Question

Which of the following documents discusses how requirements activities will be planned, tracked and changed? a....

Which of the following documents discusses how requirements activities will be planned, tracked and changed?

a. WBS

b. Requirements management plan

c. Change control plan

d. Scope management plan

You are developing the project charter. You should consider all of the following as inputs in the Develop Charter process EXCEPT:

a. Enterprise Environmental Factors

b. Business Case

c. Project Management Plan

d. Project Statement of Work

Your initial list of identified risks will generally have all of the following information on it EXCEPT:

a. Probability

b. Event

c. Consequence

d. Cause

You are managing a construction project. Your team took a sample of wet concrete and sent it to the laboratory for testing the quality. Which project management process is your team performing?

a. Control quality

b. Perform quality sampling

c. Perform quality inspection

d. Perform quality assurance

0 0
Add a comment Improve this question Transcribed image text
Answer #1
  1. Which of the following documents discusses how requirements activities will be planned, tracked and changed?

Ans: b. Requirements management plan

Analysis: The requirements activities will be planned , tracked and changed cn be properly discussed under the segment of requirements management plan. It properly discusses stakeholders requirements, scope management process and change control plan.

  1. You are developing the project charter. You should consider all of the following as inputs in the Develop Charter process EXCEPT:

Ans: c. Project Management Plan.

Analysis: The project charter includes project statement of work, business case, agreements, enterprise environmental factors and organizational process assets. The project management plan is not included in charter process.

  1. Your initial list of identified risks will generally have all of the following information on it EXCEPT:

Ans: b. Event.

Analysis: An identified risk analyses the risk probability, risk consequence and cause of the risk. However, the risk event is not a part of initial list of identified risk.

  1. You are managing a construction project. Your team took a sample of wet concrete and sent it to the laboratory for testing the quality. Which project management process is your team performing?

Ans: c. Perform quality inspection.

Analysis: Only the perform quality inspection tests the quality of the sample at the laboratory. Thus, option ‘b’ should be the answer.

Add a comment
Know the answer?
Add Answer to:
Which of the following documents discusses how requirements activities will be planned, tracked and changed? a....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Someone on your team is skeptical that the project is following the project's original requirements. Which...

    Someone on your team is skeptical that the project is following the project's original requirements. Which document will you refer to in order to convince him/her that the project is indeed following the original requirements? a. Project Management Plan b. Project Scope Statement c. Project Charter d. Work Breakdown Structure

  • You are the project manager for a power plant project. You have completed project initiation activities...

    You are the project manager for a power plant project. You have completed project initiation activities and you are now creating a document that describes processes to document the scope, decompose deliverables into work packages, verify that all work is complete and manage changes to the baseline. What process plan would you choose to perform? A. Develop project management plan B. Develop project management life cycle C. Develop WBS and define scope D. Develop project charter

  • The Collect Requirements Process tools & techniques include: a. Expert Judgement b. Decision Making c. Prototypes...

    The Collect Requirements Process tools & techniques include: a. Expert Judgement b. Decision Making c. Prototypes d. All of the above Inputs for the Validate Scope process include: a. Verified Deliverables b. Environmental Enterprise Factors c. Organizational Process Assets d. All of the above In the Project Scope Management Knowledge Area Enterprise Environmental Factors are inputs for which of the following process(es): a. Plan Scope Management b. Create WBS c. Define Scope d. All of the above

  • QUESTION 4 Match the process with the appropriate definition.    The process of identifying quality requirements...

    QUESTION 4 Match the process with the appropriate definition.    The process of identifying quality requirements and /or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards.    The process of translating the quality management plan into executable quality activities that incorporate the organization's quality policies into the project.    The process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well...

  • Question #12 On agile projects, the scope definition begins with: A-Requirements B-large chunks of work, or...

    Question #12 On agile projects, the scope definition begins with: A-Requirements B-large chunks of work, or features C-work packages D: stories and personas Question# 13 Which of the following is an advantage associated with managing projects in a functional organization? A-Traditional department barriers are reduced. B-Combines task focus with technical capability. C- Rapid communication between the various functions working on the project. D-Rapid communication between the various functions working on the project. Question #14 A project communications plan generally includes...

  • Question 1 (1 point) The project scope statement and resource calendars are inputs to which Project...

    Question 1 (1 point) The project scope statement and resource calendars are inputs to which Project Time Management process? Question 1 options: Sequence Activities Estimate Activity Resources Develop Schedule Control Schedule Question 2 (1 point) Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area? Question 2 options: Project Time Management Project Cost Management Project Scope Management Project Human Resource Management Question 3 (1 point) Units of measure, level of precision, level of accuracy, control thresholds,...

  • Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project ...

    Table 1.1 Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project Management Process Group and Knowledge Area Mapping (PMBOK Guide® on page 556) provides you with a very specific guideline concerning what task is due for each knowledge area throughout the five projec management process groups. As you can determine from Table 1-1, a large majority of the tasks are complete during the planning process group Describe and explain how sound industry standards or best practices...

  • QUESTION 8 Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements...

    QUESTION 8 Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. All of the following are true about this process EXCEPT: A. The project's success is directly influenced by active stakeholder involvement in the discovery and decomposition of needs into requirements and by the care taken in determining, documenting, and managing the requirements of the product, service, or result of the project. b. Requirements become the foundation of the Wes. Cost,...

  • Good Morning. this is a quality management questions. Can someone help me with answer to the...

    Good Morning. this is a quality management questions. Can someone help me with answer to the below questions today. Thank you. Case 4- TBSM Quality Management Plan Please review the TBSM template and respond to the following: 1- Compare Project Quality Planning as defined in PMBOK with the process described in this template; --The Quality Management Plan documents the necessary information required to effectively manage project quality from project planning to delivery. It defines a project’s quality policies, procedures, criteria...

  • 1 Which of the following is true regarding the code of accounts? a It allows one...

    1 Which of the following is true regarding the code of accounts? a It allows one to easily identify the breakdown level of the item in the resource structure. b It describes the coding structure used by the performing organization to report financial information in its general ledger. c It is the collection of unique identifiers generally assigned to WBS items. d It defines ethical behavior in the project and the responsibilities to the customer and the profession. 2 You...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT