The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations.
a. Using the data in the table, calculate the expected time (ET) and variance for each activity.
| Job number | Predecessor Job(s) | a | m | b | expected time (ET) | variance |
|---|---|---|---|---|---|---|
| A | --- | 3 | 5 | 7 | ||
| B | A | 3 | 4 | 5 | ||
| C | A | 2 | 3 | 4 | ||
| D | B | 3 | 4 | 11 | ||
| E | B,C | 4 | 9 | 14 | ||
| F | D, E | 6 | 8 | 10 |
b. [Sketch the network diagram for the project on a sheet of paper. YOU DO NOT HAVE TO SUBMIT THE SKETCH].
c. List each unique path through the network. For example, "A, B, C" would indicate a path consisting of activity A, followed by activity B, which is followed by activity C.
d. Indicate the critical path. (You can do this by inspecting the paths -- you do not have to calculate ES, EF, LS, LF.) What is the expected completion time for the project?
e. What is the probability that the project will be completed in 29 days or less?
f. What is the probability that the project will take more than 29 days to complete?
The following table represents the set of activities required to complete a project, along with their...
The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations. a. Using the data in the table, calculate the expected time (ET) and variance for each activity. Job Predecessor mi expected variance number Job(s) time (ET) --- 468 B A 3 4 5 CIA 234|| D C 34 11 E B, C 13 5 D, E 2 46 F b. [Sketch the network diagram for the project on a...
The activities required to service a car at Zippy-Lube can be viewed as a mini-project as summarized in the following table. Time Required Expected Activity Description Predecessor Min Avg Max Time Variance A Drain Oil -- 2 3.5 5 B Replace Filter A 1 2 3 C Refill Oil B, E 1 2.5 4 D Check Tires -- 2 3 4 E Wash Windows D 2 3 5 F Fill Fluids E 2 3 4 G Final Test C, F...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
project are listed for a In the following table the activities with their precedence sequence and expected time (days) Immediate Predecessor(s) Time (days) Activity 7 A 2 A B 4 C 4 5 5 E C F 2 G E, F 3 H G, H a) The activities on the critical path are b) The project length is days.
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 – 2 4 9 2 1 2 2 11 3 1 2 4 6 4 1 3 7 8 5 2 2 3 4 6 3 1 2 6 7 4 3 5 10 8 5,6 1 3 5 9 8 1 2 12 10 7 3 4 5 11 9,10 1 5 6 b. Indicate the critical path. 1-2-5-8-9-11...
Consider the following network for a small maintenance project (all times are in days). [7 Marks] Activity Immediate Predecessor [s] Optimistic Time Most Likely Time Pessimistic Time A - 2 3 4 B - 5 6 7 C - 5 6 7 D A 3 4 5 E A 2 3 4 F C 3 4 5 G C 8 10 16 H B, E, F 5 6 7 I B, E, F 7 11 15 J B, E,...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...