Question

Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...

Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accommodations for the participants. Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequences, and the time that they would require. Their results are displayed in Table 1. Louis Odaga, the chief clerk, noted that their project had to be completed in 29 days. Whipping out his solar-powered calculator, he added up the time needed. “no,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 12 of us in this office.” “I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at the least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given Table 2.

Table 1 Family Planning Research Center Activities

Activity

Immediate

Predecessor

Time

(Days)

A. Identify faculty and their schedules

---

6

B. Arrange transport to base

---

8

C. Identify and collect training materials

---

4

D. Arrange accommodations

A

3

E. Identify team

A

7

F. Bring in team

B, E

5

G. Transport faculty to base

A, B

3

H. Print program material

C

6

I. Have program materials delivered

H

7

J. Conduct training program

D, F, G, I

10

K. Perform fieldwork training

J

10

Table 2 Family Planning Research Center Costs

Activity

Normal

Time (days)

Crash

Time (days)

Cost per day

to crash ($)

A

6

3

3,000

B

8

4

4,000

C

4

2

3,000

D

3

1

2,000

E

7

3

6,000

F

5

1

2,000

G

3

1

3,500

H

6

4

10,000

I

7

1

7,000

J

10

9

5,500

K

10

5

4,500

Discussion Questions

  1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required network of tasks and define the critical path. What is the length of the project without crashing? Do not just answer, but show the whole process.
  1. If the critical path is longer than 29 days, what is the least additional amounting that Dr. Watage can spend and still achieve this schedule objective (29 days)? Do not just answer, but show the whole process.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

3 Ы 2 А. S 3 3 (8 10 ( Ч 2 о (из

Activity ES EF LS LF Slack
A 0 6 0 6 0
B 0 8 7 15 7
C 0 4 1 5 1
D 6 9 15 18 9
E 6 13 6 13 0
F 13 18 13 18 0
G 8 11 15 18 7
H 4 10 5 11 1
I 10 17 11 18 1
J 18 28 18 28 0
K 28 38 28 38 0

Critical path is AEFJK with duration 38.

Activity slope max crash
A 1000 3
B 1000 4
C 1500 2
D 1000 2
E 1500 4
F 500 4
G 1750 2
H 5000 2
I 1167 6
J 5500 1
K 900 5

Crashing schedule

(i) F can be crashed by 1 day at a cost of 500. Now there are two critical paths CHIJK and AEFJK. Duration is 37.

(ii) K can be crashed by 5 days ata cost of 4500. Duration is now 32.

(iii) I and F can be crashed for 3 days at a cost of 3 x ( 1167+500) = 5000

Duration is now 29. Cost is 500+4500+5000=10000

Add a comment
Know the answer?
Add Answer to:
Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...

    Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control.  These workers already had training in family planning education but must receive specific training regarding the new method of contraception.  Two types of materials must also be prepared: (1) those for use...

  • Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3...

    Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...

  • Question #1: Some of the tasks in this project can be done in parallel. Prepare a...

    Question #1: Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required network of tasks and define the critical path. What is the length of the project without crashing? Do not just answer, but show the whole process. Question #2: If the critical path is longer than 29 days, what is the least additional amounting that Dr. Watage can spend and still achieve this schedule objective (29 days)? Do not just answer,...

  • 5. Imagine that you are in charge of planning a short course for executives wishing to...

    5. Imagine that you are in charge of planning a short course for executives wishing to upgrade their Operations Research skills. The following list of activities is involved: Cost Per ImmediateNormal DescriptionPredecessors (days) Crash Time (days)Reduction Day of Time Activity A Develop course outline 4 S50 Arrange speakers $100 Identify potential locations $150 Choose location 4 $150 Arrange travel for B, D speakers Final confirmation of $200 eakers Advertise course B, D Take rescrvations Arrange welcome party F, H $100...

  • A Not-for-Profit Medical Research Center A Not-for-Profit Medical Research Center You are Alexis, the director of...

    A Not-for-Profit Medical Research Center A Not-for-Profit Medical Research Center You are Alexis, the director of external affairs for a national not-for-profit medical research center that does research on diseases related to aging. The center’s work depends on funding from multiple sources, including the general public, individual estates, and grants from corporations, foundations, and the federal government. Your department prepares an annual report of the center’s accomplishments and financial status for the board of directors. It is mostly text with...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • A Not-for-Profit Medical Research Center A Not-for-Profit Medical Research Center You are Alexis, the director of external affairs for a national not-for-profit medical research center that does resea...

    A Not-for-Profit Medical Research Center A Not-for-Profit Medical Research Center You are Alexis, the director of external affairs for a national not-for-profit medical research center that does research on diseases related to aging. The center’s work depends on funding from multiple sources, including the general public, individual estates, and grants from corporations, foundations, and the federal government. Your department prepares an annual report of the center’s accomplishments and financial status for the board of directors. It is mostly text with...

  • At the Hard Rock Café, like many organizations, project management is a key planning tool. Tomasso...

    At the Hard Rock Café, like many organizations, project management is a key planning tool. Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within 5-month planning horizon. Tomasso identifies activities, their immediate predecessors and time estimates as shown in the table below. As a chief project manager, you have been asked to prepare a report for your company. This report needs to address the concerns...

  • Can someone walk me through manual steps to solve e, f, and g? The Farmer's American...

    Can someone walk me through manual steps to solve e, f, and g? The Farmer's American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table: Time Estimates (weeks) Activity Activity Activity Description Position recruiting System development Predecessor a C A 5 17 ? -- 7 3 12 15 System training...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT