Network Diagram - Critical Path Method: in Hand written Format

|
From the Network Diagram, It is clear that Critical Path is ADEH, as activities on that critical path have zero float, Further, Project needs at least 11 days time to finish as Critical path duration is 11 Days, which is here Maximum time, the critical Path is shown with Bold Arrow |
| Activity | Duration | Early Start | Late Start | Early Finish | Late Finish | Slack or Float Time = Late start - Early Start = Late Finish - Early Finish | Critical path activities Yes or No |
| A | 3 | 0 | 0 | 3 | 3 | 0 | Yes |
| B | 2 | 0 | 1 | 2 | 3 | 1 | No |
| C | 2 | 0 | 4 | 2 | 6 | 4 | No |
| D | 2 | 3 | 3 | 5 | 5 | 0 | Yes |
| E | 4 | 5 | 5 | 9 | 9 | 0 | Yes |
| F | 6 | 2 | 3 | 8 | 9 | 1 | No |
| G | 3 | 2 | 6 | 5 | 9 | 4 | No |
| H | 2 | 9 | 9 | 11 | 11 | 0 | Yes |
| Resource Loading | ||||||||||||||||
| Activity | Duration | Resource | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | |||
| A | 3 | Painter | 1 | 1 | 1 | |||||||||||
| B | 2 | Painter | 1 | 1 | ||||||||||||
| C | 2 | Trimmer | 1 | 1 | ||||||||||||
| D | 2 | Painter | 1 | 1 | ||||||||||||
| E | 4 | Trimmer | 1 | 1 | 1 | 1 | ||||||||||
| F | 6 | Trimmer | 1 | 1 | 1 | 1 | 1 | 1 | ||||||||
| G | 3 | Painter | 1 | 1 | 1 | |||||||||||
| H | 2 | Painter plus Trimmer | 2 | 2 | ||||||||||||
| Total | 3 | 3 | 3 | 3 | 3 | 2 | 2 | 2 | 1 | 2 | 2 | |||||
| Resource Leveling | ||||||||||||||||
| Activity | Duration | Resource | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| A | 3 | Painter | 1 | 1 | 1 | |||||||||||
| B | 2 | Painter | 1 | 1 | ||||||||||||
| C | 2 | Trimmer | 1 | 1 | ||||||||||||
| D | 2 | Painter | 1 | 1 | ||||||||||||
| E | 4 | Trimmer | 1 | 1 | 1 | 1 | ||||||||||
| F | 6 | Trimmer | 1 | 1 | 1 | 1 | 1 | 1 | ||||||||
| G | 3 | Painter | 1 | 1 | 1 | |||||||||||
| H | 2 | Painter plus Trimmer | 2 | 2 | ||||||||||||
| Total | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 1 | 1 | 2 | 2 | ||
After Resource loading and Leveling Project Duration has changed,
The new Project duration = 14 Days, or project needs at least 14 Days time to complete,
there will be new critical path as We have done Resource leveling and considering, there is only one Painter and One Trimmer, The New critical path would be ABGEH
B. Resource Loading (33 pts). The network diagram below represents a project plan. a. b. C....
Plan ME Develop a loading schedule for each resource below. (Figure 8.3) EE ME 0 1 2 3 4 5 6 7 8 9 10 11 12 Fill in the times below for a resource activity schedule. ID/RES ES LSEF LF SL 1-EE Schedule 2.EE Legend ES ID EF 3-ME SL LS DUR LF 4.EE 5-ME 6-ME 7-EE Resource EX8-1 (Static) Given the network plan that... Given the network plan that follows, compute the early, late, and slack times. What...
Chapter - Project Management
This assignment involves creating a Gantt chart using the
GanttProject software.
1) Use the attached example task list to create a new Gantt
chart. Make sure you indicate the task dependencies from the task
list. Use the IDs assigned by the site, not the ones in the
example.
2) Add two new tasks: the 1st between "Programming" and
"Program Test" called "Code Review" with duration 3 days, and the
2nd between “Write User Manual” and “User...
In Exercise 1 Chapter 8, Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now? Could something...
In Exercise 1 Chapter 8, Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now? Could something...
Below is the network diagram for a construction project. Given ONLY THREE (3) workers are available at all times, develop a resource schedule using the parallel heuristics for resource-constrained projects. 0 A 1 1 2 1 1 1 2 4 E 7 0 0 4 3 7 IN نا 7 G 2 c 4 3 0 2 24 1 ON 0 7 00 000 7 1 4 1 F 1 0 B 2 02 o 0 2 2 N ON...
You just completed developing the schedule for your project and got the approval from stakeholders and the sponsor. One of the team members assigned to work on a critical component informs you that she needs additional time to complete her activities as several relevant pieces were missed during planning. Her updated estimate would have no impact on the critical path; thus, the project duration would be the same. The best approach the project manager may take in this situation will...
Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project phase, it has sembled a project planning team and is undertaking discussions with the client to produce a mgheve pct plan. A range of key tasks have been identified and a logical network diagram for high-level the project has been developed. Project task information is provided in the following table (Table...
You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having four backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in 13 months. Develop a resource schedule to see if it is possible to complete the project in 13...
Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...
Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project phase, it has sembled a project planning team and is undertaking discussions with the client to produce a mgheve pct plan. A range of key tasks have been identified and a logical network diagram for high-level the project has been developed. Project task information is provided in the following table (Table...