A Cost Plus Fixed Fee (CPFF) Contract has an estimated Cost of $55,000,000 and a Fixed Fee of
$5,000,000. What is the final price and the ROS if :
a.) The actual cost is $48,000,000
b.) The actual cost is $75,000,000
| Price = Cost + Fixed Fee | ||||
| 1) Final Price if actual cost is $48,000,000 | ||||
| = $48,000,000 +50,00,000 | ||||
| $ 5,30,00,000 | ||||
| 1) Final Price if the actual cost is $75000000 | ||||
| =$75000000+5000000 | ||||
| $ 8,00,00,000 | ||||
| Feel Free To Discuss Queries. Please Rate | ||||
A Cost Plus Fixed Fee (CPFF) Contract has an estimated Cost of $55,000,000 and a Fixed...
A Fixed Price Incentive Fee (FPI) contract has a Target Cost of $130,000, a Target Profit of $15,000, a Target Price of $145,000, a Ceiling Price of $160,000 and a share ratio of 80/20. e.) How much profit does the seller make if the actual cost is $120,000? f.) What is the ROS? g.) How much profit does the seller make if the actual cost is $ 165,000? h.) How much profit does the seller make if the actual cost...
A Client has decided to use a Cost Plus Incentive Fee contract price arrangement to motivate the Contractor to be more efficient and productive in executing the project. The Contractor’s Fee will be calculated based on a Sliding Fee approach by considering a $110,000,000 target price and a 4% Base (R). Calculate Contractor’s Fee and Total Payment to the Contractor for two following scenarios: Scenario 1) Actual Cost of Project = $102,000,000 Scenario 2) Actual Cost of Project = $124,000,000
2a) A contractor will be compensated in a construction project using Cost-Plus-Fixed-Fee with Profit Sharing payment scheme. The estimated target cost of the project is $1,250,000, contractor’s fixed fee is $100,000, and the contractor’s percentage of profit/loss sharing is 25%. What is the actual cost of the project that will result in zero profit to the contractor? 2b) A contractor is negotiating a contract with the owner of a new power plant. The contractor estimated that the cost can range...
A contract has the following data: Target Cost = 300K Target Fee = 15K Max Fee = 20K Min Fee = 5K Share Ratio = 80/20 Actual Cost = 360K What is the final price that would be paid to the contractor?
Calculate the organization's total cost for the following scenario: The organization has signed a cost-plus-incentive-fee contract. The sharing formula is 90/10 (90 percent by buyer). The seller estimate of allowable expenses is $150,000. The target fee is set at $10,000. The maximum fee is $19,750. The minimum fee is $5,000. a. (15 points) Calculate the result if the project is completed by the seller at a cost of $146,000. b. (10 points) Calculate the result if the project is completed...
22. Note this is the same information from #10: A contract is Fixed Price Incentive Fee. The target fee is $10,000, and the target price is $100,000. The share ratio is 80/20 and the actual cost is $85,000. The ceiling price is $110,000. a. What is the PTA? b. What does this mean? Be specific using your answer from 22a. (2 points)
For cost plus incentive fee contract, calculate the final payment made to the supplier, Target cost = $100,000 Target profit = $12,000 Maximum fee = $14,000 Minimum fee = $9,000 Sharing below target (customer/supplier) = 80/20 Sharing above target (customer/supplier) = 70/30 1) How much will the contractor be reimbursed if the cost of performing the work is $85,000? 2) How much will the contractor be reimbursed if the cost of performing the work is $120,000?
A fixed price contract where the price is $150,000. a.) How much profit does the seller make if the actual cost is $120,000? b.) ROS? c.) How much profit does the seller make if the actual cost is $160,000? d.) ROS? e.) How much profit does the seller make if the actual cost is $100,000? f.) ROS?
Bigelow Contractors signed a contract to construct a storage facility for RGN manufacturing, Inc. The fixed-fee contract specifies that the facility is to be completed in three years. Bigelow uses the percentage-of-completion method (cost-to-cost approach) to account for its construction transactions. Information related to this contract is summarized in the following table. Contract price $ 2,000,000 2018 2019 2020 Actual construction costs incurred during the year $ 900,000 $ 300,000 $ 600,000 Construction costs incurred in prior years 0 900,000...
Which of the following contract types is not appropriate for Commercial Items? a Fixed Price level of Effort (FPLOE) b Cost Plus Fixed Fee (CPFF) c IDIQ Indefinite Quantity Task Order d Firm Fixed Price (FFP)