Seven tasks are to be performed on two work stations. Drilling and painting. Task times are given below .
|
FIRST STATION DRILING |
SECOND STATION PAINTING |
|
|
A |
18 |
10 |
|
N |
16 |
13 |
|
C |
2 |
7 |
|
D |
10 |
16 |
|
E |
13 |
20 |
|
F |
14 |
4 |
|
G |
7 |
7 |
In which order would you perform these task? Explain your work:
Use Johnson's rule to find the sequence of jobs for minimum makespan.
The minimum processing time is 2, for C, on Drilling. Schedule C
the earliest. C, _, _, _, _, _, _
The next minimum processing time is 4, for F, on Painting. Schedule
F the latest. C, _, _, _, _, _, F
The next minimum processing time is 7, for G, on Drilling. Schedule
G the earliest. C, G, _, _, _, _, F
The next minimum processing time is 10, for A, on Painting.
Schedule A the latest. C, G, _, _, _, A, F
The next minimum processing time is 10, for D, on Drilling.
Schedule A the earliest. C, G, D, _, _, A, F
The next minimum processing time is 13, for E, on Drilling.
Schedule A the earliest. C, G, D, E, _, A, F
So,
the final optimal sequence is C, G, D, E, B, A, F
Gantt chart

The minimum makespan in 84
Seven tasks are to be performed on two work stations. Drilling and painting. Task times are...
OPERATIONS AND SUPPLY CHAIN MANAGEMENT L06-4 SOLVED PROBLEM 2 TASKS THAT MUST PRECEDE TASK TIME (SECONDS) 50 TASK A B С D E F G H 40 20 45 20 25 10 35 A С С D E B, F, G a. Draw the schematic diagram. b. What is the theoretical minimum number of stations required to meet a forecast demand ei 400 units per eight-hour day? c. Use the longest-task-time rule and balance the line in the minimum number...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) The minimum cycle...
The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...
1. Consider the following table providing the needed tasks to completing a successful project. The first column provides the name of the task, the second column states the time to complete that task and the third column tells when a task can begin. Task Time to Condition to start task complete #1 #2 #3 #4 #5 #6 #7 #8 #9 #10 #11 #12 #13 #14 #15 #16 #17 #18 #19 7 days None 5 days 8 daysNone 4 days 3...
Consider the following project, all durations are in days. Find the critical path and which tasks have slack. What is the probability the project will be done in 50 days? How about in 53 days? Suppose any task can be crashed for up to two days for the same cost per day, but that tasks A and N cannot be crashed at all. Which tasks should be crashed if the project needed to be completed in 45 days with at...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) I have not been...
3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time(secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d,e g 38 f For output to equal forecasted demand, what will be the second...
Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers performing these tasks seven times, with the results (in minutes) shown in the following table. No Tasks 1 2 3 4 5 6 7 PR 1 Select correct mufflers 5 4 6 3 4 5 5 120 2 Remove old muffler 8 8 8 6 8 7 6 85 3 Install new muffler 15 13 15 14 12 15 13 85 4 Inspect the...
Question 6 (1 point) Hypothesis Test. Ten pilots performed crisis problem-solving tasks with response time measured in seconds. Each pilot first performed the tasks in a completely sober condition and, 3 hours later, repeated similar tasks after consuming two servings of alcohol. Evaluate whether alcohol has negative effects on performance le-g. times to perform critical tasks increase at the 0.05 level of significance. The data are given below. She 25 53 15 18 28 10 10 10 2 lime 2030...