For cost plus incentive fee contract, calculate
the final payment made to the supplier,
Target cost = $100,000
Target profit = $12,000
Maximum fee = $14,000
Minimum fee = $9,000
Sharing below target (customer/supplier) = 80/20
Sharing above target (customer/supplier) = 70/30
1) How much will the contractor be reimbursed if the cost of
performing the work is $85,000?
2) How much will the contractor be reimbursed if the cost of
performing the work is $120,000?
1.
Final Fee = Target Fee + (Target Cost - Actual Cost) * Contractor Share = 12000 + (100000-85000)*20% = 12000 + 3000 = $15000
This is more than maximum fee, hence the contractor will get maximum permissible fee i.e. $14000.
2. Final Fee = Target Fee + (Target Cost - Actual Cost) * Contractor Share= 12000 + (100000-120000)*30% = $6000
This is less than minimum fee, hence the contractor will get minimum fee i.e. $9000.
For cost plus incentive fee contract, calculate the final payment made to the supplier, Target cost...
A Fixed Price Incentive Fee (FPI) contract has a Target Cost of $130,000, a Target Profit of $15,000, a Target Price of $145,000, a Ceiling Price of $160,000 and a share ratio of 80/20. e.) How much profit does the seller make if the actual cost is $120,000? f.) What is the ROS? g.) How much profit does the seller make if the actual cost is $ 165,000? h.) How much profit does the seller make if the actual cost...
A Client has decided to use a Cost Plus Incentive Fee contract price arrangement to motivate the Contractor to be more efficient and productive in executing the project. The Contractor’s Fee will be calculated based on a Sliding Fee approach by considering a $110,000,000 target price and a 4% Base (R). Calculate Contractor’s Fee and Total Payment to the Contractor for two following scenarios: Scenario 1) Actual Cost of Project = $102,000,000 Scenario 2) Actual Cost of Project = $124,000,000
Calculate the organization's total cost for the following scenario: The organization has signed a cost-plus-incentive-fee contract. The sharing formula is 90/10 (90 percent by buyer). The seller estimate of allowable expenses is $150,000. The target fee is set at $10,000. The maximum fee is $19,750. The minimum fee is $5,000. a. (15 points) Calculate the result if the project is completed by the seller at a cost of $146,000. b. (10 points) Calculate the result if the project is completed...
2a) A contractor will be compensated in a construction project using Cost-Plus-Fixed-Fee with Profit Sharing payment scheme. The estimated target cost of the project is $1,250,000, contractor’s fixed fee is $100,000, and the contractor’s percentage of profit/loss sharing is 25%. What is the actual cost of the project that will result in zero profit to the contractor? 2b) A contractor is negotiating a contract with the owner of a new power plant. The contractor estimated that the cost can range...
22. Note this is the same information from #10: A contract is Fixed Price Incentive Fee. The target fee is $10,000, and the target price is $100,000. The share ratio is 80/20 and the actual cost is $85,000. The ceiling price is $110,000. a. What is the PTA? b. What does this mean? Be specific using your answer from 22a. (2 points)
A sharing arrangement in a “cost plus incentive fee arrangement” should be the same on either side of the target cost (same % sharing to buyer and seller). Question 27 options: True False
A contract has the following data: Target Cost = 300K Target Fee = 15K Max Fee = 20K Min Fee = 5K Share Ratio = 80/20 Actual Cost = 360K What is the final price that would be paid to the contractor?
5. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target Cost 1,000,000 Target Profit for Seller 100,000 Target Price 1,100,000 Ceiling Price 1,300,000 Share Ratio 80% buyer-20% Evaluate the point of total assumption (PTA, breakpoint) of the project.
5. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target Cost 1,000,000 Target Profit for Seller 100,000 Target Price 1,100,000 Ceiling Price 1,300,000 Share Ratio 80% buyer-20% Evaluate the point of total assumption (PTA, breakpoint) of the project.
MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the stage of completion of its construction act. Total estimated contract costs of their contract are $100 million. In the first year of their contract, ABC Engineering has incurred the following costs: Cost of purchase of raw materials worth $10 million ($5 million of which are unused by the year end) 2. Payment of salaries and wages of $5 million ($1 million of accrued salaries...