Consider a project network that begins with activity A and is followed by activity B. Activity A takes 6 days to finish. If the earliest start time for activity B is 6 days and the latest start time for it is 10 days, activity B has a slack of _____. 4 days 16 days 10 days 12 days
ANSWER:
Slack time = latest start time of activity b - earliest start time of activity b = 10 - 6 = 4
so the correct answer is option a that is 4 days.
ANSWER:
Slack time = latest start time of activity b - earliest start time of activity b = 10 - 6 = 4
so the correct answer is option a that is 4 days.
Consider a project network that begins with activity A and is followed by activity B. Activity...
.8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...
a.) Create project network for activites A thru G
b.) Then compute on the network above, the correct Activity on
Arrow format (AOA), the earliest start, earliest finish, latest
start, and latest finish times for project.
a n b b Activity C, E E A Activity А 6 B 2 с 8 D 5 E 6 8 8 12 6 3 9 E Immediate Predecessor(s) G 3 3 5 Н 2 2 2 I 5 5 5 J 4 7...
Given is a CPM project network diagram as shown below.
Activity
Start
A
B
C
D
E
F
G
H
End
day
0
5
6
9
6
9
8
5
4
0
a) The Project Completion time = days.
b) The Earliest Start time, ES, of Activity G = days.
c) The Latest Finish time, LF, of Acitivity C = days..
d) The critical activities are = (ex. Fill in answer as: ABCD)
End Start
QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a) Represent the project by means of a simple network diagram. (b) Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times. (c) Identify the critical path. ...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 7 7 N/A B none 3 2 $500 C A 5 3 $1000 D A, B 6 4 $2000 E C, D 4 3 $1250 F D 3 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...
Consider the following set of activities: Time Predecessor Activity Required Activities A 5 None B 4 A C 5 B D 8 B E 9 C F 6 C,D G 8 D H 3 E,F,G a. Draw the CPM network for this problem. b. Calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities. c. What is the earliest time that the project can be completed? d. If the project needed to be completed...
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)
A project manager discovers that his team has neglected to
complete the network diagram for the project. the network diagram
is shown below. however the project manager has some information
available, specifically that each activity a-g, has a different
duration between one and seven weeks. also the slack time for each
of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...