ACTIVITY | IMMEDIATE PREDECESSORS | OPTIMISTIC TIME | MOST LIKELY TIME | PRESSMISTIC TIME |
A | - | 1 | 2 | 4 |
B | - | 3 | 3.5 | 4 |
C | - | 10 | 12 | 12 |
D | - | 4 | 5 | 7 |
E | - | 2 | 4 | 5 |
F | A | 6 | 7 | 8 |
G | B | 2 | 4 | 5.5 |
H | C | 5 | 7.7 | 9 |
I | C | 9.9 | 10 | 12 |
J | C | 2 | 4 | 5 |
K | D | 2 | 4 | 6 |
L | E | 2 | 4 | 6 |
M | F,G,H | 5 | 6 | 6.5 |
N | J,K,L | 1 | 1.1 | 2 |
O | I,M | 5 | 7 | 8 |
P | N | 5 | 7 | 9 |
Q1.draw an activity network diagram showing es, ef, ls and lm?
Q2.calculate estimated time t and variance for each activity?
Q3 .calculate the project completion time and project variance?
Q4.determine the number of paths associated with the network diagram?
Q5.find out the critical path?
Q5.you as a manager would like to determine the project completion time, so what is the probability of this project being done in 63 days.?
Q6.what date results in a 99% probability of completion?
Step 1:
Completion Time(t) = (a+4m+b)/6
| Activity | Immediate Predecessor | Completion Time (t) in Weeks |
| A | 12 | |
| B | 10 | |
| C | 5 | |
| D | A | 8 |
| E | B | 3 |
| F | C | 4 |
| G | C | 4 |
| H | A,E,F | 8 |
| I | A,E,F | 10 |
| J | D | 8 |
| K | G,H,I | 6 |

So Activities on the critical path are- B-E-I-K.
Expected Duration of the project is =10+3+10+6 = 26 weeks
Step 2:
Completion Time(t) = (a+4m+b)/6
Standard Deviation (σ) = (b-a)/6
Variance (σ^2) = (σ)^2
Slack = LS-ES (or) LF-EF
| Activity | Immediate Predecessor | Optimistic (a) | Most Likely (m) | Pessimistic (b) | Completion Time (t) | Standard Deviation (σ) | Variance (σ^2) | ES | EF | LS | LF | Slack | CP Variance |
| A | 6 | 12 | 18 | 12 | 2.00 | 4.00 | 0 | 12 | 1 | 13 | 1 | ||
| B | 5 | 10 | 15 | 10 | 1.67 | 2.78 | 0 | 10 | 0 | 10 | 0 | 2.78 | |
| C | 2 | 5 | 8 | 5 | 1.00 | 1.00 | 0 | 5 | 4 | 9 | 4 | ||
| D | A | 2 | 8 | 14 | 8 | 2.00 | 4.00 | 12 | 20 | 13 | 21 | 1 | |
| E | B | 2 | 3 | 4 | 3 | 0.33 | 0.11 | 10 | 13 | 10 | 13 | 0 | 0.11 |
| F | C | 3 | 4 | 5 | 4 | 0.33 | 0.11 | 5 | 9 | 9 | 13 | 4 | |
| G | C | 2 | 4 | 6 | 4 | 0.67 | 0.44 | 5 | 9 | 19 | 23 | 14 | |
| H | A,E,F | 3 | 8 | 13 | 8 | 1.67 | 2.78 | 13 | 21 | 15 | 23 | 2 | |
| I | A,E,F | 2 | 10 | 18 | 10 | 2.67 | 7.11 | 13 | 23 | 13 | 23 | 0 | 7.11 |
| J | D | 2 | 8 | 14 | 8 | 2.00 | 4.00 | 20 | 28 | 21 | 29 | 1 | |
| K | G,H,I | 2 | 6 | 10 | 6 | 1.33 | 1.78 | 23 | 29 | 23 | 29 | 0 | 1.78 |
| Summed Variance | 11.78 | ||||||||||||
| Project Standard Deviation | 3.43 |
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....
Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
Consider the following network for a small maintenance project (all times are in days). [7 Marks] Activity Immediate Predecessor [s] Optimistic Time Most Likely Time Pessimistic Time A - 2 3 4 B - 5 6 7 C - 5 6 7 D A 3 4 5 E A 2 3 4 F C 3 4 5 G C 8 10 16 H B, E, F 5 6 7 I B, E, F 7 11 15 J B, E,...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
activity preceding optimistic probability pessimistic a -- 7 9 14 b a 2 2 8 c a 8 12 16 d a 3 5 10 e b 4 6 8 f b 6 8 10 g c,f 2 3 4 h d 2 2 8 i h 6 8 16 j g,i 4 6 14 k e,j 2 2 5 a. What is the estimated time of completing the project if the critical path is A-D-H-I-J-K? b. calculate the project...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...
Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8...