A Fixed Price Incentive Fee (FPI) contract has a Target Cost of $130,000, a Target Profit of $15,000, a Target Price of $145,000, a Ceiling Price of $160,000 and a share ratio of 80/20.
e.) How much profit does the seller make if the actual cost is $120,000?
f.) What is the ROS?
g.) How much profit does the seller make if the actual cost is $ 165,000?
h.) How much profit does the seller make if the actual cost is $ 100,000?
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
A Fixed Price Incentive Fee (FPI) contract has a Target Cost of $130,000, a Target Profit...
A fixed price contract where the price is $150,000. a.) How much profit does the seller make if the actual cost is $120,000? b.) ROS? c.) How much profit does the seller make if the actual cost is $160,000? d.) ROS? e.) How much profit does the seller make if the actual cost is $100,000? f.) ROS?
22. Note this is the same information from #10: A contract is Fixed Price Incentive Fee. The target fee is $10,000, and the target price is $100,000. The share ratio is 80/20 and the actual cost is $85,000. The ceiling price is $110,000. a. What is the PTA? b. What does this mean? Be specific using your answer from 22a. (2 points)
For cost plus incentive fee contract, calculate the final payment made to the supplier, Target cost = $100,000 Target profit = $12,000 Maximum fee = $14,000 Minimum fee = $9,000 Sharing below target (customer/supplier) = 80/20 Sharing above target (customer/supplier) = 70/30 1) How much will the contractor be reimbursed if the cost of performing the work is $85,000? 2) How much will the contractor be reimbursed if the cost of performing the work is $120,000?
5. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target Cost 1,000,000 Target Profit for Seller 100,000 Target Price 1,100,000 Ceiling Price 1,300,000 Share Ratio 80% buyer-20% Evaluate the point of total assumption (PTA, breakpoint) of the project.
5. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target Cost 1,000,000 Target Profit for Seller 100,000 Target Price 1,100,000 Ceiling Price 1,300,000 Share Ratio 80% buyer-20% Evaluate the point of total assumption (PTA, breakpoint) of the project.
The target cost of a fixed price contract is $50,000. The price of the contract is targeted at $75,000 with a ceiling price of $100,000. The share ratio is 80/20. What is the Point of Total Assumption of this procurement? $100,000 $125,000 $81,250 $112,500
A contract has the following data: Target Cost = 300K Target Fee = 15K Max Fee = 20K Min Fee = 5K Share Ratio = 80/20 Actual Cost = 360K What is the final price that would be paid to the contractor?
A Client has decided to use a Cost Plus Incentive Fee contract price arrangement to motivate the Contractor to be more efficient and productive in executing the project. The Contractor’s Fee will be calculated based on a Sliding Fee approach by considering a $110,000,000 target price and a 4% Base (R). Calculate Contractor’s Fee and Total Payment to the Contractor for two following scenarios: Scenario 1) Actual Cost of Project = $102,000,000 Scenario 2) Actual Cost of Project = $124,000,000
A Cost Plus Fixed Fee (CPFF) Contract has an estimated Cost of $55,000,000 and a Fixed Fee of $5,000,000. What is the final price and the ROS if : a.) The actual cost is $48,000,000 b.) The actual cost is $75,000,000
Calculate the organization's total cost for the following scenario: The organization has signed a cost-plus-incentive-fee contract. The sharing formula is 90/10 (90 percent by buyer). The seller estimate of allowable expenses is $150,000. The target fee is set at $10,000. The maximum fee is $19,750. The minimum fee is $5,000. a. (15 points) Calculate the result if the project is completed by the seller at a cost of $146,000. b. (10 points) Calculate the result if the project is completed...