| a.) Balance in Work in Process inventory would ne the amount of cost applied till the date of Januray 1. | |||||||
| Balance in Work in Process = | |||||||
| Cost of Direct Material | $5,000.00 | ||||||
| Cost Of Labour | $6,000.00 | ||||||
| Cost of OH | $4,800.00 | ||||||
| TOTAL COST | $15,800.00 | ANS | |||||
| b.) | |||||||
| Prior Year OH Rate | Cost of Beginning Balance of Direct Labour Hour | ||||||
| Cost of Begging Balance of OH | |||||||
| 4800 | |||||||
| 6000 | |||||||
| 0.8 | ANS | ||||||
| Current Year OH Rate | Cost of Direct Labour Hour | ||||||
| Cost of OH | |||||||
| 5600+2800 | |||||||
| 8000+4000 | |||||||
| 8400 | |||||||
| 12000 | |||||||
| 0.7 | ANS | ||||||
| c.) Unit Cost Of Production | Total Cost | ||||||
| No. of Units | |||||||
| 45200 | |||||||
| 2000 | |||||||
| 22.6 | ANS | ||||||
| II.) | |||||||
| Pre Determined Manufacturing OH Rate | 400000 | ||||||
| 150000 | |||||||
| 2.67 | ANS | ||||||
| Amount of Overhead Overapplied | (160000*2.67) - 385000 | ||||||
| 42200 | ANS | ||||||
| Overhead was OverApplied | ANS | ||||||
THANK YOU
HOPING FOR A POSITIVE RESPONSE
Name All questions are worth 20 points I. A job order cost sheet for Ryan Company...
help please
nelurumenda Ajob order cost sheet for Ryan Company is shown below. Job No.92 For 2,000 Units oport Direct Materials Date Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 7,000 6,400 7.000 se 10,000 500 2,800 4,000 21,000 16,200 3,000 15,400 Cost of completed job: Direct materials $16,200 Direct labor 21,000 Manufacturing overhead 15,400 Total cost $52,600 Unit cost ($52,600 + 2,000) $26,30 Unit cost ($52,600 2,000) $26.30 (a) On the basis of the foregoing data, answer the following...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 6,500 6,000 4,200 6,000 8,000 6,800 25 3,000 4,000 18,000 15,500 3,400 14,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (547,900 = 2.000) $15,500 18,000 14,400 $47.900 $23.95 (a) on the basis of the foregoing data, answer the following questions. (1) What was the balance...
A job order cost sheet for Ryan Company is shown below. (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job? Balance in Work in Process Inventory on January 1 _______ (2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year? (b) Prepare summary entries at January 31 to record the current...
A job order cost sheet for Ryan Company is shown
below.
Job No. 92
For 2,000 Units
Date
Direct
Materials
Direct
Labor
Manufacturing
Overhead
Beg. bal. Jan. 1
6,400
6,560
4,592
8
6,560
12
10,000
7,500
25
2,800
27
4,000
3,000
15,760
20,560
15,092
Cost of completed job:
Direct materials
$15,760
Direct labor
20,560
Manufacturing overhead
15,092
Total cost
$51,412
Unit cost ($51,412 ÷ 2,000)
$25.71
(a) On the basis of the foregoing data, answer the following
questions.
(1) What...
A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...
Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials 6,300 7,000 Direct Labor 7,000 For 2,000 Units Manufacturing Overhead 4,900 Date Beg. bal. Jan. 1 8 12 25 27 9,000 7,200 3,000 4,000 20,000 3,200 15,300 16,300 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($51,600 + 2,000) $16,300 20,000 15,300 $51,600 $25.80 (a) On the basis of the foregoing data, answer the...
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 6,300 6,700 4,690 Jan. 1 8 12 25 27 6,700 9,200 7,360 2,600 4,800 3,840 15,60020,700 15,890 Cost of completed job Direct materials $15,600 20,700 15,890 $52,190 $26.10 Direct labor Manufacturing overhead Total cost Unit cost ($52,190 2,000) (a) On the basis of the foregoing data, answer the following questions (1) What was the...
Exercise 2-3
A job order cost sheet for Ryan Company is shown below.
Job No. 92
For 2,000 Units
Date
Direct
Materials
Direct
Labor
Manufacturing
Overhead
Beg. bal. Jan. 1
5,200
6,000
4,200
8
6,000
12
10,000
7,500
25
2,700
27
4,000
3,000
13,900
20,000
14,700
Cost of completed job:
Direct materials
$13,900
Direct labor
20,000
Manufacturing overhead
14,700
Total cost
$48,600
Unit cost ($48,600 ÷ 2,000)
$24.30
(a) On the basis of the foregoing data, answer the following
questions....