1. General Foundry, Inc., a metal works plant in Milwaukee, has long been trying to avoid the expense of installing air pollution control equipment. The local environment protection group has recently given the foundry 16 weeks to install a complex air filter system on its main smokestack. General Foundry has been warned that it may be forced to close unless the device installed in the allotted period. Lester Harky, the managing partner, wants to make sure that installation of the filtering system progressed smoothly and on time. General Foundry has identified the following eight activities that need to be performed and their sequential relationship.
a. Construct the appropriate network diagram. (10 points)
b. Which jobs can be delayed without delaying the project completion time? (10 points)
c. Can General Foundry complete the project on time? Why or why not? (20 points)
d. Suppose Lester wants to shorten the completion time and his options are:
(1) Reduce activity time of D by one week, which costs $700/week;
(2) Reduce activity time of E by one week, which costs $800/week;
(3) Reduce activity time of G by one week, which costs $1000/week;
If General Foundry will save $2000 for each week that the earliest completion time is reduced, which single option, if any, should Lester choose? And why? (10 points)
| Activity | Description | Time | Immediate |
| (weeks) | Predecessors | ||
| A | Build internal components | 2 | -- |
| B | Modify roof and floor | 4 | -- |
| C | Construct collection stack | 2 | A |
| D | Pour concrete and install frame | 4 | A, B |
| E | Build high-temperature burner | 4 | C |
| F | Install pollution control system | 3 | C |
| G | Install air pollution device | 7 | D, E |
| H | Inspect and test | 2 | F, G |
(a)

(b)
| Project paths | Duration |
| A-C-F-H | 9 |
| A-C-E-G-H | 17 |
| A-D-G-H | 15 |
| B-D-G-H | 17 |
So, the critical paths are A-C-E-G-H and B-D-G-H and the critical activities are A, B, C, D, E, G, and H.
So, 'F' is the only non-critical activity that can be delayed without delaying the project.
(c)
Project completion time = Duration of the critical paths = 17 weeks.
So, there will be a delay of 1 week.
(d)
As mentioned earlier, there are two critical paths - A-C-E-G-H and B-D-G-H.
If we want to reduce the project duration, we have to reduce the length of both the critical paths simultaneously. This is possible by reducing G or H.
So, given the alternatives, (3) should be chosen.
1. General Foundry, Inc., a metal works plant in Milwaukee, has long been trying to avoid...
Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing...
A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened. Activity Precedes Normal Time. (week) Crashing Costs ($000) 1st...
HOMEWORK ASSIGNMENT FOR PROJECT MANAGEMENT 13. An automation project has the following activities and related data Time (weeks)Crash Immed. Maximum Activity Prede- Opti- Most Cost/week Crashable Mean Varice cessors mistic (a) Likely (m) mistic (c (S1000) Weeks E(t) V(t) C A 5 D A 4 E B1 F B1 G C,D,E 2 6 6 HF2 12 15 3 13a. (5 points) Compute the mean and variance of each activity and record them on the table above. 13b. (5 points) Develop...
Dr. Thomas has been given a budget of $10,000 to organize a conference at her university in 3 months’ time (12 weeks) via an educational grant. She has a team of 2 research assistants and after some deliberation, they identified the following activities that are required to be completed for hosting a successful conference. Activity Description Immediate Predecessor A Planning Topics and Sessions . . B Inviting presenters from various universities A C identifying potential venues...
The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions. Hospital Expansion Project Activity Description Immediate predecessor(s) Activity Time (Weeks) A Select administrative and medical staff - 12 B Select site and do site survey - 9 C Select equipment A 10 D Prepare final...
Use the following information for questions 1 to 10. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...
You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...
Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...
You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...
Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...