Question

alls Corners Construction Limited (BCCL) specializes in the construction of commercial buildings. A typical construction proj
0 0

> Construction of commercial buildings requires detailed planning, accurate budgeting, and efficient execution to achieve successful results. From offices to retail and mixed-use developments, cost control is critical at every stage. Working with a professional commercial estimator helps contractors and developers prepare precise estimates, reduce financial risks, and keep projects on schedule while maintaining quality standards.

nathanangel Thu, Jan 15, 2026 12:45 AM

Add a comment Improve this question Transcribed image text
Answer #1

a)

Cost of total job is $1,500,000

Billing on contract issued to date is $1,115,000

Percentage of contract is completed = Bill issued contract/ Cost of total Job*100

= $1,115,000/$1,500,000*100

= 74.33%

b)

Billing on contract issued date $1,115,000

Labour $207,000

Materials $519,000

Material stored on the job site but not installed $ 51,000

Indirect cost $ 75,000 $ 852,000

Gross Profit $ 263,000

Gross profit of the 2016 = $ 263,000

c)

Particular Debit Credit

Accounts Receivable A/C Dr $1,115,000

To Services Revenue A/C Cr $1,115,000

Labour A/C Dr $207,000

To Cash A/C Dr        $207,000

Materials A/C Dr $5,70,000

To Cash A/C Cr $5,70,000

Indirect cost A/C Dr $ 75,000

To Cash A/C Cr $ 75,000

Profit and loss A/C Dr $ 263,000

To Capital A/C Cr   $ 263,000

Total $2,230,000 $2,230,000

d)

Particular Debit Credit

Services Revenue A/C Dr $980,000

To Bank A/C Cr $980,000

Accounts Receivable A/C Dr $135,000

To Services Revenue A/C Cr $135,000

Labour A/C Dr $207,000

To Cash A/C Dr $207,000

Materials A/C Dr $5,70,000

To Cash A/C Cr $5,70,000

Indirect cost A/C Dr $ 75,000

To Cash A/C Cr $ 75,000

Profit and loss A/C Dr $ 263,000

To Capital A/C Cr   $ 263,000

Total $2,230,000 $2,230,000

e)

Assume that latest forecast on total at end of the 2016 was $2,050,000 profit  =$550,000

Forecast Total cost was 2016 was $1,50,0000 profit =$263,000

Income loss for 2016    =$2,87,000

Add a comment
Know the answer?
Add Answer to:
alls Corners Construction Limited (BCCL) specializes in the construction of commercial buildings. A typical construction project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question No. 3 (15 marks) Napanee Construction Company (NCC) has entered into a non-cancellable contract with...

    Question No. 3 (15 marks) Napanee Construction Company (NCC) has entered into a non-cancellable contract with Raglan Company to construct a building for $2,100,000. NCC is a public company with a December 31 year-end. NCC has elected to use the Percentage-of-Completion method. The following data are available: 2018 2019 2020 Construction costs incurred to-date $ 400,000 $1,600,000 $1,900,000 Estimated costs to completion 1,400,000 450,000 0 Progress Billings to-date 320,000 1,128,000 652,000 Cash collected to date 300,000 1,050,000 750,000 Required: (Note:...

  • 18.A construction company was hired on a construction project to build a building for $1,800,000. The...

    18.A construction company was hired on a construction project to build a building for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $450,000 $1,100,000 Estimated costs to complete 1,050,000 0 Billing during the year 400,000 1,400,000 Cash collections during the year 300,000 1,500,000 Assume that A recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all journal entries...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...

    Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:                                             2017                                    2018 Current year construction costs                                       $3,300,000                             $ 620,000 Estimated remaining costs to complete                              600,000                                   -0- Current year billings                                                            3,100,000                              1,400,000 Current year collections                                                    3,000,000                                1,500,000 Required: Calculate the following amounts for each method:               Completed Percentage-of Contract Completion                                   2017      2018    2017    2018 a) Gross Profit                                                                                              $             $           $          ...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is...

    n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,600,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2016, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 30,000 Construction in progress $ 100,000 Less: Billings on construction contract (94,000 ) Cost and profit of uncompleted contracts in excess of billings 6,000 Income...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT