a...

  • Problema #1 ( 10 points) A system has a mean time to repar (MTTR) of 30...

    Problema #1 ( 10 points) A system has a mean time to repar (MTTR) of 30 minutes, and a mean time between unscheduled maintenance actions (MTBF) of 60 hours. The intended utilization (actual hours of operation to meet the customer demand for the output) of the system is 4800 hours per year. determine 1. How many unscheduled maintenance actions are to be expected each year? 2. How many hours of unscheduled maintenance are to be expected each year 3. If...

  • Consider a production line with three single-machine stations in series. Each has processing times with mean...

    Consider a production line with three single-machine stations in series. Each has processing times with mean two hours and standard deviation of two hours. a. Suppose we run this line as a push system and release jobs into it at a rate of 0.45 per hour with arrival variability given by Ca = 1. What is the average WIP in the line? b. Compute the throughput of this line if it is run as a CONWIP line with a WIP...

  • The guidance system of a ship is controlled by a computer that has three major modules....

    The guidance system of a ship is controlled by a computer that has three major modules. In order for the computer to function properly, all three modules must function. Two of the modules have reliabilities of .87, and the other has a reliability of .97. a.What is the reliability of the computer? (Round your answer to 4 decimal places.) Reliability            b. A backup computer identical to the one being used will be installed to improve overall reliability. Assuming...

  • The average time between failures of a laser machine is exponentially distributed with a mean of...

    The average time between failures of a laser machine is exponentially distributed with a mean of 40,000 hours. a) What is the expected time until 4th failure? b) What is the probability that the time to the 5th failure is greater than 80,000 hours?

  • A production station has a naturally occurring rate of unexpected breakdowns. The mean time between interruptions...

    A production station has a naturally occurring rate of unexpected breakdowns. The mean time between interruptions is 6 hours. The average repair time is 20 minutes, and the CV for repair time is 1.75. The mean natural processing time is 10 minutes with standard deviation 1 minute. a. What is the effective processing time and the CV of effective process time? b. If the arrival rate to the station is 5 jobs per hour, what is the station’s utilization? c....

  • Benny's Arcade has five video game machines. The average time between machine failures is 50 hours.​...

    Benny's Arcade has five video game machines. The average time between machine failures is 50 hours.​ Jimmy, the maintenance​ engineer, can repair a machine in 15 hours on average.The machines have an exponential failure​ distribution, and Jimmy has an exponential​ service-time distribution. a. ​Jimmy's utilization is     . (Enter your response rounded to three decimal​ places.) b. The average number of machines out of​ service, that​ is, waiting to be repaired or being repaired is nothing machines. ​(Enter your response rounded...

  • “I’m not sure we should lay out $305,000 for that automated welding machine,” said Jim Alder,...

    “I’m not sure we should lay out $305,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $85,000 for software and installation, and another $49,200 per year just to maintain the thing. In addition, the manufacturer admits it would cost $48,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...

  • HW 12LC: Inventory Saved Help Save&Exit Submit 2 The Grinell Machine Shop makes a line of metal tables. Some of these tables are carried in finished goods inventory. A particular table has the fo...

    HW 12LC: Inventory Saved Help Save&Exit Submit 2 The Grinell Machine Shop makes a line of metal tables. Some of these tables are carried in finished goods inventory. A particular table has the following characteristics Sales- 300 per year · Setup cost = $1200 per setup (this includes machine setup for all the different parts in the table) Carrying cost 20 percent per year Item cost $25 20 points Print a. How many of these tables should be made in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT