Question

Can someone walk me through manual steps to solve e, f, and g?

The Farmers American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determi


0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

89.44% confidence interval for length of project: Z value corresponding to 94% probability= 1.250 NORMSINV(0.8944) B17 c D E

f)

39 weeks Given time-Expected time Standard deviation 39-33 4+9+1 6 6 VIS 3.87 1.55 Note: Calculate the probability for z valu

Probability of completing the project between 35 and 39 weeks = 93.94% - 69.84% = 24.1%

g. Normal cost of project 4800910030003600 01500 1800 +0+0+0+5000 $ 28800 Crash as shown below Process: Step 1: Determine theA B C D F Activity Cost (S) Activity Time (weeks) Normal time Crash time Normal cost 1 Activity Crash cost Slope 2 7 4,800 6,Activity crashed k Total crash cost k f g a 200 700 700 750 750 1000 1000 250 Cost 5350 Note: Though activity f has a lower c

Add a comment
Know the answer?
Add Answer to:
Can someone walk me through manual steps to solve e, f, and g? The Farmer's American...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Must use AOA PERT/CPM Manual Calculations and show Networks. 10. A farm owner is going to...

    Must use AOA PERT/CPM Manual Calculations and show Networks. 10. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table: Activity Activity Activity Activity Description Predecessor Time Excavate Erect building Install generator Install tank Install maintenance equipment Connect generator and tank to building b.c,d Paint finish Η Check out facility Construct the network for this project and calculate the...

  • For the network shown D(4) B(12) E(6) G(4) C(6) F(5) a-1. Determine the critical path A-C-E-G...

    For the network shown D(4) B(12) E(6) G(4) C(6) F(5) a-1. Determine the critical path A-C-E-G A-C-F-G A-B-D-G A-B-E-G a-2. Determine the early completion time in weeks for the project. Early completion time For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened weeks NORMAL NORMAL CRASH CRASH ACTIVITY TIME COST TIME COST $ 7,300 2$13,400 18,200 6,550 6,800 5,400 9,000 8,400 7 12 6 12,400 10 5,400 4,500 3,200 6,700...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max            Crash cost             Activity                           Predecessors          Time (weeks)             Crash*    per week                   A                                none                                    7                          7         N/A                   B                                none                                    3                          2        $500                   C                                A                                       5                          3      $1000                   D                                A, B                                    6                          4      $2000                   E                                 C, D                                    4                          3      $1250                   F                                D                                       3                          2      $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • The table below defines the activities and the normal time duration for each activities within a...

    The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • I ONLY need help on letters G and I. According to the answers I've tried for...

    I ONLY need help on letters G and I. According to the answers I've tried for these, it is NOT Activity G for the letter G and not $2,120 for letter I. M5_A5. A computer installation project is being reviewed. Assume the project has to be completed in 16 weeks. Crash the project as necessary (crashing one week at a time). The relevant information is in the table below. CRASH STANDARD STANDARD CRASH IMMEDIATE ACTIVITY TIME TIME COST PREDECESSORS COST...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • Problem 5-18 The following CPM network has estimates of the normal time in weeks listed for...

    Problem 5-18 The following CPM network has estimates of the normal time in weeks listed for the activities: CS 103 a. Identify the critical path. O A-C-D-E-G O A-C-D-F-G A-B-D-E-G O A-B-D-F-G b. What is the length of time to complete the project? Number of weeks c. Which activities have slack, and how much? OB, 2 week(s); F, 4 week(s). OC, 3 week(s); F. 3 week(s). OB, 2 week(s): E, 3 week(s). O C. 3 week(s); E, 3 week(s). Here...

  • Question 6 - 8 Activity Depends on А B C D E F G A A...

    Question 6 - 8 Activity Depends on А B C D E F G A A А B C,D D, E, F Duration (Days) Normal Crash 5 4 7 5 8 5 11 8 6 4 4 3 7 5 Cost ($) Normal Crash 500 620 350 500 800 920 1000 1300 600 750 420 500 700 1000 6. Draw the node network for the above project using the following template. For each activity, show the computed value of early...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT