
Normal Time = 13
Total Direct Cost =1000
1)
Time = 12
Total Direct Cost =1050
Activities Changed: C
2)
Time = 11
Total Direct Cost =1120
Activities Changed: E
3)
Time = 10
Total Direct Cost =1210
Activities Changed: F
4)
Time = 9
Total Direct Cost =1340
Activities Changed: D, E
Use the information below to compress one-time unit per move using the least cost method. Reduce...
Use the information contained
below to compress one time unit per move using the least cost
method. Reduce the schedule until you reach the crash point of the
network. For each move identify what activity(ies) was crashed and
the adjusted total cost. (i.e., Calculate the minimum direct cost
when project is finished in 13 days, 12 days, 11 days, as well as
10 days.)
Note: Choose B instead of C
and E (equal costs) because it is usually smarter to...
Use the information contained
below to compress one time unit per move using the least cost
method. Reduce the schedule until you reach the crash point of the
network. For each move identify what activity(ies) was crashed and
the adjusted total cost. (i.e., Calculate the minimum direct cost
when project is finished in 13 days, 12 days, 11 days, as well as
10 days.)Note: Choose B instead of C
and E (equal costs) because it is usually smarter to crash...
Chapter 9 Reducing Project Durarion 327 7. Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $2.000 and there is a savings of $100 per time unit reduced. Calculate the total direct, indirect, an graph. What is the optimum cost-time schedule for the project? Note: The correct normal project duration and total direct cost are provi ded. Normal Cost 200 1000 800 1000...
Assume the network and data that follow: ACTIVITY NORMAL TIME (WEEKS) NORMAL COST CRASH TIME (WEEKS) CRASH COST IMMEDIATE PREDECESSORS A 3 $ 60 2 $ 80 — B 5 70 4 110 A C 9 50 6 80 A D 7 100 6 130 A E 8 90 6 100 B F 5 30 3 50 D G 6 110 5 190 C, E, F b. Indicate the critical path when normal activity times are used. A-B-E-G A-C-F-G A-D-E-G...
Assume that Indirect project costs are $75,000 per week Crash
the network (one week at a time) until you reach the optimum
cost-time point. Document your crashes clearly. d. What is the
project length at the optimum point?
MGMT 4143 Ch 9 HomeworkDue 3/27, 9pm NOTE due date is changed All work must be done in Excel Put each problem on a separate worksheet tab Label the worksheet tabs, put your name on each worksheet. Note: Crash the networks as...
A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 А B с D E 7 3 6 3 2 $300 $250 $400 $200 $300 4 2 1 ive the crash cost per day per activity. (5 points) Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the network diagram below and the additional information provided to answer the corresponding questions. (10 points) B E...
Problem #3 (25 points) For the construction project whose network diagram is shown below, a time-cost optimization procedure is required to determine the shortest duration and its corresponding lowest cost. Activity ID ES Darwin EF LS UF 1. Fill in values for the normal cost and crashed cost in the table below. Activities A and B already have costs associated with them. For activities through I do not use the same costs for any activity 2. Calculate the slope and...
Question 16 4 points Save Answe The following provides information about a project, including a list of activities and precedence relationships, activity durations (normal and "crash" times), direct activity costs (normal and "crash"), indirect costs for the project, as well as calculated crash costs/day and the maximum amount that each activity can be shortened (crashed) by. There are no penalty costs for this project. Total project cost (using normal times), a network diagram, and the four paths and durations have...
5. Imagine that you are in charge of planning a short course for executives wishing to upgrade their Operations Research skills. The following list of activities is involved: Cost Per ImmediateNormal DescriptionPredecessors (days) Crash Time (days)Reduction Day of Time Activity A Develop course outline 4 S50 Arrange speakers $100 Identify potential locations $150 Choose location 4 $150 Arrange travel for B, D speakers Final confirmation of $200 eakers Advertise course B, D Take rescrvations Arrange welcome party F, H $100...
15. Given the following project (all times are in days): Pre- Normal Normal Crash Crash Activity decessor Time Cost Time Cost $50 200 160 a, c a, c 290 100 180 (a) Draw the network and find the critical path, time, and (b) Calculate the crash cost-per-day (all activities may be (c) Find the optimal way of getting an 18-day delivery (d) Find the optimal way of getting a 16-day delivery (e) Calculate the shortest delivery time for the project....