Question

A.   True/False/Fill-in-the-blanks T/F.    Gantt chart can be used to visually see when major milestones are, when...

A.   True/False/Fill-in-the-blanks

  1. T/F.    Gantt chart can be used to visually see when major milestones are, when tasks have been completed, the projected length of a task and relationships among all project tasks.
  2. T/F. All projects are temporary and undertaken to create a product, service, exceed customer expectation or result that is unique
  3. T/F.   The Delphi technique is a quick and economical way to estimate the duration and cost of project activities.  

  1. T/F.   A requirements management plan should describe how requirements activities will be planned, tracked, and reported

B. Multiple Choices

1. What is true for modern project management? Project managers need...

a)         ... to have a strict standing in negotiating

b)         ... to show experience in managing business partners

c)         ... to be team players and facilitators instead of "bosses"

d)         ... to be strongly linked to local traditions

2. Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives. Which stage of team development can be difficult to overcome in such a situation?

a)         Storming from Forming, Storming, Norming, Performing

b)         Panic from Enthusiasm, Panic, Hope, Solution

c)         Kickoff from Assignment, Kickoff, Training, Communicating

d)         Frustration from Direction, Frustration, Cooperation, Collaboration

3. Resource Planning consists of:   

  1. People
  2. Management
  3. Equipment
  4. Quantities

4. The Project QA includes:

  1. Quality planning, quality assurance, and quality control make up the three of the five process of project quality management
  2. QA in project management is about an overall process of improvements on a project and having them produced without errors
  3. QA establishes standards for how project quality will be appraised, and checks the effectiveness of project operations against baselines to identify shortcomings or gaps in project processes.
  4. All of the above
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

A.   True/False/Fill-in-the-blanks

  1. Gantt chart can be used to visually see when major milestones are, when tasks have been completed, the projected length of a task and relationships among all project tasks ✓ True
  2. all projects are temporary and undertaken to create a product, service, exceed customer expectation or result that is unique. ✓ True
  3. The Delphi technique is a quick and economical way to estimate the duration and cost of project activities. ✓ false (Delphi technique is expensive and is suitable for qualitative data collection and research.)
  1. A requirements management plan should describe how requirements activities will be planned, tracked, and reported. ✓True

B. Multiple Choices

1)What is true for modern project management? Project managers need,

✓ c)to be team players and facilitators instead of "bosses"

(Modern project manager must participate in the tasks to better guide the members and have concern towards them by facilitating their needs. They should not use bossism, because members have capabilities and are well experienced to undertake their responsibilities. They need support and motivation. Not an authoritative style of control)

2)Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives. Which stage of team development can be difficult to overcome in such a situation?

✓a) Storming from Forming, Storming, Norming, Performing

(These phases are included in team development. Other options are not part of it.)

3) Resource Planning consists of:

✓ d) quantities. (These quantities have number of labours, equipment and materials, that makes up the resources.)

4) The Project QA includes

✓ d) all of the above

(All the options are self explanatory.)

Please like the answer, it will encourage me.

Add a comment
Know the answer?
Add Answer to:
A.   True/False/Fill-in-the-blanks T/F.    Gantt chart can be used to visually see when major milestones are, when...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • First, read the article on "The Delphi Method for Graduate Research." ------ Article is posted below...

    First, read the article on "The Delphi Method for Graduate Research." ------ Article is posted below Include each of the following in your answer (if applicable – explain in a paragraph) Research problem: what do you want to solve using Delphi? Sample: who will participate and why? (answer in 5 -10 sentences) Round one questionnaire: include 5 hypothetical questions you would like to ask Discuss: what are possible outcomes of the findings from your study? Hint: this is the conclusion....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT