first activity should be framing and one can not start draywall installation without completing framing work.the next task is finishing and painting. we can carry both installtion and finishing and painting as parallel task by giving one day or two day break for the last event to ensure some part of the preceding activity will be completed so that the next task can be started
the above shown logical
network is built by CPM method of project planning.
in the above network 2 days have been left with no work to ensure some part of installation of drywall to be completed to carry finishing works and also to satisfy the given condition "each activity should be finished atleast 1 day after finishing of its predecessor activity".
in the above network critical path has been shown with black line.the network is telling that after framing activity, installation, finishing amd painting of the drywall are carried as parallel activities to reduce project duration.
Therefore from the above network the total project duration is 10 days.(critical path duration)
CPM -5% A Subcontractor must do the following: a) Framing (5 days) b) Drywall Installation (4...
Must use AOA PERT/CPM
Manual Calculations and show Networks.
10. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table: Activity Activity Activity Activity Description Predecessor Time Excavate Erect building Install generator Install tank Install maintenance equipment Connect generator and tank to building b.c,d Paint finish Η Check out facility Construct the network for this project and calculate the...
Consider the following set of activities: Time Predecessor Activity Required Activities A 5 None B 4 A C 5 B D 8 B E 9 C F 6 C,D G 8 D H 3 E,F,G a. Draw the CPM network for this problem. b. Calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities. c. What is the earliest time that the project can be completed? d. If the project needed to be completed...
Construction methods
Do 4-3
5. Answer the following two questions, 5-1 and S-2 5-1) Draw the "node" network diagram and perform the CPM calculations based on the end-of-day convention to complete the table entries. (20 points) (Note: use very simple node design for the network diagram: for example, box or circle.) Activity! Duration | Predecessors | EST E-LS 1 LF- B. BFF/2 | 구 | 11 | 15 | 19 E, F SS12 5 13 it is assumed that the...
Choose an event or significant task and prepare an activities
list following a format similar to that used in the text, Table
9.3, Chapter 9, page 391. Be sure to include the immediate
predecessors.
Then, create a project network similar to that shown in Figure
9.7, Chapter 9, page 392.
Do NOT include times for the activities and do NOT attempt to
determine the critical path.
Examples of events you might consider (there are many
others):
formal dinner for 5...