You are the project manager for a power plant project. You have completed project initiation activities and you are now creating a document that describes processes to document the scope, decompose deliverables into work packages, verify that all work is complete and manage changes to the baseline. What process plan would you choose to perform?
A. Develop project management plan
B. Develop project management life cycle
C. Develop WBS and define scope
D. Develop project charter
Answer : A. Develop project management plan
The only plans given in the option is project management plan. Project management plan comprises of other sub plans which cover fhe content for successfully executing the project. The activities given in question comprise of activities for execution of the project.
Develop project charter is carried out in initiation phase. There is no process like Develop project management life cycle.
Develop WBS and define scope doesn't cover management of changes to baseline. Hence, Develop Project management plan is the answer.
You are the project manager for a power plant project. You have completed project initiation activities...
Question 1 (1 point) The project scope statement and resource calendars are inputs to which Project Time Management process? Question 1 options: Sequence Activities Estimate Activity Resources Develop Schedule Control Schedule Question 2 (1 point) Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area? Question 2 options: Project Time Management Project Cost Management Project Scope Management Project Human Resource Management Question 3 (1 point) Units of measure, level of precision, level of accuracy, control thresholds,...
Which of the following documents discusses how requirements activities will be planned, tracked and changed? a. WBS b. Requirements management plan c. Change control plan d. Scope management plan You are developing the project charter. You should consider all of the following as inputs in the Develop Charter process EXCEPT: a. Enterprise Environmental Factors b. Business Case c. Project Management Plan d. Project Statement of Work Your initial list of identified risks will generally have all of the following information...
(TCO 2) You are a project manager for a new hardware/software project. You just received the project charter and established your scope statement. Within the scope statement, you defined some of the key components to meet the overall project objective. Establishing requirements will be critical to define and get approved. The hardware will be new for your company, so you will need to ensure the vendor is selected and the hardware is appropriately installed into your environment. The supporting software...
You were offered an opportunity to work as a project manager at one of these institutions: • AUST Hotel Dicu Red Cross • Dar Al Aytam You first task is to come up with the idea of a project that hasn't been already done by your institution Write a SOW or a project charter for your project. This must include but not limited to: Detailed project goals, objectives, requirements, characteristics, project product deliverables, assumptions, and constraints. Assignment Instructions: Work Breakdown...
Project Management Processes Assignment Part I by answering the assigned questions. Part II by completing the matching exercise. Part III by answering true or false to the questions. Part I – Answer the following questions (30 points): 1. Why aren’t the processes groups the same as project phases? (15 points) 2. After “create WBS” on a project what would be the next five sequences to follow? (15 points) Part II – Matching Exercise (20 Points): Match column A with B: (2...
Assignment Details Scenario You have been asked to be the project manager for the development of an information technology (IT) project. The system to be developed will allow a large company to coordinate and maintain records of the professional development of its employees. The company has over 30,000 employees who are located in four sites: Florida, Colorado, Illinois, and Texas. The system needs to allow employees to locate and schedule professional development activities that are relevant to their positions. Sophisticated...
1) "Once you have identified all of the stakeholders, it is important to determine which group of stakeholders holds the most power and which group may have the greatest impact in the overall outcome of the project. " a) true b) false 2) You are leading an international team and you are considering how this might impact your communications and decision making processes as a team. Your goal is to _______________. a) adapt the work processes to cope with the...
!!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a project plan showing each task. Assume you are a project manager to lead your team to acquire an additional delivery van for the company. Please find the details below. The current month is January. Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?)...
Project Description: Student groups will select an industrial project to be developed throughout the semester. Students groups will select an appropriate project and define measurable project objectives and requirements. A project plan and schedule will be generated as well as resources allocated to accomplish project objectives. Prepare a group project for the class. Use as your model one of the following Construction project Software development project Events management project ( e.g. Awards banquet) New product development Project Components: Using the...
The project team you are working with is doing the work of obtaining formal stakeholders’ acceptance of the completed project and associated deliverables. Each deliverable is reviewed to check that it has been completed satisfactorily. What is this process called? A. Validate Scope B. Define Scope C. Control Scope D. Plan Scope Management