The target cost of a fixed price contract is $50,000. The price of the contract is targeted at $75,000 with a ceiling price of $100,000. The share ratio is 80/20. What is the Point of Total Assumption of this procurement?
$100,000
$125,000
$81,250
$112,500
Answer:$81,250
Explanation: target cost= 50,000
triget price= 75,000
ceiling price= 100,000
buyer share ratio= 0.80
PTAPoint of Total Assumption = ((Ceiling Price – Target Price) / Buyer’s Share Ratio) + Target Cost
PTA= ((100000 – 75000) / 0.8) + 50000 = $81,250
Please ask, if you have any doubts through the comment section. Do rate the answer
The target cost of a fixed price contract is $50,000. The price of the contract is...
A Fixed Price Incentive Fee (FPI) contract has a Target Cost of $130,000, a Target Profit of $15,000, a Target Price of $145,000, a Ceiling Price of $160,000 and a share ratio of 80/20. e.) How much profit does the seller make if the actual cost is $120,000? f.) What is the ROS? g.) How much profit does the seller make if the actual cost is $ 165,000? h.) How much profit does the seller make if the actual cost...
5. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target Cost 1,000,000 Target Profit for Seller 100,000 Target Price 1,100,000 Ceiling Price 1,300,000 Share Ratio 80% buyer-20% Evaluate the point of total assumption (PTA, breakpoint) of the project.
5. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target Cost 1,000,000 Target Profit for Seller 100,000 Target Price 1,100,000 Ceiling Price 1,300,000 Share Ratio 80% buyer-20% Evaluate the point of total assumption (PTA, breakpoint) of the project.
22. Note this is the same information from #10: A contract is Fixed Price Incentive Fee. The target fee is $10,000, and the target price is $100,000. The share ratio is 80/20 and the actual cost is $85,000. The ceiling price is $110,000. a. What is the PTA? b. What does this mean? Be specific using your answer from 22a. (2 points)
A contract has the following data: Target Cost = 300K Target Fee = 15K Max Fee = 20K Min Fee = 5K Share Ratio = 80/20 Actual Cost = 360K What is the final price that would be paid to the contractor?
6. A contract for your project is Firm Fixed Price. The negotiated price is $50,000. If the actual cost is $40,000, what is the total payment owed to the supplier?
Break even point in units = Fixed cost / Contribution Margin per unit Target Profit = (Fixed Cost + Target Profit) / Contribution Margin Per Unit Break even point in dollars = Fixed cost / Contribution Margin % After tax target profit = (Fixed Cost) + (Target Profit) / (1 - Tax Rate) / Contribution Margin Per Unit Break even on a cash basis = (Fixed cost - Non cash items) / Contribution margin per unit Variable cost per unit...
For cost plus incentive fee contract, calculate the final payment made to the supplier, Target cost = $100,000 Target profit = $12,000 Maximum fee = $14,000 Minimum fee = $9,000 Sharing below target (customer/supplier) = 80/20 Sharing above target (customer/supplier) = 70/30 1) How much will the contractor be reimbursed if the cost of performing the work is $85,000? 2) How much will the contractor be reimbursed if the cost of performing the work is $120,000?
Assignment Exercise 18–3: Target Operating Income Acme Medical Supply Company desires a target operating income amount of $100,000, with assumption inputs as follows: Desired (target) operating income amount = $100,000 Unit price for sales = $80 Variable cost per unit = $60 Total fixed cost = $60,000 Compute the required revenue to achieve the target operating income and compute a contribution income statement to prove the totals.
Company XYZ has 2 fixed price contracts for 2 different clients. The company has enough capacity for both contracts but is uncertain whether they will be profitable. Using the information below, a) calculate the activity-based costs and profits for each contract (this requires more than one step) and b) calculate the profit for each job using absorption costing, absorbing overheads using molding hours: Enter all answers in number format without commas, decimals, or dollar signs. Customer AAA BBB Component Type...