(a)

(b)
Use the Critical Path Method (CPM) to find the critical path as follows:
Forward Pass:
ES of the starting activities = 0
ES of all other activities = Max. (EF of their immediate
predecessors)
EF of an activity = Its ES + Its duration
Backward Pass:
LF of ending activities = Max. (All the EFs)
LF of all other activities = Min. (LS of their immediate
successors)
LS of an activity = Its LF - Its duration
Total slack (or, float) = LF - EF for each activity.
| Activity | Duration | ES | EF | LS | LF | Slack |
| A | 12 | 0 | 12 | 0 | 12 | 0 |
| B | 6 | 0 | 6 | 14 | 20 | 14 |
| C | 10 | 12 | 22 | 14 | 24 | 2 |
| D | 8 | 12 | 20 | 12 | 20 | 0 |
| E | 6 | 12 | 18 | 14 | 20 | 2 |
| F | 10 | 22 | 32 | 24 | 34 | 2 |
| G | 10 | 20 | 30 | 24 | 34 | 4 |
| H | 10 | 20 | 30 | 20 | 30 | 0 |
| I | 4 | 30 | 34 | 30 | 34 | 0 |
| J | 6 | 34 | 40 | 34 | 40 | 0 |
The critical path of a project is composed of activities with zero total slack. So, the critical path is A-D-H-I-J.
(c)
Project duration = LF of the last activity 'J' = 40 weeks
(d)
Slack of 'B' = 14 weeks < the delay of 6 weeks
Slack of 'E' = 2 weeks > the delay of 4 weeks by 2 weeks
Slack of 'G' = 4 weeks < the delay of 5 weeks.
So, the project will be delayed only by 'E' by 2 weeks. So, it will finish in 42 weeks
Kenya Motors Ltd. has listed the following actities as necessary in introducing a new vehicle moc...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...
Mauritius Pharmaceuticals Ltd was undertaking a project for reviewing the packaging of its saline drips. The activities and the duration of each activity are shown in the table below. Activity Completion time (weeks) ACTIVITY Completion time (weeks) A 6 B 9 C 8 D 5 E 10 F 6 G 14 H 11 I 9 The immediate precedence relationships are: Activities D and E follow activity B. Activities A and D follow activity C. Activities G and...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
Problems 3.4.3.14 relate to Project Management Techniques • 3.4 Using the project information listed in the table below: a) Draw the AON network for the construction activity. b) Draw the AOA for the construction activity. ACTIVITY IMMEDIATE PREDECESSOR(S) DURATION (DAYS) A 4 B - 2 с 2 D A 2. E B 3 B 4 F G 2 H с D, E F, G 5 3 -
Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...
Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks). Activity Immediate Predecessor a m b A -- 2 5 8 B A 3 6 9 C A 4 7 10 D B 2 5 14 E D 3 3 3 F C 6 8 10 G E, F 1 1 1 H C 6 10 14 I G,...
Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c, e 2 e b 8 f e 9 g d 5 h f,g 8 Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. The data analysis team members are going to be late delivering some key data points...
Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?