Bank Boston has a branch at Bryant College. The branch is busiest at the beginning of the college year when freshmen and transfer students open accounts. This year, freshmen arrived at the office at a rate of 40 per day (assume 8-hour days). On average, it takes the Bank Boston staff person about ten minutes to process each account application. The bank is considering having one or two tellers. Each teller is paid $12 per hour and the cost of waiting in line is assumed to be $8 per hour. By how much will the addition of one staff reduce the waiting time?
options:
1)6388
2)7357
3)6762
4)7983
pl rate if it helped
Total Cost = Cw x L + Cs x s
Cw = cost of customer waiting time per time period
L = average number customers in system
Cs = cost of servers per time period
s = number of servers
If s = 1,
Total Cost = Cw x L + Cs x s = .833 hours
If s = 2,
Total Cost = Cw x L + Cs x s = .035 hours
Hence, if second teller is added to serve then the waiting time will be reduced to = .833 hours - .035 hours = .798 hrs
the correct option is
(4) .7983
Bank Boston has a branch at Bryant College. The branch is busiest at the beginning of...
Bank Boston has a branch at Bryant College. The branch is busiest at the beginning of the college year when freshmen and transfer students open accounts. This year, freshmen arrived at the office at a rate of 40 per day (assume 8-hour days). On average, it takes the Bank Boston staff person about ten minutes to process each account application. The bank is considering having one or two tellers. Each teller is paid $12 per hour and the cost of...
Bank Boston has a branch at Bryant College. The branch is busiest at the beginning of the college year when freshmen and transfer students open accounts. This year, freshmen arrived at the office at a rate of 40 per day (assume 8-hour days). On average, it takes the Bank Boston staff person about ten minutes to process each account application. The bank is considering having one or two tellers. Each teller is paid $12 per hour and the cost of...
Bank Boston has a branch at Bryant College. The branch is busiest at the beginning of the college year when freshmen and transfer students open accounts. This year, freshmen arrived at the office at a rate of 40 per day (assume 8-hour days). On average, it takes the Bank Boston staff person about ten minutes to process each account application. The bank is considering having one or two tellers. Each teller is paid $12 per hour and the cost of...
Allegheny Bank has a branch at the local community college. The branch is the busiest at the beginning of the college year when freshman open accounts. This year, freshman arrived at the office at a rate of 3 every twelve minutes. On average, it takes the Allegheny Bank staff person about 2.5 minutes to process each account application. The bank is considering having one or two tellers. Each teller is paid $15 per hour and the cost of waiting in...
The operations manager of a soon-to-open branch of a large bank is in the process of configuring teller operations. Currently some branches have a separate teller line for customers who have a single transaction, while other branches do not have separate lines. A separate teller line can help reduce the number of complaints about long waits that have been received at some branches. Because the demographics differ from location to location, a system that works at one branch will not...
Consider a bank branch that has three distinct customer arrival patterns throughout the day, as measured by average arrival rates (below) Morning (8:30 11:30): 40/hour Lunch (1:30-1:30): 60/hour Afternoon (1:30 4:00): 3 35/hour. Regardless of the time of day, the average time it takes for a teller to serve customers is 2 minutes, 52 seconds Because of competition with other banks in the area, management has determined that they want to keep the average customer wait before service to be...
Customers arrive at bank according to a Poisson process with rate 20 customers per hour. The bank lobby has enough space for 10 customers. When the lobby is full, an arriving customers goes to another branch and is lost. The bank manager assigns one teller to customer service as long as the number of customers in the lobby is 3 or less. She assigns two tellers if the number is more than 3 but less than 8. Otherwise she assigns...
A bank with a branch located in a commercial district of a city has developed an improved process for serving customers during the noon to 1 P.M. lunch period. The waiting time (operationally defined as the time elapsed from when the customer enters the line until he or she reaches the teller window) of all customers during this hour is recorded over a period of one week. A random sample of 15 customers is selected, and the results (in minutes)...
Q4. What changes would you suggest making to the process? Why?
(CLO3)
1 of 2 Case Study Assignment METROPOLITAN COLLEGE Professors P. Fraser Johnson and Robert D. Klassen wrote this case solely to provide material for class discussion. The authors de not intend to illustrate either effective or ineffective handing of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality Copyright © 2009. Ivey Management Services Version (A) 2009-12-14 Mary Clark, manager...
Closing Case 1 Football Teams Use Virtual Reality The Problem College and professional football teams have a unique set of problems. First and foremost, teams would like to reduce the physical wear and tear of drills and practices on their players. In the National Football League (NFL), the most recent Collective Bargaining Agreement (2011) reduced the number of off-season practices, prohibited training camp “two-a-day” practices, and limited the number of contact practices in both the preseason and the regular season....