How does Planned Value (PV) differ from Budget-at-Completion (BAC)? Suppose you have a scheduled project activity...

How does Planned Value (PV) differ from Budget-at-Completion (BAC)? Suppose you have a scheduled project activity with a total duration of 12 weeks and an activity budget of $1,200. Assuming the planned expenditure rate is constant throughout the activity duration, what is PV at the end of the fourth week? At the end of the tenth week? At the end of the twelfth week?

Suppose now the planned expenditure rate is: $50 for each of the 1st two weeks; $100 for each of the 3rd and 4th weeks; $125 for each of the 5th and 6th weeks; $150 for each of the 7th and 8th weeks; $125 for week 9; and $75 for each of weeks 10 through 12. What is PV at the end of the fourth week? At the end of the tenth week? At the end of the twelfth week?

Project Management/finance

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Planned value is a quantity that can be measured at any time during the project, based on the planned expenditure at that length of time, while budget at completion is the total budget allocated for project.

Planned activity budget per week = 1200/12 =100

PV at the end of the fourth week= 4x100 =400

PV at the end of the tenth week =10x100 =1000

PV at the end of the twelfth week =12x100 =1200

With the new system

PV at the end of the fourth week=50x2+100x2 =300

PV at the end of the tenth week= 50x2+100x2 +125x2+150x2+125+75 = 1050

PV at the end of the twelfth week = 50x2+100x2 +125x2+150x2+125+75x3 =1200

Add a comment
Know the answer?
Add Answer to:
How does Planned Value (PV) differ from Budget-at-Completion (BAC)? Suppose you have a scheduled project activity...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Topic: PV vs. BAC How does Planned Value (PV) differ from Budget-at-Completion (BAC)? Suppose you have...

    Topic: PV vs. BAC How does Planned Value (PV) differ from Budget-at-Completion (BAC)? Suppose you have a scheduled project activity with a total duration of 12 weeks and an activity budget of $1,200. Assuming the planned expenditure rate is constant throughout the activity duration, what is PV at the end of the fourth week? At the end of the tenth week? At the end of the twelfth week? Suppose now the planned expenditure rate is: $50 for each of the...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT