Question

) A firm is planning to set up an assembly line to assemble 40 units per...

) A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks that precede each task are contained in the following table.

Task

Preceding Task

Time to perform (min.)

A

--

.69

B

A

.55

C

B

.92

D

B

.59

E

B

.70

F

B

1.10

G

C, D, E

.75

H

G, F

.43

I

H

.29

(a) Draw a network diagram of precedence relationships.

(b) Compute the required cycle time per unit in minutes.

(c) Compute the theoretical minimum number of workstations required to produce 40 units per hour.

(d) Balance this line using the longest processing time heuristic.

(e) What is the efficiency of the line obtained in part d?

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
) A firm is planning to set up an assembly line to assemble 40 units per...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per...

    Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...

  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • The desired daily output for an assembly line is 540 units. This assembly line will operate...

    The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • A small electronics company assembles power supplies for use in computers, printers and FAX machines. They...

    A small electronics company assembles power supplies for use in computers, printers and FAX machines. They want to set up an assembly line to make their operation more efficient and plan to use line balancing with the incremental utilization heuristic. The demand for power supplies is 200 per hour, and the productive time per hour is 52 minutes. Task Tasks that must immediately preceede time to perform task A - 0.56 B A 0.34 C A 0.11 D A 0.09...

  • Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line...

    Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line that must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 1: Table 1 Work Element Time (sec.) Immediate Predecessor(s) A 40 NONE B 30 A C 50 A D 40 B E 6 B F 25 C G 15 C H 20 D, E I 18 F, G J 30 H,...

  • Swoosh Snowboard Company must set up an assembly Ins for snowboards. Forecasts show that 600 units...

    Swoosh Snowboard Company must set up an assembly Ins for snowboards. Forecasts show that 600 units per day shou id be produced . The plant operates two eigt-hour sihits esch day and runs the Ine conbnuoushy durnng both shits. The 1asks requred, task times, and precedence relationships are as folows 27 26 60 C, E.F b. What is the tek: time? c. What is the thearetical number of workstations? Round up your answer to the next whole numbar.) d. Assign...

  • An assembly line with 17 tas ks is to be balanced. The longest task is 2.4...

    An assembly line with 17 tas ks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 17 minutes. The line will operate for 474 minutes per day. a. What is the OT? minutes minutes b. What is the minimum cycle time? c. What is the maximum cycle time? minutes d. What is the range of output that is theoretically possible for the line? to units e. What is the minimum number...

  • QUESTION 37 A company is designing a product layout for a new product. It plans to...

    QUESTION 37 A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Task Predecessor Time (seconds) 50 А B А 20 С А 26 D 40 B, C C E 30 a. Draw the network described in the table. b. What is the required...

  • 4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you...

    4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you have been asked to bal- ance the assembly line, given the following task times and precedence relationships. Assume that cycle time is 1.3 minutes per unit. Task Duration (minutes) 0.2 Immediate Follower 0.4 0.3 1.3 oooo s T 0.1 0.8 0.3 1.2 a. Do each of the following: i. Draw the precedence network. ii. Assign the tasks to workstations using the heuristic rule "Assign...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT