Question

2. Given the table below (10 pts): A. Draw the project network B. Calculate the expected time to complete each activity as we
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity To Tm Tp Te (Var)^0.5 Var
A 3 4 11 5 1.333333 1.777778
B 2 5 8 5 1 1
C 3 6 9 6 1 1
D 8 12 20 12.66667 2 4
E 3 5 12 5.833333 1.5 2.25
F 2 4 7 4.166667 0.833333 0.694444
G 6 9 14 9.333333 1.333333 1.777778
H 1 2 4 2.166667 0.5 0.25

2:Ь ЧТЬ

The possible paths are

ABEH with duration 17.99

ABDFH with duration 28.98

ACDFH with duration 29.98

ACGH with duration 22.49

The critical path is ACDFH with duration 29.98.

Variance of the CP =7,7221

SD of the CP = (7721)^0.5 =2.778

Probability that the project will be completed within 30 days

z = 30-29.98 /2.778 =0.0071

which gives a probability of 50%

Prob. of completing in 35 days

z = 35-29.98 /2.778 =1.807

which gives a probability of 0.9645

Note : As per Chegg policies I can answer the first four questions only. Inconvenience is regretted.

Add a comment
Know the answer?
Add Answer to:
2. Given the table below (10 pts): A. Draw the project network B. Calculate the expected...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For the activities given in the table: Draw the AOA network diagram Find the critical activities...

    For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...

  • Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A...

    Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...

  • Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m...

    Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...

  • Question 2 (50%): The project information is presented in Table 1. It is known that the...

    Question 2 (50%): The project information is presented in Table 1. It is known that the critical path of the given project is A - D + G - J. 1) Please fill out the Table 2. (1% * 10-10%) 2) The duration of the project is days (10%) Note: Calculation processes for 1) and 2) are not required. 3) What is the probability of finishing the project in 18 days? (15%) 4) What is the probability of finishing the...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • Question 1. Activities and activity durations of a Project is given below. (10 points) Find the...

    Question 1. Activities and activity durations of a Project is given below. (10 points) Find the probability of completing the Projcct in 50 weeks b. (10 points) Find the probability of completing the Project in 20 weeks. (10 points) Find the probability of completing the Project in 58 weeks. d. (10 points) Find the probability of completing the Project in 90 weeks. Most Pessimistic Time (weeks) 6 Most Optimistic Time (weeks) Most Probable Previous Activity 2 Activity Time (weeks) 4...

  • 1. When finding the approximate probability of project duration, it is necessary to know which of...

    1. When finding the approximate probability of project duration, it is necessary to know which of following? a. The mean and variance of each activity b. The mean of each activity on the CP c. The sd of only the activities on the CP d. Each activity's probability of completion e. The distribution of activity times 2. The sd of a path is computed as: a. the sum of the sd of all activities on the path b. the square...

  • 301247/mod_resource/content/B/Exam%202%20March%202020.pdf - + Fit to page Question 2) Use the table diagram below to answer the...

    301247/mod_resource/content/B/Exam%202%20March%202020.pdf - + Fit to page Question 2) Use the table diagram below to answer the following questions? (20 Points) Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start Precedes AB CD 56 D F F End a) Draw the project network? (5 Points) b) What is the expected duration and standard deviation for each activity? (5 Points) c) What is (are) the project critical path(s); duration(s); and standard deviation (s)? (5 Points) d) What's the probability that the critical...

  • Consider the following network for a small maintenance project (all times are in days). [7 Marks]...

    Consider the following network for a small maintenance project (all times are in days). [7 Marks] Activity Immediate Predecessor [s] Optimistic Time Most Likely Time Pessimistic Time A - 2 3 4              B - 5 6 7 C - 5 6 7 D A 3 4 5 E A 2 3 4 F C 3 4 5 G C 8 10 16 H B, E, F 5 6 7 I B, E, F 7 11 15 J B, E,...

  • 2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10...

    2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10 8 K 9 8 7 L 10 6 5 M 3 3 3 N KM 9 5 1 O KM 10 7 4 P LN 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT