Based on given data, we prepare a project network diagram as shown below:

The above network diagram in the form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per the legend shown in the top-left corner.
EST = Early start time
LST = Late start time
EFT = Early finish time
LFT = Late finish time
SLK = Slack = LST - EST or Slack = LFT - EFT
The EST of an activity = EFT of previous activity
EFT of an activity = EST + Duration
Similarly LFT & LST are calculated during backward pass.
There are multiple paths in the diagram:
1-4-6-8
1-5-8
2-8
3-7-8
Out of the above paths, path 1-4-6-8 is the longest path and has 0 slack. Hence, this is the critical path.
As seen from above, the expected duration is 28 periods.
We complete the table in Excel as shown below:

We have to find the probability of completion in 25 weeks
We find Z as:
Z =
Variance over critical path = Variance for Activity 1 + Variance for Activity 4 + Variance for Activity 6 + Variance for Activity 8 = 3 + 2 + 10 + 1 = 16
Hence, Z =
= -1.50
We find Probability in Excel as:

The above answer in terms of formula is shown below:

----------------------------------------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.
Kindly upvote the answer as it will be encouraging for me to keep answering further questions!!!
A7-3 (Static) The expected times and variances... The expected times and variances for the project activities...
A7-3 (Algo) The expected times and variances... The expected times and variances for the project activities are given below. Complete the table showing which activities are critical ID 1 Pilot production 2 Select channels of distrib 3Develop mktg. program 4Test market 5 Patent 6 Full production 7 Ad promotion 8Release Description Predecessor None None None Variance Critical? te 6 40 18 4 15 4 16 2,5,6,7 What is the probability of completing the project in 29 periods? (Do not round...
A7-3 (Algo) The expected times and variances... The expected times and variances for the project activities are given below. Complete the table showing which activities are critical ID Description Predecessor te Variance Critical? 1 2 3 None Pilot production Select channels of distrib. Develop mag program Test market None 4 5 Patent 6 Full production Ad promotion Rese What is the probability of completing the project in 32 periods? Hint Use the ENORM S DISTI, TRUE) function in Excel to...
The expected times and variances for the project activities follow. Complete the table showing which activities are critical ID Predecessor te Critical? 1 None 6 Variance 3 4 2. None 22 3 None 4 2 4 Description Pilot production Select channels of distrib. Developmktg program Test market Patent Full production Ad promotion Release 4 1 1 2 5 14 5 6 7 4 10 22 13 2 3 2,5,6,7 B 2 1 ces What is the probability of completing the...
4. For the following project, the expected times and variances for the project activities are given. a. Draw the AON diagram. b. What is the probability of completing the project in 30 time periods? (10 points) Activity ID Predecessor ariance [(b-a)/6) 4 1 2 Naluna 2, 5, 6, 7 Z Value Probability Z Value Probability +0.0 9893
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
The estimated times and immediate predecessors for the activities in a project at Caesar Douglas’s screening company are given in the following table. Assume that the activity times are independent. All times are in weeks. Activity Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A -- 9 10 11 B -- 4 10 16 C A 9 10 11 D B 5 8 11 What is the critical path based on expected times? You may use any...
(50 points) Data regarding the activities for a project are presented below. The times are in weeks The critical path for this project is A-D-H-I-J-K 2. Pessimistic Time Most Likely Time y Optimistic Time 8 16 10 8 10 12 8 14 5 6 2 a. Determine the standard deviation of the critical path. b. Determine the probability of completing the project in 38 weeks or less c What is the probability of completing the project in 32 weeks or...
please
help!!
The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K. Activity Optimistic Time Most Likely Time Pessimistic Time A 7 9 14 B 2 2 8 C 8 12 16 D 3 5 10 E 4 6 8 F 6 8 10 G 2 3 4 H 2 2 8 I 6 8 16 J 4 6...
The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...