Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below:
| Task | Time (seconds) | Predecessor |
| A | 13 | - |
| B | 4 | A |
| C | 10 | B |
| D | 10 | - |
| E | 6 | D |
| F | 12 | E |
| G | 5 | E |
| H | 6 | F, G |
| I | 7 | H |
| J | 5 | H |
| K | 4 | I, J |
| L | 15 | C, K |
a) Determine the maximum and minimum cycle times. b) Determine the required cycle time to produce 1400 agents per day. c) What is the minimum number of stations needed? d) Draw a precedence diagram. Use the cells in Excel to enter the durations and add arrows to indicate the precedence relationships. e) Assign tasks to stations in order of most following tasks first, if there is a tie, use the task with the longest processing time first. f) Determine the average utilization and the percentage idle time of the assembly line.
a) Determine the maximum and minimum cycle times.
Maximum Cycle time = total time of completing al the task by single worker = total task time = 97 seconds
Minimum Cycle time = highest task time = 15 seconds of activity J
b) Determine the required cycle time to produce 1400 agents per day.
Demand = 1400 agents per day
Available time = 420 minutes per day = 420 x 60 = 25200 seconds per day
Cycle time = Available time/Demand = 25200/1400= 18 seconds per unit
Cycle time = 18 seconds per agent
c) What is the minimum number of stations needed?
Total work content =97 seconds
Theoretical number of workstation required = Total work content/Cycle time = 97/18 = 5.38
Minimum theoretical number of WS = 6
d) Draw a precedence diagram.

e) Assign tasks to stations in order of most following tasks first, if there is a tie, use the task with the longest processing time first.
By applying most following tasks method, the task is assigned the workstation first which is having highest no. of following task.
The assignment for workstation is as follows:
|
Task |
Time (seconds) |
Predecessor |
No, of following tasks |
|
A |
13 |
- |
3 |
|
B |
4 |
A |
2 |
|
C |
10 |
B |
1 |
|
D |
10 |
- |
8 |
|
E |
6 |
D |
7 |
|
F |
12 |
E |
6 |
|
G |
5 |
E |
6 |
|
H |
6 |
F, G |
4 |
|
I |
7 |
H |
2 |
|
J |
5 |
H |
2 |
|
K |
4 |
I, J |
1 |
|
L |
15 |
C, K |
0 |
|
Station |
Task |
Cycle time available |
Time (Seconds) |
Time left (Seconds) |
Ready tasks (# followers) |
|
A(3),D(8) |
|||||
|
1 |
D |
18 |
10 |
A(3),E(7) |
|
|
E |
8 |
6 |
2 |
A(3),F(5),G(5) |
|
|
2 |
F |
18 |
12 |
A(3),G(5) |
|
|
G |
6 |
5 |
1 |
A(3),H(4) |
|
|
3 |
H |
18 |
6 |
A(3),I(2),J(2) |
|
|
I |
12 |
7 |
A(3),J(2) |
||
|
J |
5 |
5 |
0 |
A(3),K(1) |
|
|
4 |
A |
18 |
13 |
K(1),B(2) |
|
|
B |
5 |
4 |
1 |
K(1),C(1) |
|
|
5 |
K |
18 |
4 |
C(1) |
|
|
C |
14 |
10 |
4 |
L(0) |
|
|
6 |
L |
18 |
15 |
3 |
|
|
Total idle time |
11 |
f) Determine the average utilization and the percentage idle time of the assembly line.
Utilization = Total work content/(# of workstation x cycle time) x 100
Utilization = 97/(6 x 18) x 100
Utilization = 89.81 %
%idle time = 100 – Utilization = 100 – 89.91% = 10.19%
%idle time = 10.19%
Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...
The operations manager of an instruments company is balancing an
assembly line. The company needs to build 96 instruments per
24-hour day. The assembly line activities are:
a. Draw the precedence diagram.
b. If the daily (24-hour) production rate is 96 units, what is
the greatest possible cycle time?
c. If the cycle time after allowances is given as 10 minutes,
what is the daily (24-hour) production rate?
d. With a 10-minute cycle time, what is the theoretical minimum
number...
Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line that must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 1: Table 1 Work Element Time (sec.) Immediate Predecessor(s) A 40 NONE B 30 A C 50 A D 40 B E 6 B F 25 C G 15 C H 20 D, E I 18 F, G J 30 H,...
EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt. Five hundred wagons are required per day. Production time per day is 420 minutes, and the assembly steps and times for the wagon are given in Exhibit 8.9A. Assignment: Find the balance that minimizes the number of workstations, subject to cycle time and precedence constraints SOLUTION I. Draw a precedence diagram. Exhibit 8.9B illustrates the sequential relationships identi- fied in Exhibit 8.9A. (The length...
Information regarding tasks in an assembly line run for an 8-hour shift each day is provided: Task Proceeding Task (s) Tme (min) A - 5 B - 3 C - 2 D A 1 E B 4 F C 6 G D,E 7 H G 5 I F,G 6 J H,1 4 K I 3 a)What is the theoretical minimum number of stations for a shift output of 40 units? B)if the line is balanced according to the desired cycle...
The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...
Stanford Rosenberg Computing wants to establish an
assembly line for producing a new product, the Personal Digital
Assistant (PDA). The tasks, task times, and immediate predeces-
sors for the tasks are as follows:
Rosenberg’s goal is to produce 200 PDAs per hour.
a) What is the cycle time?
b) What is the theoretical minimum for the number of work-
stations that Rosenberg can achieve in this assembly line?
c. Draw a diagram of the production process.d. With the diagram that...
) A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks that precede each task are contained in the following table. Task Preceding Task Time to perform (min.) A -- .69 B A .55 C B .92 D B .59 E B .70 F B 1.10 G C, D, E .75 H G, F .43 I H .29...
2. Show all the steps for the question to be worth any
marks.
The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...
Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job are 7, 4, 7, 8, 9, 4, 3, and 6 minutes, and the cycle time is 8 minutes?
1. [Layout Strategy-Line Balancing] The call center department of Jax-steel company needs to service 3,000 calls per 40-hour workweek. The process of servicing calls can be broken down into the six stations listed above. The precedence and time requirements for each element are as follows in the table below. The manager wants a new operational analyst to draw and label a precedence diagram for the service process. Finally, the manager needs to balance the line, calculate the efficiency of the...