Te = (To+4*Tp+Tm)/6
Variance = [( Tm-To)/6]2
| Activity | To | Tm | Tp | Te | Sigma | Sigma^2 |
| A | 5 | 8 | 11 | 8 | 1 | 1 |
| B | 4 | 9 | 14 | 9 | 1.666667 | 2.777778 |
| C | 5 | 7 | 9 | 7 | 0.666667 | 0.444444 |
| D | 2 | 4 | 12 | 5 | 1.666667 | 2.777778 |
| E | 4 | 7 | 10 | 7 | 1 | 1 |
The critical path is ADE with expected project duration of 20 days
SD of critical path = ( 1+ 2.777+1)1/2 =2.185
Probability of completing the project in 21 days
z = x ( days in case) - mu ( avg completion time) / SD of critical path
z = 21-20 /2.185 = 0.4576
which corresponds to probability of 0.675
Probability of completing the project in 18 days
z = 18-20/2.185 = -0.9153
which corresponds to probability of 0.1814.
Show all Calculations Question 1 (50 points). You were recently assigned to manage a project for...
Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: ơ Time Estimates (days) Optimistic Most Likely Pessimistic Activity ơ ال 7 کره ) | Start Finish 6 ای یا...
H m Problem 21 Question Help Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Most Likely Activity Optimistic Pessimistic A 4 8 12 5 12...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...
Must use AOA PERT/CPM
Manual Calculations and show Networks.
10. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table: Activity Activity Activity Activity Description Predecessor Time Excavate Erect building Install generator Install tank Install maintenance equipment Connect generator and tank to building b.c,d Paint finish Η Check out facility Construct the network for this project and calculate the...
The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations. a. Using the data in the table, calculate the expected time (ET) and variance for each activity. Job number Predecessor Job(s) a m b expected time (ET) variance A --- 3 5 7 B A 3 4 5 C A 2 3 4 D B 3 4 11 E B,C 4 9 14 F D, E 6 8 10...
The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations. a. Using the data in the table, calculate the expected time (ET) and variance for each activity. Job Predecessor mi expected variance number Job(s) time (ET) --- 468 B A 3 4 5 CIA 234|| D C 34 11 E B, C 13 5 D, E 2 46 F b. [Sketch the network diagram for the project on a...
You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...
1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following diagram. Optimistic, most likely, and pessimistic time estimates are displayed in the following table. Figure for Problem 1. r e 14 16 E 4 H 4 7 11 7 11 16 20 G 5 0 33 611 16 11 16 D 3 Most Likely Pessimistic Activity Optimistic 4 4 (a) Determine the expected times and variances for each activity along the critical...