A Client has decided to use a Cost Plus Incentive Fee contract price arrangement to motivate the Contractor to be more efficient and productive in executing the project. The Contractor’s Fee will be calculated based on a Sliding Fee approach by considering a $110,000,000 target price and a 4% Base (R).
Calculate Contractor’s Fee and Total Payment to the Contractor for two following scenarios:
Given data :-
Target price = $110,000,000
Base (R) = 4%
Scenario 1). :-
Actual cost of project = $102,000,000
Contractor fee :--
Now , formula for calculating sliding fee by sliding approach is
Sliding fee = R (T - A)
Where , R= base Percentage value
T = target price
A= actual cost of project
Sliding fee = 4% ×(110,000,000 - 102,000,000)
Sliding fee = (4/100) ×( 80,000,000)
fee = $ 320,000C
Contractor fee =(actual cost of project)+(sliding fee)
Contractor fee= (102,000,000 + 320,000)
Contractor fee= $ 102,320,000
Total payment of contractor:-T
Total payment of contractor is
= (contractor fee)+(overheads percentage× contractor fee)
Where overhead percentage includes contactor profit for their work which is between 10 to 20 %
Taking overhead percentage= 20%
Now, total payment of contractor is
= (102,320,000) + ( 20% × 102,320,000)
Total payment of contractor = $ 122,784,000
Scenario 2) :--
Actual cost of project= $124,000,000
Contractor fee :-
Sliding fee = R × (T - A)
Sliding fee = 4% ×( 110,000,000 - 124,000,000)
= (4/100) ×( -14,000,000)
Sliding fee= - $560,000
this means the contractor is penalized by the amount of $ 560,000
Contractor fee= (124,000,000 - 560,000)
Contractor fee= $123,440,000
Total payment of contractor is:-
Total payment of contractor
= Contractor fee + (overhead× contractor fee)
= 123,440,000 + ( 20% × 123,440,000)
Total payment of contractor= $148,128,000
A Client has decided to use a Cost Plus Incentive Fee contract price arrangement to motivate...
For cost plus incentive fee contract, calculate the final payment made to the supplier, Target cost = $100,000 Target profit = $12,000 Maximum fee = $14,000 Minimum fee = $9,000 Sharing below target (customer/supplier) = 80/20 Sharing above target (customer/supplier) = 70/30 1) How much will the contractor be reimbursed if the cost of performing the work is $85,000? 2) How much will the contractor be reimbursed if the cost of performing the work is $120,000?
2a) A contractor will be compensated in a construction project using Cost-Plus-Fixed-Fee with Profit Sharing payment scheme. The estimated target cost of the project is $1,250,000, contractor’s fixed fee is $100,000, and the contractor’s percentage of profit/loss sharing is 25%. What is the actual cost of the project that will result in zero profit to the contractor? 2b) A contractor is negotiating a contract with the owner of a new power plant. The contractor estimated that the cost can range...
Calculate the organization's total cost for the following scenario: The organization has signed a cost-plus-incentive-fee contract. The sharing formula is 90/10 (90 percent by buyer). The seller estimate of allowable expenses is $150,000. The target fee is set at $10,000. The maximum fee is $19,750. The minimum fee is $5,000. a. (15 points) Calculate the result if the project is completed by the seller at a cost of $146,000. b. (10 points) Calculate the result if the project is completed...
A sharing arrangement in a “cost plus incentive fee arrangement” should be the same on either side of the target cost (same % sharing to buyer and seller). Question 27 options: True False
A Fixed Price Incentive Fee (FPI) contract has a Target Cost of $130,000, a Target Profit of $15,000, a Target Price of $145,000, a Ceiling Price of $160,000 and a share ratio of 80/20. e.) How much profit does the seller make if the actual cost is $120,000? f.) What is the ROS? g.) How much profit does the seller make if the actual cost is $ 165,000? h.) How much profit does the seller make if the actual cost...
22. Note this is the same information from #10: A contract is Fixed Price Incentive Fee. The target fee is $10,000, and the target price is $100,000. The share ratio is 80/20 and the actual cost is $85,000. The ceiling price is $110,000. a. What is the PTA? b. What does this mean? Be specific using your answer from 22a. (2 points)
5. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target Cost 1,000,000 Target Profit for Seller 100,000 Target Price 1,100,000 Ceiling Price 1,300,000 Share Ratio 80% buyer-20% Evaluate the point of total assumption (PTA, breakpoint) of the project.
5. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target Cost 1,000,000 Target Profit for Seller 100,000 Target Price 1,100,000 Ceiling Price 1,300,000 Share Ratio 80% buyer-20% Evaluate the point of total assumption (PTA, breakpoint) of the project.
A contract has the following data: Target Cost = 300K Target Fee = 15K Max Fee = 20K Min Fee = 5K Share Ratio = 80/20 Actual Cost = 360K What is the final price that would be paid to the contractor?
A Cost Plus Fixed Fee (CPFF) Contract has an estimated Cost of $55,000,000 and a Fixed Fee of $5,000,000. What is the final price and the ROS if : a.) The actual cost is $48,000,000 b.) The actual cost is $75,000,000