Palomar Battery Company expects to operate at 75% of full capacity during April. The total manufacturing costs for April for the production of 60,000 batteries are budgeted as follows:
Direct materials $ 75,000
Direct labor 960,000
Variable factory overhead 111,000
Fixed factory overhead 288,000
Total manufacturing costs $1,434,000
The company has an opportunity to submit a bid for 17,500 batteries to be delivered by April 30 to a government agency. If the contract is obtained, it is anticipated that the additional activity will not interfere with normal production during April or increase the selling administrative experiences.
SOLUTION
(A) The April budgeted cost per battery for the production of 60,000 batteries = $23.9 per battery
Total Budgeted cost =Direct material + Direct labor+ Variable factory overhead+ Fixed factory overhead
= 75,000 + 960,000 + 111,000 + 288,000 = 1,434,000
Budgeted cost per battery of 60,000 batteries =Total budgeted cost / Total production
= $1,434,000 / 60,000 = $23.9
(B) The unit cost below which Palomar Battery Company should not go in bidding on the government contract is = $19.1 per unit
Total variable cost = Direct material + Direct labor+ Variable factory overhead
= 75,000 + 960,000 + 111,000 = 1,146,000
Variable cost per battery = 1,146,000 / 60,000 = $19.1
Palomar Battery Company expects to operate at 75% of full capacity during April. The total manufacturing...
Accepting Business at a Special Price Palomar Battery Company expects to operate at 88% of full capacity during April. The total manufacturing costs for April for the production of 35,200 batteries are budgeted as follows: Direct materials $435,600 Direct labor 160,200 Variable factory overhead 44,840 Fixed factory overhead 91,520 Total manufacturing costs $732,160 The company has an opportunity to submit a bid for 2,000 batteries to be delivered by April 30 to a government agency. If the contract is obtained,...
Accepting Business at a Special Price Palomar Battery Company expects to operate at 90% of full capacity during April. The total manufacturing costs for April for the production of 38,700 batteries are budgeted as follows: Direct materials $465,800 Direct labor 171,200 Variable factory overhead 47,990 Fixed factory overhead 135,450 Total manufacturing costs $820,440 The company has an opportunity to submit a bid for 2,000 batteries to be delivered by April 30 to a government agency. If the contract is obtained,...
Power Serve Company expects to operate at 85% of productive capacity during April The total manufacturing costs for April for the production of 30,000 batteries are budgeted as follows: Direct materials $285,000 Direct labor 104,000 Variable factory overhead 31,000 Fixed factory overhead | 58,000 Total manufacturing costs $478,000 The company has an opportunity to submit a bid for 2000 batteries to be delivered by April 30 to a government agency. If the contract is obtained, it is anticipated that the...
Power Serve Company expects to operate at 85% of productive capacity during April The total manufacturing costs for April for the production of 30,000 batteries are budgeted as follows: Direct materials $285,000 Direct labor 104,000 Variable factory overhead 31,000 Fixed factory overhead | 58,000 Total manufacturing costs $478,000 The company has an opportunity to submit a bid for 2000 batteries to be delivered by April 30 to a government agency. If the contract is obtained, it is anticipated that the...
Accepting Business at a Special Price Power Serve Company expects to operate at 85% of productive capacity during July. The total manufacturing costs for July for the production of 33,150 batteries are budgeted as follows: Direct materials $523,000 Direct labor 192,300 53,780 Variable factory overhead Fixed factory overhead 108,000 Total manufacturing costs $877,080 The company has an opportunity to submit a bid for 2,000 batteries to be delivered by July 31 to a government agency. If the contract is obtained,...
Accepting Business at a Special Price Forever Ready Company expects to operate at 90% of productive capacity during July. The total manufacturing costs for July for the production of 38,700 batteries are budgeted as follows: Direct materials Direct labor Variable factory overhead Fixed factory overhead $502,600 184,800 51,770 103,000 Total manufacturing costs $842,170 The company has an opportunity to submit a bid for 2,000 batteries to be delivered by July 31 to a government agency. If the contract is obtained,...
Accepting Business at a Special Price Power Serve Company expects to operate at 88% of productive capacity during July. The total manufacturing costs for July for the production of 36,960 batteries are budgeted as follows: Direct materials $595,600 Direct labor 219,000 Variable factory overhead 61,352 Fixed factory overhead 123,000 Total manufacturing costs $998,952 The company has an opportunity to submit a bid for 2,000 batteries to be delivered by July 31 to a government agency. If the contract is obtained,...
Accepting Business at a Special Price Forever Ready Company expects to operate at 88% of productive capacity during May. The total manufacturing costs for May for the production of 32,560 batteries are budgeted as follows: Direct materials $261,300 Direct labor 96,100 Variable factory overhead 26,808 Fixed factory overhead 54,000 Total manufacturing costs $438,208 The company has an opportunity to submit a bid for 2,000 batteries to be delivered by May 31 to a government agency. If the contract is obtained,...
Accepting Business at a Special Price Power Serve Company expects to operate at 82% of productive capacity during July. The total manufacturing costs for July for the production of 34,440 batteries are budgeted as follows: Direct materials $409,800 Direct labor 150,700 Variable factory overhead 42,200 Fixed factory overhead 84,000 Total manufacturing costs $686,700 The company has an opportunity to submit a bid for 3,000 batteries to be delivered by July 31 to a government agency. If the contract is obtained,...
Calculator eBook Accepting Business at a Special Price doty dur ng My, The total men fating aets for My for the podud n of 2S OO bate e se bodged a Portable Power Company expects to operate at 80% of productive follows: $162,500 Direct materials Direct labor 70,000 Vaniable factory overhead 30,000 Fixed factory overhead 112,500 Total manufacturing costs $375,000 The company has an opportunity to submit a bid for 2,500 batteries to be delivered by July 31 to a...