Question

IT PROJECT

Question 2. (Marks: 20) Create a WBS for the project. Given the size of the project, the WBS should include up to the third level and must demonstrate dividing work up to multiple work items. A graphic chart must be used.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

WBS:

Here, I will be working with Mobile APP development project that would assist and benefit south African citizen in consumer behavior category, I have prepared the Work breakdown Structure for this project and WBS is presented below:

Mobile app development in consumer behavior category prepare Requirement documentation build behavioral design Research and d

  • Mobile app development in consumer behavior category
    • prepare Requirement documentation
      • define initial requirements
      • define more detailed requirements
    • build behavioral design
      • design related to functional area
      • design related to how consumers behave in the system.
    • Research and development work
      • define various modules
      • coding related works
      • define various interfaces
    • Testing works
      • prepare reports
      • perform various analysis
    • Implementation works
      • Training initiatives
      • integration with the available system
Add a comment
Know the answer?
Add Answer to:
IT PROJECT
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Create a work breakdown structure

    Create a work breakdown for the project, the WBS should include up to the third level and must demonstrate dividing work up to multiple work items. A graphic chart must be used. Information :You have decided to enter a South African innovative App competition. The competition requires you (and your team) to think of an innovative idea that could lead to the development of an App aimed at assisting and benefiting south African citizens in the following category: (Government services)Some fundamental...

  • Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the...

    Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the Green Computing Research Project. The company’s CIO, Ben, is the project sponsor, and Ito is the program manager for the larger Environmental Technologies Program that this project is part of. Now you need to put together your project team and get to work on this high-visibility project. You will work with Ben to handpick your team. Ben had already worked with the HR department...

  • Create a Work break down structure (WBS) for the following project case. The WBS should be...

    Create a Work break down structure (WBS) for the following project case. The WBS should be organized by either “phase” or “project management process groups.” Break down the work to Level 3. The case description is simple. Thus, go beyond the case description and be creative to include additional detailed tasks.    ---------------[Case] ----------------------- Project for building a new, state-of-the-art multimedia classroom for your organization within the next five months and the budget is $200,000. The classroom should include 40...

  • Create a Work break down structure (WBS) for the following project case. The WBS should be organi...

    Create a Work break down structure (WBS) for the following project case. The WBS should be organized by either “phase” or “project management process groups.” Break down the work to Level 3. The case description is simple. Thus, go beyond the case description and be creative to include additional detailed tasks.    ---------------[Case] ----------------------- Project for building a new, state-of-the-art multimedia classroom for your organization within the next five months and the budget is $200,000. The classroom should include 40 high-end...

  • DESIGN ELECTRONIC SOLUTION

    Question 3. (Marks: 45) Design of the electronic solution using an appropriate tool to construct the activity list/ work package. The electronic solution should include the following tasks: • Project information; • Schedule of the project; • The work pattern (calendar). (Consider eight working hours per day, possible holidays and other non-working days where possible); • Activity duration and possible dependencies; • Milestones; • Predecessors/Gantt chart; • Project summary. Marking Guideline Required Allocation of Marks Setup of the project information....

  • QUESTION 5 When planning a project there are several key points that must be considered. A bar chart based on the work breakdown structure (WBS) of a plant is a very clear means of presenting a pr...

    QUESTION 5 When planning a project there are several key points that must be considered. A bar chart based on the work breakdown structure (WBS) of a plant is a very clear means of presenting a programme of work. Draw a bar chart and a resource chart derived from the bar chart showing all salient values. [14] QUESTION 5 When planning a project there are several key points that must be considered. A bar chart based on the work breakdown...

  • Chapter 5 Make sure to do a Save As and replace yourLastName with your last name....

    Chapter 5 Make sure to do a Save As and replace yourLastName with your last name. (ex. CantrellCh05) Create a WBS using Microsoft Project 2016 and indenting categories appropriately. Assume that the Level 1 category is called Software Project, and that the Level 2 categories are Initiating, Planning, Executing, Monitoring and Con- trolling, and Closing. Under the Executing section, include Level 3 categories of Analysis, Design, Prototyping, Testing, Implementation, and Support. Assume that the Support category includes Level 4 items...

  • 3. Develop a work breakdown structure for the project. Break down the work to Level 3...

    3. Develop a work breakdown structure for the project. Break down the work to Level 3 or Level 4, as appropriate. Use the template on the companion Web site and samples in this text as guides. Print the WBS in list form. Be sure the WBS is based on the project charter earlier, the project scope statement created in Task 2, and other relevant information. 4. Use the WBS you developed in Task 3 to begin creating a Gantt chart...

  • Question 1 (1 point) The project scope statement and resource calendars are inputs to which Project...

    Question 1 (1 point) The project scope statement and resource calendars are inputs to which Project Time Management process? Question 1 options: Sequence Activities Estimate Activity Resources Develop Schedule Control Schedule Question 2 (1 point) Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area? Question 2 options: Project Time Management Project Cost Management Project Scope Management Project Human Resource Management Question 3 (1 point) Units of measure, level of precision, level of accuracy, control thresholds,...

  • In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software applicatio...

    In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software application that you have selected. Prepare the WBS, and submit the file to your instructor. This assignment is due Sunday at 11:59 p.m. All assignments should be uploaded in the Assignment area. Project Software Options There are many project management software applications that are designed to help develop project plans and schedules as well as keeping track of these plans and creating...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT