Question

Name All questions are worth 20 points I. A job order cost sheet for Ryan Company is shown below Date Beg, bal. Jan. 1$ 5,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1
a.) Balance in Work in Process inventory would ne the amount of cost applied till the date of Januray 1.
Balance in Work in Process =
Cost of Direct Material $5,000.00
Cost Of Labour $6,000.00
Cost of OH $4,800.00
TOTAL COST $15,800.00 ANS
b.)
Prior Year OH Rate Cost of Beginning Balance of Direct Labour Hour
Cost of Begging Balance of OH
4800
6000
0.8 ANS
Current Year OH Rate Cost of Direct Labour Hour
Cost of OH
5600+2800
8000+4000
8400
12000
0.7 ANS
c.) Unit Cost Of Production Total Cost
No. of Units
45200
2000
22.6 ANS
II.)
Pre Determined Manufacturing OH Rate 400000
150000
2.67 ANS
Amount of Overhead Overapplied (160000*2.67) - 385000
42200 ANS
Overhead was OverApplied ANS

THANK YOU
HOPING FOR A POSITIVE RESPONSE

Add a comment
Know the answer?
Add Answer to:
Name All questions are worth 20 points I. A job order cost sheet for Ryan Company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • help please nelurumenda Ajob order cost sheet for Ryan Company is shown below. Job No.92 For...

    help please nelurumenda Ajob order cost sheet for Ryan Company is shown below. Job No.92 For 2,000 Units oport Direct Materials Date Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 7,000 6,400 7.000 se 10,000 500 2,800 4,000 21,000 16,200 3,000 15,400 Cost of completed job: Direct materials $16,200 Direct labor 21,000 Manufacturing overhead 15,400 Total cost $52,600 Unit cost ($52,600 + 2,000) $26,30 Unit cost ($52,600 2,000) $26.30 (a) On the basis of the foregoing data, answer the following...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 6,500 6,000 4,200 6,000 8,000 6,800 25 3,000 4,000 18,000 15,500 3,400 14,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (547,900 = 2.000) $15,500 18,000 14,400 $47.900 $23.95 (a) on the basis of the foregoing data, answer the following questions. (1) What was the balance...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

     A job order cost sheet for Ryan Company is shown below. (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job? Balance in Work in Process Inventory on January 1 _______  (2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year?  (b) Prepare summary entries at January 31 to record the current...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 6,400 6,560 4,592 8 6,560 12 10,000 7,500 25 2,800 27 4,000 3,000 15,760 20,560 15,092 Cost of completed job:    Direct materials $15,760    Direct labor 20,560    Manufacturing overhead 15,092 Total cost $51,412 Unit cost ($51,412 ÷ 2,000) $25.71 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job...

    Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials 6,300 7,000 Direct Labor 7,000 For 2,000 Units Manufacturing Overhead 4,900 Date Beg. bal. Jan. 1 8 12 25 27 9,000 7,200 3,000 4,000 20,000 3,200 15,300 16,300 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($51,600 + 2,000) $16,300 20,000 15,300 $51,600 $25.80 (a) On the basis of the foregoing data, answer the...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 6,300 6,700 4,690 Jan. 1 8 12 25 27 6,700 9,200 7,360 2,600 4,800 3,840 15,60020,700 15,890 Cost of completed job Direct materials $15,600 20,700 15,890 $52,190 $26.10 Direct labor Manufacturing overhead Total cost Unit cost ($52,190 2,000) (a) On the basis of the foregoing data, answer the following questions (1) What was the...

  • Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

    Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,200 6,000 4,200 8 6,000 12 10,000 7,500 25 2,700 27 4,000 3,000 13,900 20,000 14,700 Cost of completed job:    Direct materials $13,900    Direct labor 20,000    Manufacturing overhead 14,700 Total cost $48,600 Unit cost ($48,600 ÷ 2,000) $24.30 (a) On the basis of the foregoing data, answer the following questions....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT